Earned Value Cost
Field Reference
Earned value cost is a calculated value describing money earned from an activity. The value is calculated by the formula: Earned Value Cost = Earned Work Cost + Earned Fixed Cost On the summary level the value is calculated as sum of the Earned Work Cost and Earned Fixed Cost values.
Earned Value Work
Field Reference
Earned Value Work is the value describing work (in hours) from an activity. The value is calculated by the formula: Earned Value Work = Current Work * % complete, or Earned Value Work = Baseline Work* % complete depending on selected Calculate Earned Values based on project option.
Earned Work Cost
Field Reference
Earned work cost is the value that is calculated by the formula: Earned Work Cost = Current Work Cost * % complete, or Earned Work Cost = Baseline Work Cost * % complete depending on selected Calculate Earned Values based on project option. On the summary level the value is calculated as sum of the lower-level Earn...
Expended Work
Field Reference
Expended work is the hours registered in the timesheet. This field is available in Reporting module.