f06250e | 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163 164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183 184 185 186 187 188 189 190 191 192 193 194 195 196 197 198 199 200 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215 216 217 218 219 220 221 222 223 224 225 226 227 228 229 230 231 232 233 234 235 236 237 238 239 240 241 242 243 244 245 246 247 248 249 250 251 252 253 254 255 256 257 258 259 260 261 262 263 264 265 266 267 268 269 270 271 272 273 274 275 276 277 278 279 280 281 282 283 284 285 286 287 288 289 290 291 292 293 294 295 296 297 298 299 300 301 302 303 304 305 306 307 308 309 310 311 312 313 314 315 316 317 318 319 320 321 322 323 324 325 326 327 328 329 330 331 332 333 334 335 336 337 338 339 340 341 342 343 344 345 346 347 348 349 350 351 352 353 354 355 356 357 358 359 360 361 362 363 364 365 366 367 368 369 370 371 372 373 374 375 376 377 378 379 380 381 382 383 384 385 386 387 388 389 390 391 392 393 394 395 396 397 398 399 400 401 402 403 404 405 406 407 408 409 410 411 412 413 414 415 416 417 418 419 420 421 422 423 424 425 426 427 428 429 430 431 432 433 434 435 436 437 438 439 440 441 442 443 444 445 446 447 448 449 450 451 452 453 454 455 456 457 458 459 460 461 462 463 464 465 466 467 468 469 470 471 472 473 474 475 476 477 478 479 480 481 482 483 484 485 486 487 488 489 490 491 492 493 494 495 496 497 498 499 500 501 502 503 504 505 506 507 508 509 510 511 512 513 514 515 516 517 518 519 520 521 522 523 524 525 526 527 528 529 530 531 532 533 534 535 536 537 538 539 540 541 542 543 544 545 546 547 548 549 550 551 552 553 554 555 556 557 558 559 560 561 562 563 564 565 566 567 568 569 570 571 572 573 574 575 576 577 578 579 580 581 582 583 584 585 586 587 588 589 590 591 592 593 594 595 596 597 598 599 600 601 602 603 604 605 606 607 608 609 610 611 612 613 614 615 616 617 618 619 620 621 622 623 624 625 626 627 628 629 630 631 632 633 634 635 636 637 638 639 640 641 642 643 644 645 646 647 648 649 650 651 652 653 654 655 656 657 658 659 660 661 662 663 664 665 666 667 668 669 670 671 672 673 674 675 676 677 678 679 680 681 682 683 684 685 686 687 688 689 690 691 692 693 694 695 696 697 698 699 700 701 702 703 704 705 706 707 708 709 710 711 712 713 714 715 716 717 718 719 720 721 722 723 724 725 726 727 728 729 730 731 732 733 734 735 736 737 738 739 740 741 742 743 744 745 746 747 748 749 750 751 752 753 754 755 756 757 758 759 760 761 762 763 764 765 766 767 768 769 770 771 772 773 774 775 776 777 778 779 780 781 782 783 784 785 786 787 788 789 790 791 792 793 794 795 796 797 798 799 800 801 802 803 804 805 806 807 808 809 810 811 812 813 814 815 816 817 818 819 820 821 822 823 824 825 826 827 828 829 830 831 832 833 834 835 836 837 838 839 840 841 842 843 844 845 846 847 848 849 850 851 852 853 854 855 856 857 858 859 860 861 862 863 864 865 866 867 868 869 870 871 872 873 874 875 876 877 878 879 880 881 882 883 884 885 886 887 888 889 890 891 892 893 894 895 896 897 898 899 900 901 902 903 904 905 906 907 908 909 910 911 912 913 914 915 916 917 918 919 920 921 922 923 924 925 926 927 928 929 930 931 932 933 934 935 936 937 938 939 940 941 942 943 944 945 946 947 948 949 950 951 952 953 954 955 956 957 958 959 960 961 962 963 964 965 966 967 968 969 970 971 972 973 974 975 976 977 978 979 980 981 982 983 984 985 986 987 988 989 990 991 992 993 994 995 996 997 998 999 1000 1001 1002 1003 1004 1005 1006 1007 1008 1009 1010 1011 1012 1013 1014 1015 1016 1017 1018 1019 1020 1021 1022 1023 1024 1025 1026 1027 1028 1029 1030 1031 1032 1033 1034 1035 1036 1037 1038 1039 1040 1041 1042 1043 1044 1045 1046 1047 1048 1049 1050 1051 1052 1053 1054 1055 1056 1057 1058 1059 1060 1061 1062 1063 1064 1065 1066 1067 1068 1069 1070 1071 1072 1073 1074 1075 1076 1077 1078 1079 1080 1081 1082 1083 1084 1085 1086 1087 1088 1089 1090 1091 1092 1093 1094 1095 1096 1097 1098 1099 1100 1101 1102 1103 1104 1105 1106 1107 1108 1109 1110 1111 1112 1113 1114 1115 1116 1117 1118 1119 1120 1121 1122 1123 1124 1125 1126 1127 1128 1129 1130 1131 1132 1133 1134 1135 1136 1137 1138 1139 1140 1141 1142 1143 1144 1145 1146 1147 1148 1149 1150 1151 1152 1153 1154 1155 1156 1157 1158 1159 1160 1161 1162 1163 1164 1165 1166 1167 1168 1169 1170 1171 1172 1173 1174 1175 1176 1177 1178 1179 1180 1181 1182 1183 1184 1185 1186 1187 1188 1189 1190 1191 1192 1193 1194 1195 1196 1197 1198 1199 1200 1201 1202 1203 1204 1205 1206 1207 1208 1209 1210 1211 1212 1213 1214 1215 1216 1217 1218 1219 1220 1221 1222 1223 1224 1225 1226 1227 1228 1229 1230 1231 1232 1233 1234 1235 1236 1237 1238 1239 1240 1241 1242 1243 1244 1245 1246 1247 1248 1249 1250 1251 1252 1253 1254 1255 1256 1257 1258 1259 1260 1261 1262 1263 1264 1265 1266 1267 1268 1269 1270 1271 1272 1273 1274 1275 1276 1277 1278 1279 1280 1281 1282 1283 1284 1285 1286 1287 1288 1289 1290 1291 1292 1293 1294 1295 1296 1297 1298 1299 1300 1301 1302 1303 1304 1305 1306 1307 1308 1309 1310 1311 1312 1313 1314 1315 1316 1317 1318 1319 1320 1321 1322 1323 1324 1325 1326 1327 1328 1329 1330 1331 1332 1333 1334 1335 1336 1337 1338 1339 1340 1341 1342 1343 1344 1345 1346 1347 1348 1349 1350 1351 1352 1353 1354 1355 1356 1357 1358 1359 1360 1361 1362 1363 1364 1365 1366 1367 1368 1369 1370 1371 1372 1373 1374 1375 1376 1377 1378 1379 1380 1381 1382 1383 1384 1385 1386 1387 1388 1389 1390 1391 1392 1393 1394 1395 1396 1397 1398 1399 1400 1401 1402 1403 1404 1405 1406 1407 1408 1409 1410 1411 1412 1413 1414 1415 1416 1417 1418 1419 1420 1421 1422 1423 1424 1425 1426 1427 1428 1429 1430 1431 1432 1433 1434 1435 1436 1437 1438 1439 1440 1441 1442 1443 1444 1445 1446 1447 1448 1449 1450 1451 1452 1453 1454 1455 1456 1457 1458 1459 1460 1461 1462 1463 1464 1465 1466 1467 1468 1469 1470 1471 1472 1473 1474 1475 1476 1477 1478 1479 1480 1481 1482 1483 1484 1485 1486 1487 1488 1489 1490 1491 1492 1493 1494 1495 1496 1497 1498 1499 1500 1501 1502 1503 1504 1505 1506 1507 1508 1509 1510 1511 1512 1513 1514 1515 1516 1517 1518 1519 1520 1521 1522 1523 1524 1525 1526 1527 1528 1529 1530 1531 1532 1533 1534 1535 1536 1537 1538 1539 1540 1541 1542 1543 1544 1545 1546 1547 1548 1549 1550 1551 1552 1553 1554 1555 1556 1557 1558 1559 1560 1561 | ## Page 1
FORMWORK
A STUDY OF ITS VARIOUS TYPES, MATERIALS AND
CONSTRUCTION TECHNIQUES
|
}
---
## Page 2
INTRODUCTION TO FORMWORK
What is Formwork?
Formwork in construction is the use of support structures and
moulds to create structures out of concrete which is poured
into the moulds. Formwork can be made using moulds out of
steel, wood, aluminium and/or prefabricated forms.
Formwork is an ancillary construction, used as a mould for a
structure. Into this mould, fresh concrete is placed only to
hgfden subsequently.
The construction of formwork takes time and involves
expenditure up to 20 to 25% of the cost of the structure or
even more.
The operation of removing the formwork is known as stripping.
Stripped formwork can be reused. Reusable forms are known
as panel forms and non-usable are called stationary forms.
Formwork is designed according to The ACI document SP-4.
---
## Page 3
A good formwork should satisfy the following requirements:
Strong enough to withstand all types of dead and live loads
Rigidly constructed and efficiently propped and braced both horizontally and vertically, so as to
retain its shape
The joints in the formwork should be tight against leakage of cement grout
Construction of formwork should permit removal of various parts in desired sequences without
damage fo the concrete
Material of the formwork should be cheap, easily available and should be suitable for reuse
The formwork should be set accurately to the desired line and levels should have plane surface.
AS light as possible
Material of the formwork should not warp or get distorted when exposed to the elements
Should rest on firm base
The following points are to be kept in view to effect economy in the cost of formwork:
The plan of the building should imply minimum number of variations in the size of rooms, floor area
etc. so as to permit reuse of the formwork repeatedly.
Design should be perfect to use slender sections only in a most economical way.
Minimum sawing and cutting of wooden pieces should be made to enable reuse of the material a
number of times. The quantity of surface finish depends on the quality of the formwork.
---
## Page 4
CATEGORIES OF FORMWORK
Conventional: The formwork is built on site out of timber and plywood or moisture-resistant particleboard. It is
easy to produce but time-consuming for larger structures, and the plywood facing has a relatively short
lifespan. It is still used extensively where the labour costs are lower than the costs for procuring reusable
formwork. It is also the most flexible type of formwork, so even where other systems are in use, complicated
sections may use it.
Modern-Day Formworks: This formwork systems are mostly modular, which are designed for speed and
efficiency. They are designed to provide increased accuracy and minimize waste in construction and most
have enhanced health and safety features built-in. The main types of formwork systems in use now are:
of
Table form/flying form
System column formwork
Horizontal panel
Slip form
Tunnel form
Engineered/Pre-fabricated Formworks: This formwork is built out of prefabricated modules with a metal frame
(usually steel or aluminium) and covered on the application (concrete) side with material having the wanted
surface structure (steel, aluminium, timber, etc.). The two major advantages of formwork systems, compared to
traditional timber formwork, are speed of construction and lower life-cycle costs (barring major force, the
frame is almost indestructible, while the covering if made of wood; may have to be replaced after a few -ora
few dozen — uses, but if the covering is made with steel or aluminium the form can achieve up to two thousand
uses depending on care and the applications).
---
## Page 5
MATERIALS USED
Formwork are mainly of two types
Steel formwork
Wooden formwork
Steel formwork is made of
Steel sheets
Angle Iron
Tee Iron
Wooden formwork consists of
Props
Planks battens
Ledgers
Sheeting
Steel Formwork
---
## Page 6
Timber formwork:
Most common material used for
bracing the member, hence called
as the traditional formwork.
can easily be cut to size onsite.
Joist are replaced with engineered
wood beams and supports are
replaced with metal props. This
makes this method more systematic
and reusable.
Various sizes of members of timber
Sheeting for slabs,
beam, column side
and beam bottom
25mm to 40mm
thick
mm
75 x 100mm to
100 x 100 mm
---
## Page 7
Plywood
- This is by far the most common material
used for the facing panel. It is easily cut
to shape on site, and if handled and
stored carefully, it can be used many
times.
- Astandard plywood thickness on site is
18mm. This is usually sufficient for most
pours.
- However, if the formwork is curved, a
thinner plywood is used to facilitate
bending.
- Thicker plywood may be used when the
weight of concrete causes a standard
thickness plywood to bow out, distorting
the concrete face.
---
## Page 8
Steel formwork:
- Steel forms are stronger, durable
and have longer life than timber
formwork and their reuses are more
in number
- Steel forms can be installed and
dismantled with greater ease and
speed.
- The quality of exposed concrete
surface by using steel forms is good
and such surfaces need no further
treatment.
- Steel formwork does not absorb
moisture from concrete.
- Steel formwork does not shrink or
warp
---
## Page 9
Aluminium formwork
Often used in pre-fabricated
formwork, that is put together on site.
Aluminium is strong and light, and
consequently fewer supports and ties
are required.
The lighter sections will deflect more,
but this can be avoided by simply
following the manufacturers
recommendations.
---
## Page 10
Plastic formwork
Glass reinforced plastics (GRP) and
vacuum formed plastics are used
when complicated concrete shapes
are required (e.g. waffle floors).
Although vacuum formed plastics
will always need support, GRP can
be fabricated with integral bearers
making it self supporting.
Like steel, plastic formwork can be
re-used many times, as long as care
is taken not to scour the surface
whilst vibrating the concrete.
---
## Page 11
PROCESS OF FORMWORK
CONSTRUCTION
FORMWORK FOR VARIOUS STRUCTURAL MEMBERS
Construction of formwork:
This normally involves the following operations:
Propping and centering
Shuttering
Provision of camber
Cleaning and surface treatment
---
## Page 12
FORMWORK FOR WALL
It consists of
* Timber sheeting
* Vertical posts
* Horizontal members
* Rackers
* Stakes
* Wedges
After completing one side of formwork
reinforcement is provided at the place
then the second side formwork is provided.
. ZS
ZA “a SOAS 4, SSS SSP LF RD ESTA ONS
2
TIMBER SPACER
BOLT WITH NUT& HEAD
STRUTS AT EQ AL
SPACING
BOARDING
BRACINGS
a ONL
WOODEN BLOCKS
PACKING
---
## Page 13
Wall Formworks and its components
Floor soffit Timber joists to support the floor soffit
Metal prop (tubular frame)
---
## Page 14
It consists of the following
— Side & End Planks
— Yoke
— Nut & Bolts
Two end & two side planks are
joined by the yokes and bolts.
---
## Page 15
| Erection sequence for a column
Prior to positioning column formwork check that steel for the column
has been inspected and cleared for casting.
-Propping
- Position formwork for the column from predetermined grids. Prop
- Plumb formwork both ways and securely support using adjustable
steel props.
- The propping angle should be 45° to the floor.
- - Ensure the steel props are safely secured to the column formwork
and the
flooryand that adjustment for pushing and pulling is operational.
- Serout the positions of column clamps from a storey rod.
ansfer the column clamp positions from the storey rod onto colu
mn formwork.
Use nails to support the arms of column clamps while wedging.
Position and wedge the bottom, middle and top clamps sets.
Check the formwork at the top for square.
Position and wedge the remainder of the column clamps.
Using a plumb bob suspended from a gauge block plumb the
COLUMN CLAMPS IN POSITION
column. Column clamps are created to give extra
external support to the formwork from
When all the column formwork is securely propped a final check must avoiding circularing of the column
be made for plumb and column alignment before and immediately
after the concrete has been poured and vibrated.
---
## Page 16
MS. Bars
35 mm TH Boarding
$0 x 100 Batten
20 min D budt
Wedge
Vashout --
hole
Ww
Adjustable steel clamps
Bolts through timber yokes
ADJUSTABLE STEEL CLAMPS
Wxtteste top and bottom
sTOREY ROO
Nails to provide temporary support for
clamps ]
Arms ready to intertock around coturnn-
note positions of returned ends
TEMPORARY GUPPORT FOR COLUMN CLAMP
---
## Page 17
CIRCULAR AND OCTAGONAL COLUMNS
Circular column formwork / STWPENER IBS
Fabricated steel, usually two piece, and often with
a hinge.
Fibre cement pipes which are left in place as perm
anent formwork.
Timber sheathing tied with standard column clamp
s. Corners need to have infill pieces. Alternatively,
etal strap can be used without the need for corn
er infills.
Fabricated steel with bolted joints
Vertical steel two piece form column
TIMBER FRAME
Vertical Timber sheathing column
---
## Page 18
COLUMN BRACING FORMWORK
*Column formwork bracing performs two functions:
¢lt must maintain the accuracy of the column form position and plumb so that it is
within tolerance.
¢Withstand results of forces acting on either the column formwork or the bracing.
The forces may be wind or impact. These impact forces can occur from the coll
ision of Concrete buckets or cranes hoisting materials
wn i COLUMN Fromm
ihe went
‘Va ‘ j
HINGE TO TOP OF PROF
eoureo TO COLUMN FORM
PROP CATENSION
WHEN IM TENSION
PROF TIGHTENLD AGAINST
_- COLUMN CLamr
Fact of
HINGE TO BOTTOM OF
FORMwoRK
PROF BOLTED TO Siab
WOOD MLOCK SHOT
Se 'O Sean
---
## Page 19
FORMWORK FOR BEAM
Beam soffit must be thickened timber or strengthened plywood.
Beam sides 18mm plywood or 25mm boards, with studs (cleats)
at 500 to 600mm centres.
Deep beams (over 600mm) should have walkers and fies.
Use angle fillets in the beam side to soffit joint where possible.
owance must be made for height adjustment of the props or
Erection sequence for constructing beam formwork includes
¢ Position of sole plates;
¢Marking out and setting heights for falseworks;
bearers and Spreaders;
«Construct and erect side walls and beam soffit.
¢ Position of sole plates
Assemble and position props, adjustable head jacks, falseworks ,
p> 25 x 50 ties at 600 c/c
15 mm thick plywood 75 x 25 cleats
sdes at 600 c/c
— alternative
fixing teat— fixing cleat
75 x 50 crosshead _ 21 mm thick plywood
or headtree - soffit
w.i. dogs to both sides
100 x 75 props at
folding wedges 1-200 c/e
for adjustment —
a: 225 x 75 sole plate
21 men track plywood softer
18 mam thack plywood beam wes.
---
## Page 20
FORMWORK FOR STAIRCASE
¢Points fo consider when designing stair form work :
Stair formwork must support the weight of concrete.
The weight of the throat of the stair and the steps will
have to be supported.
Because of the slope of the stair, some of the force is
transmitted sideways. All formwork must be well tied
togéther to prevent sideway movement.
onsider the finish of the stair treads and type of nosing.
Space may have fo be left for purpose made nosing.
———
Y
———— f ot bridytng
---
## Page 21
SUSPENDED SLABS
Suspended floor slabs can be constructed using cast in-
situ, precast units or a combination of both.
Whichever method is used, it is important to support the
roposed method ofconstruction using a combination o
f timber or steel bearers and adjustable shoring.
The spacing and type of support system required is
determined by the load imposed during the
construction process.
Manufacturers provide tables to assist in the selection
and spacing of adjustable shoring
systems.
Standard slab formwork
The erection sequence for constructing a
suspended floor slab includes:
¢ Determining the bearer spacing;
¢ Erecting bearers and joists;
¢ Fixing the sheeting;
¢ Preparation for concrete.
---
## Page 22
SOLE PLATE
one vertical support member to the foundation
The vertical support requires a base plate fitted to help
pooren. the load to the sole plate, which is usually a
eper.
If the sole plate is positioned on natural ground, it is
important the ground is graded and consolidated to a
level surface.
The objective is to achieve maximum bearing beneath
sole plate. Once sole plates are positioned and firmly be
dded they should be checked for level. Form Work for concrete Beams & Slabs
---
## Page 23
\
---
## Page 24
Curing is the process in which the concrete is
protected from loss of moisture and kept within
a reasonable temperature range. The result of
this process is increased strength and
decreased permeability. Curing is also a key
player in mitigating cracks in the concrete,
which severely impacts durability
The length of adequate curing fime_ is
dependent on the following factors:
Mixture proportions
Specified strength
Size and shape of concrete member
Ambient weather conditions
Future exposure conditions
Deshuttering is a process after curing
---
## Page 25
DESHUTTERING
DESHUTTERING in simple means, the process of removing the shuttering (Formwork for
Concrete).
Order and method of removing formwork:
Shuttering forming vertical faces of walls, beams & column sides should be removed first.
Shuittering forming sofit to slab should be removed next.
huttering forming soffit to beams, girders or other
heavily loaded members should be removed in the end.
Factors considerd :
Concreting is done under normal circumstances
Cement used is Ordinary Portland Cement
Adequate curing is done
Ambient temperature is not fall below 15 degree
---
## Page 26
DESHUTTERING AGENTS
There are chances of concréte sticking to the formwork
Hence deshuttering agents are used to ease the process
Dosage / Coverage:
Dilution ratio: KEM MRA 2: water at 1:10. Coverage: 1600 sq. ft. depending
on conditions of formwork
KEM MRA 1 - 25 / 30 mia% / liter depending upon the porosity and usage
condition of the substrate
---
## Page 27
TRADITIONAL FORMWORK
Timber form work was used traditionally later it
got replaced with modem materials due to its
limitations and cost factors
Formwork is built on site with timber and ply or
oisture resistant particle board.
It is easier to produce but the time taken is
more
Extensively used where the labor cost s are low ,
Usually timber in the form of
plywood, planking,
batten and joist are used as
the basic material.
It is the most flexible type of formwork
Human workers need to enter
into every comer to perform
the formwork installation works
---
## Page 28
re
XPLORING NEW FORMWORK TECHNIQUES
---
## Page 29
| SLIPFORM TECHNOLOGY
INTRODUCTION:
*Method of vertically extruding a reinforced concrete
section and is suitable for construction of core wallsin
high-rise structures — lift shafts, stair shafts,towers.
‘The formwork rises continuously, at a rate of about 300
mm per hour, supporting itself on the core and not
relying on support or access from other parts of the
building or permanent works.
«Allows for the continuous pouring of concrete into walls
of a structure and only stops when the full required
height of the structure has been reached.
‘The height of the formwork is designed in such a way
that while the top of the formwork is being filled by
concrete the lowest layer of concrete poured earlier ' : ‘
has already gained an initial set. When the formwork is “ae : 4 on
moved upwards the concrete that is then exposed ; . , ;
remains firm. :
CHEUNG KONG
CENTRE
---
## Page 30
| PROCEDURE :
«Assembly can only start once the foundations are in place and
the wall starter is in correct alignment.
*Slipform shuttering is aligned with the help of yokes.
*Horizontal crossbeams connect these yokes.
[Top Deck]
«Hydraulic jacks are atiached to these crossbeams for
simultaneous upward movement. eG
(Panel)
(Top Deck)
*Height of the slipform ranges from 1.1 to 1.5 metres. -
*Yokes and crossbeams also used to support the working
platform
«Structure should be rigid and shape maintained at all times.
*Make sure there is no lag or else if prevents the structure from
free upward movement
* Itis also possible to reduce wall thicknesses
as the construction gains height and arrangements
have to be made in the slipform structure that will
enable such reduction at regular intervals.
---
## Page 31
Concrete Supplier
Top Deck
Lattice Truss
Yoke
Lift Jack
Working Deck
Concrete Form
Hanging Deck
ERECTION OF A TOWER USING SLIPFORM
---
## Page 32
HORIZONTAL FORMWORK :
*Slipform methods of construction
can also be adapted to horizontal
structures and are used for paving,
canals, and tunneling.
* The technique is more in use for
structures that have continuous walls
like silos , chimneys, and piers for
very tall bridges.
* It has also been successfully used for
construction of buildings, although
this requires the manner of leaving
inserts for openings like doors and
windows to be decided well in
advance, as well as also any
necessary inserts to support floor slabs
after the walls are constructed.
---
## Page 33
ADVANTAGES:
*A major cost of concrete structure construction is the
required formwork to retain the concrete fill it can be safely
de-shuttered and be able to support itself and other imposed
loads.
*The formwork needs to be continually removed to newer
locations and then re-erected.
*Continuous use of manpower and lifting equipment like
cranes.
«In the case of slipform building, the formwork is erected only
nce and remains intact until the entire structure is
completed.
*Great reduction in the cost of formwork as
well as time saving for re-erection.
*Cost effective
*Saving onto the labour cost otherwise
used for intermittent concreting operations.
‘The reduction in the movement of formwork
and workers also leads to far more safe working
conditions that also make if a major advantage.
---
## Page 34
fa)
Sa Saat ah A A Gn a ae eae
PRECAUTIONS
* Concrete is continuously protected against loss of moisture and
rapid temperature changes for 7 days
* Unhardened concrete is protected from rain and flowing water
* Prevent plastic shrinkage
* Plastic cracks are filled by injection of epoxy resin.
Reinforcing bars
Fresh concrete may be lifted from
the hardened part
Steel bar hinders
fresh concrete flow &
and causes cracking
---
## Page 35
RELATION BETWEEN
CONCRETE SETTING TIME
AND SLIPFORM RATE:
elt is calculated by using the
following equation:
Vs =(h1- h1) / (ts— tt)
Where
Vs —slipform rate (mm / h)
HI = the distance from the top
of the slipform panel to the
average curing front (mm)
H2 = The distance from the top
of the slipform panel to
average freeboard (mm)
Ts = setting time (h)
Tt = Time from mixing concrete
to placing
a gas slip form
design
Yoke leg Top Deck
KICT Intergrated Configuration
Control System
| Bade
GPS
ki Wireless.
plumb |
---
## Page 36
TUNNEL FORMWORK SYSTEM
sTunnel formwork system allows the contractor to cast walls and slabs
in one operation ina daily cycle.
elt combines the speed, quality and accuracy of factory/off-site
production with the flexibility and economy of in-situ construction
* Recognized as a modern method of construction (MMC).
---
## Page 37
The result is a cellular reinforced structure, the surfaces of which are
sufficiently high quality to require only minimal finishing for direct
decoration, while the end walls and facades are easily completed with
thermally insulated units that can be clad as required.
The system creates an efficient load-bearing structure for use in a wide
variety of applications.
Itis particularly effective in projects suited to repetitive cellular
construction such as residential blocks, hotels, student accommodation,
bo rracks and prisons.
---
## Page 38
ADVANTAGES:
Cost
cost-effective, high quality construction,
generating significant savings in time
and costs over alternative methods
without compromising on design
Building
The repetitive nature of the system and the use of prefabricated forms
nd reinforcing mats/cages simplifies the whole construction process,
producing a smooth and fast operation
Quality
Quality is enhanced despite the speed of construction. The precise,
even steel face of the formwork creates a smooth, high quality finish
capable of receiving direct decoration with the minimum of
preparation (a skim coat may be required). This reduces the
requirement for following trades, thus providing additional cost savings
and speeding the entire process.
---
## Page 39
Design
The large bays constructed provide exceptional flexibility in the
design and layout of the building and allow a high degree of
freedom in the final appearance.
Safety
Integral working platforms and edge protection systems. The
repetitive, predictable nature of the tasks involved encourages
familiarity with operations. The minimal requirement for tools and
quipment further reduces the risk of accidents on site.
Sustainability
The in-situ casting of units on site and the local availability of ready-
mixed concrete supplies reduce transportation impacts.
Just-in-time deliveries and near zero wastage produce an overall
tidier site with associated cost savings and safety benefits.
Concrete’s thermal mass coupled with correct insulation and boiler
design minimises heating costs and can even reduce air-
conditioning requirements.
---
## Page 40
GENERAL FACTS :
Tunnel formwork come in half units and in the form of an inverted “L”
which are bolted together at the top to form each tunnel. The inbuilt
wheels and the jacks help the formwork move in and out of the
position and adjusted to the final height.
The factory-made steel formwork can be re-used up to 600 times
and it can suit a variety of module sizes. This makes the method of
construction very versatile and extremely economical.
Tunnel-form work allows a 24-hour construction cycle to be achieved
and thus the buildability of in-situ concrete is improved by choosing
this type of formwork.
---
## Page 41
The Casting Process of Tunnel Formwork:
1) Stage One: Prefabricated Wall reinforcement is placed by
crane along the entire wing prior to casting the kickers (used to
position wall formwork).
Wal remforcement,
4
2) Stage Two: Two and a half tunnel is craned into place, bolted
together and ties are added.
Wat remforcement,
---
## Page 42
3) Stage Three: The wall concrete is poured.
Wat remforcement
4) Stage Four: The slab reinforcements are fixed
Wal rem forcement.
4
---
## Page 43
5) Stage 5: The slab concrete is placed. The formwork system provides
for a pour to be wrapped in tarpaulins and for the use of butane
heaters to maintain a sufficiently high temperature for the concrete to
reach its striking strength overnight.
6) Stage 6: The tunnel-forms are removed next day.
Wal remforcement
---
## Page 44
7) Stage 7: The process is repeated for the next two bays.
, Wal remforcement_
‘
Tunnel form can produce strong and durable in-situ cellular
structures. This method of construction can achieve time
savings up to 25% with cost savings of 15%.
Since the concrete finish is very good, the requirement for post
construction trades such as plasterers and electricians are
greatly reduced.
---
## Page 45
Honzorta! Panel
Stab Stopens
Wal Stopend
Vertical Panel (inner)
Push Put Prop
Wheeled Prop
Wheeled Prop Support
COMPONENTS OF TUNNEL FORMWORK
---
## Page 46
COLUMN SYSTEM FORMWORK
The column formwork
systems now available are
normally modular in nature
and allow quick assembly
) and erection on-site while
minimizing labor and
crane time. They are
available in steel,
aluminium and even
cardboard (not reusable
but recycled) and have a
variety of internal face
surfaces depending on the
concrete finish
i required. Innovations have
led to adjustable, reusable
column forms which can
be clamped on-site to give
different column sizes.
---
## Page 47
Benefits
‘Increased speed and efficiency in construction
‘The requirement of skilled labor is reduced due to
the
simplicity of assembly and disassembly.
«Metal column forms can be assembled and erected
more easily than traditional formwork.
* Disposable forms come ready assembled to site. ijl
*High quality surface finishes are possible. |
‘The highly engineered nature of the metal formw
yste ‘to the formwi
16mm bolts or
threaded rods hardwood
rs |
=<
column shutters
timber yoke ply and say 375 x 36
say 100x 75
---
## Page 48
Safety
«Metal formwork systems can have
integral ready-to-use concreting
platforms with guard rails and access
equipment including ladders. This
reduces the need for independent
access.
*For systems with disposable formwork,
working platforms for concreting have
to be erected separately to allow safe
access to the top of the column forms.
*Formwork systems are available which
need to be worked only from one side.
This could be an important safety
consideration for columns situated at
building edges and corners.
*Metal systems typically provide robust
assemblies.
*Assembly process is simple allowing site
operatives to become familiar with
health and safety aspects.
*Normally these formwork systems
require minimal use of power tools.
---
## Page 49
Other considerations
Column forms are designed for specific maximum concrete
pressures. The concrete placement rates have to be adjusted
to keep the concrete pressure within the specified limits.
The assembled formwork has to be restrained at the base
propery to avoid displacement, and grout loss during
vertical beam
fasterner
SCAFFOLD FOR COLUMN
---
## Page 50
M
~~
O
=
=
oO
O
LL
a)
Lu
_—
<
O
ag
faa)
<
Lu
Ww
as
---
## Page 51
ADVANTAGES OF PRE- FABRICATED FORMWORK
* Very little on-site skilled labor needed.
* The ability to reuse forms either as a large section or as
individual units.
* All prefabricated systems are designed for light as well as
heavy construction.
* Contractors can bid almost any type of work; straight,
battered, curved or cut-up.
* Prefab forms may be set in any combination, horizontally and
vertically, fo any wall height.
* On high walls, one side of forms can be erected and ties
placed; then the close-out side can be erected during
placement, minimizing concrete drop and assuring effective
vibration.
---
## Page 52
QO2Z>OQ
Oe = <7 Om
In a prefab system the contractor can remove
and replace forms at any point. This simplifies
erection and stripping, which can be started at
any location.
To allow for a casting pocket, a panel is simply
removed and replaced maintenance of forms
can be a tiresome task, but well-maintained
forms mean more reuses.
A big advance in prefab forming has been the
development of gang forming, which is simply
defined as the grouping together and moving
of a number of forms as a single unit.
The success of gang forming is due fo the
development of easy-to-use hard w a re and
ties, made _ especially for this forming
technique.
Since pre forms are pre - engineered and
precision made, they offer the best materials
available and work equally well on all jobs,
resulting in lower cost per use. Although
prefabricated forms work well on any size job,
the small job is a good way fo introduce the
system to the workmen.
---
## Page 53
DRAWBACKS
* High cost factor
* Greater transportation cost, due to the large
pieces, where as the regular formwork can be
transported easily .
* Too many pieces involved in the pre fabricated
formwork
*, Pre fabricated formwork, leave poor finishes at the
joints of the forming members.
Pre“fab formwork deflect during placement.
Tye first cause of deflection is the rate of placing,
ich is usually too fast.
If recommended placing rates are followed and
there is good supervision of placement and
vibrating, the problem of deflection can be
controlled.
With many prefab systems, panels can be re m
oved at different locations and used as casting
pockets.
This procedure avoids dropping the concrete a
great distance and helps to maintain a more
constant rate of placement.
---
## Page 54
POINTS OF
DIFFERENTIATION
MATERIAL USED
TIME
CONSUMPTION
Pas SPAN
USED IN
FLEXIBILITY
CONVENTIONAL
METHOD
TIMBER ( Plywood
Or moisture-resistant
Particleboard).
VERY TIME
CONSUMING.
(For large
structures.)
The plywood facing
has a relatively
SHORT LIFE SPAN.
The labour costs are
LOWER than the
costs for procuring
reusable formwork.
MOST FLEXIBLE
MODERN DAY
METHOD
STEEL AND
ALUMINIUM.
DESIGNED FOR
SPEED AND
EFFICIENCY.
(mostly modular)
LONGER LIFE SPAN
The labour costs are
HIGHER than the
costs for procuring
reusable formwork.
LESS FLEXIBLE.
PREFABRICATED METHOD
Frame of ALUMINIUM
covered with ALUMINIUM
OR TIMBER
Work happens
simultaneously with
construction hence saves
time
The frame is very durable
(If made of metal n
aluminium can be used for
2000 times)
The labour costs are HIGHER
than the costs for procuring
reusable formwork.
There is NO FLEXIBILITY after
making the formwork
---
## Page 55
Time of Removal of formwork
OPC Rapid Hardening
Structural Member (Ordinary Portland Cement) Cement
1 Beam sides, walls & Columns 2-3 Days
Slab (Complete Formwork removal) 10 Days
Beams (Removal of Sheeting, Props 8 Days 5 Days
remains intact)
Beams & Arches (Complete formwork 14 Days
removal) (up to 6 m span)
Beams & Arches (Complete formwork 21 Days 8-10 Days
removal) (more than 6 m span)
---
## Page 56
ETA
Sawa 7
TTT) me /A TO gh
wa
|
eS FOS 1 See eee
r
---
## Page 57
Formwork failures are the cause of many accidents
and failures that occur during concrete construction
which usually happen when fresh concrete is placed
Generally some unexpected event causes one
member fo fail, then others become overloaded or
misaligned and the entire formwork structure collapses
Improper stripping and shore removal
Inadequate bracing
Vibration
Unstable soil under mudsills, shoring not plumb
nadequate control of concrete placement
Lack of attention to formwork details
Inadequate cross bracing and horizontal bracing of
shores
Forms sometime collapse when their shores/ jack are
displaced by the vibration caused by:
passing traffic
movement of workers & equipment on the formwork
the effect of vibrating concrete to consolidate it
---
## Page 58
SAFETY PRECAUTION
Material used for the construction of formwork must fulfill the
specification.
Formwork is fixed firmly & properly
Construction area must be protected to prevent vandalism of
formwork.
Warning sign must be put up at the area where the formwork is fixed
to prevent entrance of people that may damage the formwork.
The formwork must be inspected before the concrete is poured.
---
## Page 59
STRIKING, MAINTENANCE, STORAGE OF FORMWORK
Striking :
As column and beam side formwork will be removed before beam and slab
soffit formwork, provision must be made for easy removal and in the correct
order. If beam and slab soffit formwork is to be removed before the concrete
has achieved working strength, permanent propping or shoring is required.
Take care to avoid damage to formwork which is fo be re used. Eight or more
uses may be obtained from timber formwork.
Maintenance Clean forms with stiff brush and clean cold water. Use scrapers
only as a last resort. Keep forms well oiled to prevent delamination of
plywood or rusting of steel and always oil the edges.
Storage of forms Any formwork with steel components should be stored in the
dry. Avoid direct sunlight on timber forms. Store clear of the ground without
twist or bend, and keep free of dirt.
---
## Page 60
THANK YOU
ZEUS PITHAWALLA (37) RITHIKA RAVISHANKAR(40) EKTA SHAH(44)
GARIMA RAJPUT(38) SHIVALI SANAP(41] RAJESH SHELAKE(45)
MANASVI RANE (39) SUVOJIT SEN(43) |