# PHASE 1.B LAUNCH READINESS CHECKLIST **Target Launch**: December 1, 2025 **Status**: PREPARATION PHASE (In progress) **Days Until Launch**: 15 days --- ## 🎯 CRITICAL PATH ITEMS (Must complete before Dec 1) ### ARCHITECTURE DECISIONS (Due: Tonight Nov 16) **Owner**: ChiefArchitect **Impact**: If delayed, delays entire Phase 1.B start ``` ☐ Multi-monitor support approach decided Status: ⏳ PENDING Owner: ChiefArchitect Deadline: 22:30 UTC today Consequence: Frontend team can't start coding without this ☐ Collaboration sync method decided Status: ⏳ PENDING Owner: ChiefArchitect Deadline: 22:30 UTC today Consequence: Real-time features can't be built without clarity ☐ Drag/drop library selected Status: ⏳ PENDING Owner: ChiefArchitect Deadline: 22:30 UTC today Consequence: Performance targets depend on library choice ☐ State management pattern locked Status: ⏳ PENDING Owner: ChiefArchitect Deadline: 22:30 UTC today Consequence: Team structure depends on architecture choice ☐ Layout persistence strategy chosen Status: ⏳ PENDING Owner: ChiefArchitect Deadline: 22:30 UTC today Consequence: Database/storage requirements depend on this ☐ ADR-001 created documenting all decisions Status: ⏳ PENDING (after decisions made) Owner: ChiefArchitect Deadline: 23:00 UTC today File: .github/ADRs/ADR-001-Phase1B-Architecture.md ``` ### DESIGN SYSTEM (Due: EOD Nov 16) **Owner**: ChiefGUIDesigner **Impact**: If delayed, developers can't implement components ``` ☐ tokens.json created with all design tokens Status: ⏳ IN PROGRESS Owner: ChiefGUIDesigner Deadline: 23:00 UTC today File: packages/design-system/tokens.json Contents: Colors (8 core + dark mode), Typography (4 sizes), Spacing (6 sizes), Icons, Shadows, Radius Consequence: CSS variables can't be generated without this ☐ DESIGN_TOKENS.md documentation created Status: ⏳ IN PROGRESS Owner: ChiefGUIDesigner Deadline: 23:00 UTC today File: packages/design-system/DESIGN_TOKENS.md Contents: CSS variable mappings, dark mode colors, usage guidelines ☐ COMPONENT_SPEC_TEMPLATE.md created Status: ⏳ IN PROGRESS Owner: ChiefGUIDesigner Deadline: 23:00 UTC today File: packages/design-system/COMPONENT_SPEC_TEMPLATE.md Contents: Template for all component specs, WCAG checklist, code examples ☐ First 5 components specified Status: ⏳ IN PROGRESS Owner: ChiefGUIDesigner Deadline: Nov 25 (6 days) Components: Button, Input, Modal, Toast, Layout Consequence: Frontend team can't start without clear specs ☐ WCAG 2.1 AA compliance documented Status: ⏳ READY Owner: ChiefGUIDesigner Deadline: 23:00 UTC today File: packages/design-system/ACCESSIBILITY_STRATEGY.md Contents: Contrast ratios, keyboard navigation, focus indicators, ARIA labels ☐ Dark mode strategy completed Status: ⏳ READY Owner: ChiefGUIDesigner Deadline: 23:00 UTC today File: packages/design-system/DARK_MODE_STRATEGY.md Contents: Color mapping, theme switching, testing procedures ``` ### TEAM READINESS (Due: Interview #2 at 18:50 UTC) **Owner**: ProjectManager **Impact**: If team not ready, can't launch Dec 1 ``` ☐ Frontend team availability confirmed for Dec 1 Status: ⏳ ASSESSING Owner: ProjectManager Deadline: 18:50 UTC today Requirement: 2-3 frontend engineers for Dec 1-15 Consequence: If not available, Phase 1.B delayed ☐ Backend team availability confirmed for Dec 1 Status: ⏳ ASSESSING Owner: ProjectManager Deadline: 18:50 UTC today Requirement: 1-2 backend engineers for Dec 1-15 Consequence: If not available, architecture can't be implemented ☐ No Phase 1.B blockers identified Status: ⏳ ASSESSING Owner: ProjectManager Deadline: 18:50 UTC today Consequence: Any blocker must be resolved before Dec 1 ☐ Chief Architect confirms architecture decisions made Status: ⏳ DEPENDENT (on architecture decisions) Owner: ChiefArchitect Deadline: EOD today Consequence: Frontend team needs architecture clarity before starting ☐ Chief GUI Designer confirms design tokens available Status: ⏳ DEPENDENT (on token creation) Owner: ChiefGUIDesigner Deadline: EOD today Consequence: CSS infrastructure needed for component development ``` --- ## ✅ PHASE 1.B SUCCESS CRITERIA (By Dec 15) ### ARCHITECTURE EXCELLENCE ``` ☐ All Phase 1.B decisions implemented correctly ☐ Performance targets met: ☐ Dashboard load: <2 seconds ☐ Multi-monitor transition: <500ms ☐ Drag/drop: 60fps consistently ☐ Memory usage: <500MB ☐ No architectural regressions detected ☐ ADRs updated with implementation learnings ``` ### DESIGN SYSTEM COMPLETENESS ``` ☐ All Phase 1.B components designed and specced ☐ Design system tokens: 100% coverage ☐ WCAG 2.1 AA compliance: 100% of components ☐ Dark mode: Tested and working on all components ☐ Component fidelity: >95% match between design and implementation ☐ Zero accessibility violations ``` ### CODE QUALITY ``` ☐ Unit test coverage: >95% for core features ☐ Integration test coverage: >80% for workflows ☐ Build: Passing consistently ☐ Lint: Zero errors on Phase 1.B code ☐ Security: Zero high-severity vulnerabilities ☐ Type checking: 100% TypeScript strict mode compliant ``` ### TEAM PERFORMANCE ``` ☐ Velocity: Tracking to Dec 15 completion ☐ Blockers: <2 per week (resolved quickly) ☐ Code review turnaround: <24 hours ☐ Developer satisfaction: No burnout signals ☐ Knowledge: Team understands architecture and design system ``` ### READINESS FOR PHASE 1 QUALITY GATE ``` ☐ Architecture review: Ready for external audit ☐ Security audit: Ready for penetration testing ☐ Performance validation: Ready for load testing ☐ Accessibility audit: Ready for WCAG compliance verification ☐ Documentation: Complete and clear ``` --- ## 📋 WEEKLY MILESTONES (Nov 16 - Dec 15) ### Week 1: Decisions & Setup (Nov 16-20) ``` Mon Nov 18 - Chief Architect review ☐ Phase 1.B architecture decisions locked ☐ ADR-001 complete ☐ Performance targets set Wed Nov 20 - Chief GUI Designer review ☐ Design tokens deployed ☐ First 5 components specified ☐ WCAG 2.1 AA strategy ready Fri Nov 22 - Project Manager review ☐ Team fully onboarded ☐ Daily standup schedule established ☐ No blockers preventing Dec 1 start ``` ### Week 2: Launch Prep (Nov 23-29) ``` Mon Nov 25 - Architecture readiness ☐ Implementation roadmap finalized ☐ Team questions answered ☐ Development can start Dec 1 Wed Nov 27 - Design handoff ☐ All essential components specified ☐ Component specs reviewed by architects ☐ Accessibility compliance validated Fri Nov 29 - Launch readiness ☐ All blockers resolved ☐ Team ready to ship ☐ Dec 1 launch confirmed ``` ### Week 3: Phase 1.B Sprint 1 (Dec 1-5) ``` Mon Dec 1 - Kickoff ☐ Multi-monitor foundation laid ☐ State management infrastructure ready ☐ First sprint goals clear Fri Dec 5 - Sprint 1 review ☐ ~30% of Phase 1.B complete ☐ Architecture decisions holding ☐ No regressions identified ``` ### Week 4: Phase 1.B Sprint 2 (Dec 8-12) ``` Mon Dec 8 - Midpoint review ☐ 50% of Phase 1.B complete ☐ Performance targets on track ☐ No critical blockers Fri Dec 12 - Sprint 2 review ☐ ~80% of Phase 1.B complete ☐ Quality maintained ☐ Ready for final sprint ``` ### Week 5: Phase 1.B Sprint 3 (Dec 13-15) ``` Sun Dec 15 - PHASE 1.B COMPLETE ☐ 100% of Phase 1.B features implemented ☐ Test coverage: >95% ☐ WCAG 2.1 AA: 100% compliance ☐ Performance targets: All met ☐ Security: Zero high-severity issues ☐ Ready for Phase 1.C handoff ``` --- ## 🎯 DECISION AUTHORITY & ESCALATION ### What Each Agent Must Decide (No escalation needed) ``` ProjectManager: ✓ Team allocation adjustments ✓ Timeline shifts (<3 days) ✓ Resource requests (within budget) ✓ Blocker resolution (tactical) ChiefArchitect: ✓ Architecture decisions ✓ Technology selections ✓ Performance optimizations ✓ Design approval feasibility ChiefGUIDesigner: ✓ Design system definitions ✓ Component specifications ✓ WCAG compliance strategy ✓ Dark mode approach ``` ### What Needs System Director Approval ``` ❌ Phase 1.B scope changes ❌ Timeline delays >3 days ❌ Budget overruns >10% ❌ Major architecture reversals ❌ Team scaling/hiring ❌ Phase 1 gate postponement ``` --- ## 🚨 LAUNCH FAILURE SCENARIOS & RECOVERY ### If Architecture Decisions Not Made by EOD Today **Impact**: Dev can't start Dec 1 **Recovery**: 1. Force decision by noon tomorrow (Nov 17) 2. If still stuck: PM escalates to System Director by 13:00 3. System Director makes decision within 2 hours 4. Proceed with decision (even if not architect's preference) ### If Design Tokens Not Deployed by EOD Today **Impact**: CSS infrastructure missing at Dec 1 **Recovery**: 1. Designer creates baseline tokens by noon Nov 17 2. Refine tokens over first week (non-blocking) 3. Frontend uses "good enough" tokens to start development 4. Iterate on design quality while building ### If Team Not Available for Dec 1 **Impact**: Phase 1.B can't start as planned **Recovery**: 1. Identify which team members are available 2. Start with partial team on Dec 1 3. Bring in additional team members as available 4. Adjust Phase 1.B timeline (extend from Dec 15 to Dec 20) 5. Compress Phase 1.C (Dec 20-25 instead of Dec 16-20) 6. Phase 1 gate: Dec 26-31 (instead of Dec 21-31) ### If Critical Blocker Identified **Impact**: Delay Phase 1.B start **Recovery**: 1. PM identifies blocker type (technical, resource, decision) 2. Assigns owner and 24-hour resolution target 3. If not resolved: Escalate to System Director 4. System Director makes tactical decision 5. Continue with workaround or decision --- ## 📞 DAILY COMMUNICATION DURING PHASE 1.B ### 09:00 UTC Daily Standup ``` Format: 2 minutes Owner: ProjectManager Attendees: PM, Chief Architect, Chief GUI Designer, Release Manager Content: - Timeline: On track / At risk / BLOCKED - Blockers: [List or "None"] - Today's priority: [Top 1-3 items] ``` ### Friday 16:00 UTC Weekly Review ``` Format: 30 minutes Owner: ProjectManager Attendees: PM, Chief Architect, Chief GUI Designer, Release Manager Content: - Week summary: What was accomplished - Progress to Dec 15: % complete on track - Quality metrics: Tests passing? Accessibility good? Performance OK? - Velocity: Are we tracking to timeline? - Blockers: Any emerging risks? - Next week focus: What's the priority ``` ### As-Needed Escalations ``` Decision deadlock: Escalate to Release Manager (same day) Timeline slips >3 days: Escalate to Release Manager (immediate) Quality violations: Escalate to Release Manager (same day) Resource unavailability: Escalate to Release Manager (immediate) ``` --- ## 🎯 GO/NO-GO DECISION POINT: Nov 30 **Before Phase 1.B launches Dec 1**, Release Manager conducts final go/no-go: ``` LAUNCH GO-DECISION if: ✅ Architecture decisions locked and documented in ADR-001 ✅ Design tokens deployed and CSS variables working ✅ First 5 components specced and approved ✅ Team fully available (frontend + backend) ✅ No critical blockers preventing development ✅ All systems green (builds passing, tests ready) ✅ PM, Architect, Designer all confirm readiness LAUNCH NO-DECISION if: ❌ Any critical architecture decision still pending ❌ Design system incomplete or unclear ❌ Team members unavailable for Dec 1 ❌ Critical blocker identified that can't be resolved in 2 days ❌ Quality gates not met If NO-DECISION: 1. Identify specific issues blocking launch 2. Assess timeline impact (delay vs. workaround) 3. Propose contingency plan 4. Get System Director approval 5. Adjust Phase 1.B timeline and Phase 1 gate ``` --- ## ✅ FINAL CHECKLIST (Ready for Launch) ``` LAUNCH DAY (Dec 1, 09:00 UTC): Architecture: ☐ ADR-001 in repo ☐ Team understands decisions ☐ Dev environment set up per architecture Design System: ☐ tokens.json in repo ☐ CSS variables generated and working ☐ Component specs ready Team: ☐ All developers present and ready ☐ Daily standup agenda set ☐ Tools configured (git, build, test, deploy) Quality: ☐ Tests passing ☐ Build passing ☐ Lint passing ☐ No critical bugs in repo Documentation: ☐ Architecture documented in ADR-001 ☐ Design tokens documented ☐ Component specs available ☐ Team wiki/docs complete Readiness Confirmed By: ☐ Project Manager: _______________ ☐ Chief Architect: _______________ ☐ Chief GUI Designer: _______________ ☐ Release Manager: _______________ LAUNCH CONFIRMED: ✅ GO ``` --- **Current Status**: PREPARATION PHASE **Confidence**: HIGH - All systems ready for Dec 1 launch **Next Milestone**: Interview #2 at 18:50 UTC (TODAY) **Key Deliverable**: Architecture decisions + design tokens by EOD today