text
stringlengths
13
991
The Port Authority could only use the funds from the Passenger Facility Charge to make improvements that exclusively benefited airport passengers. As a result, only the sections linking Jamaica and Howard Beach to JFK Airport were approved and built, since it was expected that airport travelers would be the sole users ...
Construction of the system began in May 1998. Most of the system was built one span at a time, using cranes mounted on temporary structures that erected new spans as they progressed linearly along the structures. Several sections were built using a balanced cantilever design, where two separate spans were connected to ...
The route ran mostly along existing rights-of-way, but three commercial properties were expropriated and demolished to make way for new infrastructure. Members of the New York City Planning Commission approved the condemnation of several buildings along the route in May 1999 but voiced concerns about the logistics of t...
The Port Authority predicted that the AirTrain's opening would create 118 jobs at JFK Airport. Service was originally planned to begin on the Howard Beach branch in October 2002, followed by the Jamaica branch in 2003, but was delayed because of several incidents during testing. In July 2002, three workers were injured...
Southeast Queens residents feared the project could become a boondoggle, as the construction cost of the system had increased to $1.9 billion. Like other Port Authority properties, the AirTrain did not receive subsidies from the state or city for its operating costs. This was one of the reasons cited for the system's r...
Several projects were developed in anticipation of the AirTrain. By June 2003, a , 16-story building was being planned for Sutphin Boulevard across from the Jamaica station. Other nearby projects built in the preceding five years included the Jamaica Center Mall, Joseph P. Addabbo Federal Building, the Civil Court, and...
In 2004, the city proposed rezoning 40 blocks of Jamaica, centered around the AirTrain station, as a commercial area. The mixed-use "airport village" was to consist of of space. According to the RPA, the rezoning was part of a proposal to re-envision Jamaica as a "regional center" because of the area's high usage as a ...
Plans to extend the AirTrain to Manhattan were examined even before the system's opening. Between September 2003 and April 2004, several agencies, including the MTA and the Port Authority, conducted a feasibility study of the Lower Manhattan–Jamaica/JFK Transportation Project, which would allow subway or LIRR trains to...
On January 4, 2017, the office of New York Governor Andrew Cuomo announced a $7–10 billion plan to renovate JFK Airport. As part of the project, the AirTrain JFK would either see lengthened trainsets or a direct track connection to the rest of New York City's transportation system, and a direct connection between the A...
In July 2017, Cuomo's office began accepting submissions for master plans to renovate the airport. A year later, in October 2018, Cuomo released details of the project, whose cost had grown to $13 billion. The improvements included lengthening AirTrains as well as adding lanes to the Van Wyck Expressway.
AirTrain JFK connects the airport's terminals and parking areas with the Howard Beach and Jamaica stations. It is located entirely within the New York City borough of Queens. The system consists of three routes: two connecting the terminals with either the Howard Beach or Jamaica stations, and one route looping continu...
The Howard Beach Train route (colored green on the official map) begins and ends at the Howard Beach–JFK Airport station, where there is a direct transfer to the New York City Subway's . It makes an additional stop at Lefferts Boulevard, where passengers can transfer to parking lot shuttle buses; the B15 bus to Brookly...
The Jamaica Station Train route (colored red on the official map) begins and ends at the Jamaica station, adjacent to the Long Island Rail Road platforms there. The Jamaica station contains a connection to the Sutphin Boulevard–Archer Avenue–JFK Airport station on the New York City Subway's . The AirTrain and LIRR stat...
The Howard Beach Train and Jamaica Station Train routes merge at Federal Circle for car rental companies and shuttle buses to hotels and the airport's cargo areas. South of Federal Circle, the routes share track for and enter a tunnel before the tracks separate in two directions for the terminal loop. Both routes conti...
The Airline Terminals Train (colored gold on the official map), an airport terminal circulator, serves the terminals. It makes a continuous clockwise loop around the terminals, operating in the opposite direction to the Howard Beach Train and Jamaica Station Train routes. The terminal-area loop is long.
Trains to and from Jamaica and Howard Beach were originally planned to run every two minutes during peak hours, with alternate trains traveling to each branch. The final environmental impact statement projected that trains in the central terminal area would run every ninety seconds. By 2014 actual frequencies were much...
All AirTrain JFK stations contain elevators and are compliant with the Americans with Disabilities Act of 1990 (ADA). Each platform is long and can fit up to four cars. The stations include air conditioning, as well as platform screen doors to protect passengers and to allow the unmanned trains to operate safely. Each ...
All the stations have island platforms except for Federal Circle, which has a bi-level split platform layout. The Jamaica and Howard Beach stations are designed as "gateway stations" to give passengers the impression of entering the airport. There are also stations at Lefferts Boulevard, as well as Terminals 1, 2, 4, 5...
Except for Terminal 4, all stations in the airport are freestanding structures, and most are connected to their respective terminal buildings by an aerial walkway. Access to Terminal 2 requires passengers to use crosswalks at street level, while the Terminal 4 station is located inside the terminal building itself.
The AirTrain has a total route length of . The system consists of of single-track guideway viaducts and of double-track guideway viaducts. AirTrain JFK is mostly elevated, though there are short segments that run underground or at ground level. The elevated sections were built with precast single and dual guideway span...
The AirTrain runs on steel tracks that are continuously welded across all joints except at the terminals; the guideway viaducts are also continuously joined. Trains use double crossovers at the Jamaica and Howard Beach terminals in order to switch to the track going in the opposite direction. There are also crossover s...
The tracks are set at a gauge of . This enables possible future conversion to LIRR or subway use, or a possible connection to LIRR or subway tracks for a one-trip ride into Manhattan, since these systems use the same track gauge. AirTrain's current rolling stock, or train cars, are not able to use either LIRR or subway...
There are seven electrical substations. The redundancy allows trains to operate even if there are power outages at one substation. Since there are no emergency exits between stations, a control tower can automatically guide the train to its next stop in case of an emergency.
AirTrain JFK is free to use for travel within the terminal area, as well as at the Lefferts Boulevard station, which is located next to the long-term parking, and at the Federal Circle station, where there are car-rental shuttle buses and transfers to and from the airport hotels. Passengers entering or leaving the syst...
AirTrain accepts pay-per-ride MetroCards for $7.75 for transiting through either the Jamaica or Howard Beach gates. The MetroCards are preloaded with monetary value and $7.75 is deducted for each use. Cash and other forms of payment are not accepted. A $1 fee is charged for any new MetroCards.
In addition, two types of AirTrain JFK MetroCards can be purchased from vending machines at Jamaica and Howard Beach. The 30-Day AirTrain JFK MetroCard costs $40 and can be used for unlimited rides on the AirTrain for 30 days after first use. The AirTrain JFK 10-Trip MetroCard costs $25 and can be used for ten trips on...
Transferring to the Q3, Q10, or B15 buses from Terminal 5, or to the subway at Howard Beach and Jamaica, requires an additional $2.75 fare, since the MTA does not offer free transfers from the AirTrain. Passengers pay a total of $10.50 if they transfer between the AirTrain and MTA subways or buses at either Howard Beac...
The fare to enter or exit at Howard Beach and Jamaica was originally $5, though preliminary plans included a discounted fare of $2 for airport and airline employees. The original proposal also called for fare-free travel between airport terminals, a recommendation that was ultimately implemented. In June 2019, the Port...
AirTrain JFK uses Bombardier Transportation's Innovia Metro rolling stock and technology. Similar systems are used on the SkyTrain in Vancouver, Line 3 Scarborough in Toronto, and the Kelana Jaya Line in Kuala Lumpur. The computerized trains are fully automated and use a communications-based train control system with m...
The 32 individual, non-articulated Mark II vehicles operating on the line draw power from a 750 V DC top-running third rail. A linear induction motor pushes magnetically against an aluminum strip in the center of the track. The vehicles also have steerable trucks that can navigate sharp curves and steep grades, as well...
Each car is long and wide, which is similar to the dimensions of rolling stock used on the New York City Subway's B Division. Trains can run in either direction and can consist of between one and four cars. The cars contain two pairs of doors on each side, with each door opening being wide. An individual car has 26 sea...
When AirTrain JFK was being planned, it was expected that 11,000 passengers per day would pay to ride the system between the airport and either Howard Beach or Jamaica, and that 23,000 more daily passengers would use the AirTrain to travel between terminals. This would amount to about 4 million paying passengers and 8....
During the first month of service, an average of 15,000 passengers rode the system each day. Though this figure was less than the expected daily ridership of 34,000, the AirTrain JFK had become the second-busiest airport transportation system in the United States. Within its first six months, AirTrain JFK had transport...
The AirTrain's ridership has risen each year since its opening. A "New York Times" article in 2009 observed that one possible factor in the AirTrain's increasing ridership was the $7.75 fare for AirTrain and subway, which was cheaper than the $52 taxi ride between Manhattan and JFK. In 2019, there were 8.7 million pass...
The South Shore Line is an electrically powered interurban commuter rail line operated by the Northern Indiana Commuter Transportation District (NICTD) between Millennium Station in downtown Chicago and the South Bend International Airport in South Bend, Indiana, United States. The name refers to both the physical line...
The public Monday-Friday timetable shows 20 eastbound trains operating; 18 of those operate out of Millennium Station. Of those, five terminate at Adam Benjamin Metro Center in Gary, seven at South Bend Airport, and 10 at Carroll Avenue station in Michigan City. Two daily trains begin at Carroll Avenue and continue to ...
Westbound, 16 trains operate, with seven originating in South Bend (including one rush-hour express to Millennium Station) and nine originating at Carroll Avenue. Of these, 14 terminate at Millennium Station, while two run from South Bend to Carroll Avenue.
The South Shore Line was constructed between 1901 and 1908 by the Chicago and Indiana Air Line Railway (reorganized as the Chicago, Lake Shore and South Bend Railway [CLS&SB] in 1904). Revenue service between Michigan City and South Bend began on July 1, 1908. The CLS&SB leased the Kensington and Eastern Railroad on Ap...
The power system was changed from 6600 volts AC to 1500 volts DC on July 28, 1926, allowing trains to operate directly to the Illinois Central Railroad's Randolph Street Terminal (now Millennium Station) without an engine change. Trains began running to Randolph Street on August 29. That same year, the original line be...
The Chicago South Shore and South Bend turned a profit during World War II due to the industrial nature of Northern Indiana. However, highway competition and suburban growth led to ridership declines. By the 1950s all interurban lines were seeing a decline in rail travel as automobile use increased. On September 16, 19...
The Chesapeake and Ohio Railway acquired the CSS&SB on January 3, 1967 and continued the operation of passenger services. The Chicago South Shore and South Bend was one of six railroads with long-distance passenger services to decline joining Amtrak in 1971 and in 1976, they asked the Interstate Commerce Commission (IC...
In the late 1980s, the Chicago South Shore and South Bend went bankrupt and on December 29, 1989, passenger service was assumed by NICTD. In December 1990, the track was sold to NICTD and freight service was taken over by the new Chicago South Shore and South Bend Railroad, a subsidiary of short line operator Anacostia...
The railroad began a three-year project in 2009 to replace all catenary on its line between Michigan City and Gary, some of which was nearly 90 years old. The project cost $18 million, and caused service disruptions on weekends while new wires were strung.
The Chicago Region Environmental and Transportation Efficiency Program (CREATE), replaced a bridge on the South Shore Line across 130th Street, Torrence Avenue, and Norfolk Southern tracks in the Hegewisch neighborhood of Chicago as a part of a four-year project lasting from 2011 to 2015. The 2,350 ton bridge would be ...
In 2015 NICTD began an express service between South Bend and Chicago. Targeted at business travelers, the train makes just two intermediate stops: Dune Park and East Chicago. The total scheduled travel time is 1 hour 55 minutes, more than thirty minutes faster than existing services.
In July 2020 during the COVID-19 pandemic, NICTD implemented "mask optional cars" for riders choosing not to wear masks, as Indiana did not have a statewide mask mandate. This has received controversial reception, as it does not help slow down the spread of the coronavirus disease, and the "mask optional" car is also t...
Departing South Bend Airport, the South Shore Line heads south alongside Bendix Drive, then west along Westmoor Street, before connecting with the tracks that ran to its former terminus. Between that point and Hudson Lake, Indiana, the South Shore Line runs parallel to Norfolk Southern's Chicago Line, also used by Amtr...
The line is quadruple tracked along the section shared with the Metra Electric line from Millennium Station to Kensington/115th Street, double-tracked from Kensington/115th Street to east of Gary Metro Center. From there it is single-tracked with passing sidings to South Bend Airport, save for a stretch of double track...
The South Shore Line operates with a fleet of 82 rail cars built between 1982 and 2009 by Nippon Sharyo. The fleet consists of 58 single-level self-propelled cars, 10 single-level unpowered trailers, and 14 bilevel self-propelled cars. The single level fleet's design shares commonalities with MARC's locomotive-hauled M...
Pullman-Standard and the Standard Steel Car Company delivered electric multiple units to the CSS&SB between 1926 and 1929. Many were lengthened in the 1940s and 1950s.
Since 2005, there has been an ongoing debate pertaining to plans to relocate trackage off the streets of Michigan City. In July 2009, NICTD announced its intention to relocate the Michigan City track south of its current location in order to smooth out the curves, cut down the number of grade crossings, increase speed ...
At a legislative hearing in October 2008, NICTD officials said they would drop further study of a Munster-to-Valparaiso route, and begin study of a Gary–Valparaiso route. At the hearing, NICTD officials said the projected cost of $673 million for the Munster-to-Valparaiso route as well as low projected ridership would ...
In the 1980s and 1990s, there was some discussion about the possibility of extending the line from South Bend east to Elkhart County, Indiana. In 1988, Elkhart, Indiana mayor James Perron pushed for the government to look into making long-term plans for an extension into his city. It is analogous of Metra Electric Line...
NICTD planned to apply for federal funding for a preliminary engineering study and environmental survey of a Hammond-to-Lowell leg in 2009. , that leg had a projected price tag of $551 million. , the cost has increased to $665 million. NICTD was awarded funding in the spring of 2020 and the line broke ground in October...
The new line will run through Munster to Dyer, with a possible later extension to St. John, and trains will run as shuttles between Hammond and Dyer during off-peak hours. The alignment of the new branch leaves the old CSS&SB main immediately before the current Hammond station. Hence, the NICTD has decided to build a n...
The line operates over the tracks of the Metra Electric Line from Millennium Station to Kensington-115th Street. Metra owns the track in this territory. Per a long-standing non-compete clause with Metra, outbound South Shore Line trains to Indiana only stop at Metra Electric stations to receive passengers; inbound trai...
South Shore Line trains make the following station stops:
The Pacific Surfliner is a passenger train service serving the communities on the coast of Southern California between San Diego and San Luis Obispo.
The service carried 2,924,117 passengers during fiscal year 2016, a 3.4% increase from FY2015. Total revenue during FY2016 was $73,020,267, an increase of 3.6% over FY2015. The "Pacific Surfliner" is Amtrak's third-busiest service (exceeded in ridership only by the "Northeast Regional" and "Acela Express"), and the bus...
Like all regional trains in California, the "Pacific Surfliner" is operated by a joint powers authority. The Los Angeles – San Diego – San Luis Obispo (LOSSAN) Rail Corridor Agency is governed by a board that includes eleven elected representatives from the six counties the train travels through. LOSSAN contracts with ...
The San Luis Obispo-San Diego trip takes approximately 8½ hours with an average speed of ; maximum track speed is . Much of the "Pacific Surfliner's" scenic route follows the Pacific coast, with the tracks being less than 100 feet from the ocean in some locations. However, trains travel inland through expansive farmlan...
The "Pacific Surfliner" operates thirteen daily round trips between Los Angeles and San Diego. Five round trips run north of Los Angeles: two to San Luis Obispo, and three to Goleta with Thruway Motorcoach connections to San Luis Obispo. Thruway Motorcoach connections are also available to San Pedro; to Palm Springs an...
Because the San Luis Obispo and Goleta stations are not designed to turn equipment, and the San Diego Santa Fe Depot requires a time-consuming deadhead movement into a wye located about 16 miles to the north in Miramar, trains are operated in push-pull mode. The locomotive is at the rear of the train, pushing the train...
Local agencies along with the host railroads formed the Los Angeles–San Diego-San Luis Obispo Rail Corridor Agency (LOSSAN) in 1989.
A stop at Old Town Transit Center was added in 2004. Stops at Orange and Laguna Niguel/Mission Viejo were added in 2007 but dropped in 2012. On October 7, 2013, stops were added at Coaster stations at Carlsbad Village, Carlsbad Poinsettia, Encinitas and Sorrento Valley. The Carlsbad Poinsettia and Encinitas stops were ...
A 13th daily round trip was added on October 14, 2019.
The "Pacific Surfliner" runs on track owned by several private railroads and public agencies:
The Surfliner cars were introduced in 2000-02, and were designed specifically to handle the demands of the nation's third-busiest rail line. They replaced the California Cars which had been introduced on the then-"San Diegan" in 1996, and had been fraught with problems in the latter part of the 1990s.
A dedicated fleet of 14 Caltrans-owned Siemens Charger locomotives began pre-revenue testing in October 2018 and entered revenue service later that year. The Chargers replaced a fleet of 15 Amtrak-owned EMD F59PHI locomotives (built in 1998), which were sold to Metra on March 2, 2019. Amtrak-owned GE P42DC locomotives ...
Additional Amtrak-owned cars are added (up to 12-car consists) during periods of high demand, including the San Diego Comic-Con, the San Diego County Fair, events at the Del Mar racetrack, and after the 2018 Southern California mudflows closed Highway 101. Amtrak Great Dome car "Ocean View" was occasionally used as an ...
The East Boston Tunnel under Boston Harbor was the first North American subway tunnel to run beneath a body of water when it opened in 1904, and the second underwater vehicular tunnel of significant length built in the United States. The tunnel was constructed using a modified version of the Greathead Shield; of the tu...
Initially used as a streetcar tunnel, it ran from Maverick Square in East Boston to downtown Boston's Court Street station, with an intermediate stop at Devonshire (now State). Court Street had pedestrian access to Scollay Square station (now Government Center) but transfers to the East Boston Tunnel required an additi...
The Boston Elevated Railway (BERy) began an extension towards Beacon Hill in 1912. This downtown extension was opened to Bowdoin, with an intermediate stop at Scollay Under (now Government Center), on March 18, 1916. Immediately west of the new Bowdoin station platforms, a tight turnaround loop track underground allowe...
The East Boston Tunnel was originally planned to be operated with high-floor metro rolling stock and connected to the then-planned Cambridge Elevated line. When that plan was dropped in 1903 due to a disagreement between the Boston Transit Commission and the BERy, the stations were built with low platforms. Large bi-lo...
In 1921, the Boston Transit Department (BTD)—the successor to the BTC—began work at Maverick Square to convert the East Boston Tunnel to high-floor metro trains. The next year, the BTD board approved the construction of high-level platforms at the four downtown stations. The Maverick Square incline was replaced with Ma...
Over the weekend of April 18–21, 1924, the East Boston Tunnel was converted to use the new high-floor trains. The tightly-staged changeover required 1500 men to complete. Temporary wooden platform sections were put in place to allow service to begin on April 21, with the permanent concrete sections completed over the f...
From 1952 to 1954, a surface-level extension was constructed along the recently-defunct Boston, Revere Beach and Lynn Railroad, from Maverick to the current terminus at Wonderland. The original trackage had been narrow gauge, but was converted to standard gauge for this Revere Extension of the subway. The first above-g...
The line was officially renamed the East Boston Tunnel & Revere Extension by the MTA in 1952, and designated as "Route 3" on system maps. It was renamed as the Blue Line on August 26, 1965, as part of the new MBTA's color-based rebranding. The color blue represented water, as the line passes under Boston Harbor and tra...
On April 21, 2018 the SL3 Silver Line service to Chelsea opened with a connection to the Blue Line at Airport station, providing transfer service to Chelsea, the Seaport District and South Station.
The first main construction phase of the project began on June 25, 1994, the line was cut back to at all times to permit reconstruction of the outer stations. and were completely rebuilt, while , and were renovated. A simultaneous $8 million noise reduction program added sound walls at Beachmont and Orient Heights, rub...
was closed from October 14, 2000 until October 29, 2001 for renovations, which were completed in 2003. A relocated station opened on June 3, 2004. An extension renovation of , during which the station remained open, lasted from November 2004 to May 2011.
Reconstruction of began on October 4, 2005. The project was sufficiently progressed for six-car trains to enter service on September 15, 2008, though the station was not completed until 2009. Orient Heights was closed from March 23 to November 26, 2013 for a complete reconstruction. closed from March 22, 2014 to March ...
There is a proposal to extend the Blue Line northward to Lynn, Massachusetts. The land to extend the line was purchased for the initial construction of the Revere Extension, but due to budgetary constraints Wonderland station was designated the northern terminus. Two potential extension routes have been identified. One...
In 2005, Lieutenant Governor Kerry Healy estimated construction would begin in 2017. Authorization to bond for planning money for the project was included in an April 2008 state bond bill, and $25 million in federal earmarks have been obtained. A 2004 state bond bill authorized $246.5 million on the condition of findin...
The Blue Line and Red Line are currently the only MBTA subway rail lines without a direct transfer to each other; passengers must ride one stop on the Green or Orange lines to transfer. The proposed Red–Blue connector would extend the Blue Line west from Bowdoin to an underground platform at Charles/MGH station, allowi...
An extension of the East Boston Tunnel to Charles Street was considered in a 1924 study of Charles station. A 1926 proposal to convert the Tremont Street subway and connecting streetcar lines into a pair of rapid transit trunk lines called for the East Boston Tunnel to be extended south to Park Street station, with thr...
The rise of Kendall Square as a major employment center, the coming of the Red Line Northwest Extension, and increased traffic to Logan Airport created demand in the 1970s for a direct connection between the Red and Blue lines. A 1974 state plan again proposed an extension to Park Street, while the 1978 and 1983 Progra...
In 1991, the state agreed to built a set of transit projects as part of the settlement of a lawsuit by the Conservation Law Foundation (CLF) over auto emissions from the Big Dig project. Among these projects was A Red Line–Blue Line connector, to be complete by the end of 2011. The 2003–07 reconstruction of Charles/MGH...
A 2018 MBTA long-range planning document considered a pedestrian tunnel between the Orange Line platforms at and , which would allow transfers between the Red and Blue lines similar to (though longer than) the Winter Street Concourse between the Green and Orange lines.
The North–South Rail Link is a proposed MBTA Commuter Rail and Amtrak tunnel which would link North and South Stations, which are currently stub-end terminals. In one of several options, the new tunnel would serve three new stations, two underground near the existing terminals and a third connecting to the Blue Line's ...
The MBTA awarded the $174 million construction contract for the 94 cars in November 2001, with a total program cost of $200 million. The first deliveries were scheduled for January 2004, but ultimately delayed to 2007 due to manufacturing issues. The first set entered revenue service on February 20, 2008. The first thr...
The first generation of high-floor rolling stock on the line were the No. 1 and No. 2 East Boston Rapid Transit cars, which were built by Pullman-Standard in 1923–1924 when the line was converted from streetcar operation to rapid transit. These were supplemented by the No. 3 fleet, built in 1951 by St. Louis Car Compan...
The A Line, officially called the University of Colorado A Line for sponsorship reasons, is a Regional Transportation District (RTD) commuter rail line serving Denver and Aurora, Colorado, operating between Downtown Denver and Denver International Airport (DIA). During planning and construction the A Line was also know...
Mass transit has been under consideration for the corridor between Downtown Denver and Denver International Airport since the latter was proposed in the 1980s. The project gathered momentum in 1997 when a Major Investment Study was completed for the corridor, encouraging fixed-guideway mass transit (light rail or commu...
RTD designated the line with the letter “A”, denoting service to the airport and Aurora. Groundbreaking for the A Line was held on August 26, 2010. As the second line of RTD’s FasTracks expansion plan, the East Corridor was constructed and operated under the Eagle P3 public–private partnership. The first electric multi...
Revenue service began on April 22, 2016. A software problem in the equipment closing the crossing gates has resulted in the use of traffic guards and frequent delays since the opening, earning the project a slot on Westword's 2016 Colorado Hall of Shame.
Since the A line's opening in April 2016, it has had a number of operational issues. The main issue is with the crossing gate technology. Crossing arms have been coming down too early and staying down too long, causing traffic backups. Today, RTD is making progress in fixing the crossing gate timing system along the A ...
In June 2018, the FRA approved a plan to remove the flaggers monitoring the crossing gates along the A line. This approval also allows local jurisdictions to submit requests to the FRA to establish "quiet zones", removing the need for trains crossing through the gates to blow their horns.
The A Line route follows and remains within a mile of Interstate 25, Interstate 70, and the airport access highway (Peña Boulevard). The line makes use of a preexisting Union Pacific Railroad right-of-way along the portion of the route from downtown Denver heading east, then deviates to the north along Peña Boulevard i...
The Orange Line is a rapid transit line in Chicago, Illinois, operated by the Chicago Transit Authority as part of the Chicago "L" system. It is approximately long and runs on elevated and at grade tracks and serves the Southwest Side, running from the Loop to Midway International Airport. As of 2019, an average of 27,...