Dataset Viewer
Auto-converted to Parquet Duplicate
metro_slug
stringclasses
45 values
metro
stringclasses
45 values
state
stringclasses
31 values
month
int64
1
12
month_name
stringclasses
12 values
year
int64
2.02k
2.03k
lost_workdays
float64
0
23
atlanta-ga
Atlanta
GA
1
January
2,016
14
atlanta-ga
Atlanta
GA
1
January
2,017
13
atlanta-ga
Atlanta
GA
1
January
2,018
13
atlanta-ga
Atlanta
GA
1
January
2,019
17
atlanta-ga
Atlanta
GA
1
January
2,020
18
atlanta-ga
Atlanta
GA
1
January
2,021
14
atlanta-ga
Atlanta
GA
1
January
2,022
14
atlanta-ga
Atlanta
GA
1
January
2,023
19
atlanta-ga
Atlanta
GA
1
January
2,024
17
atlanta-ga
Atlanta
GA
1
January
2,025
17
atlanta-ga
Atlanta
GA
2
February
2,016
16
atlanta-ga
Atlanta
GA
2
February
2,017
11
atlanta-ga
Atlanta
GA
2
February
2,018
11
atlanta-ga
Atlanta
GA
2
February
2,019
18
atlanta-ga
Atlanta
GA
2
February
2,020
17
atlanta-ga
Atlanta
GA
2
February
2,021
14
atlanta-ga
Atlanta
GA
2
February
2,022
8
atlanta-ga
Atlanta
GA
2
February
2,023
16
atlanta-ga
Atlanta
GA
2
February
2,024
12
atlanta-ga
Atlanta
GA
2
February
2,025
11
atlanta-ga
Atlanta
GA
3
March
2,016
10
atlanta-ga
Atlanta
GA
3
March
2,017
18
atlanta-ga
Atlanta
GA
3
March
2,018
20
atlanta-ga
Atlanta
GA
3
March
2,019
13
atlanta-ga
Atlanta
GA
3
March
2,020
14
atlanta-ga
Atlanta
GA
3
March
2,021
13
atlanta-ga
Atlanta
GA
3
March
2,022
17
atlanta-ga
Atlanta
GA
3
March
2,023
10
atlanta-ga
Atlanta
GA
3
March
2,024
14
atlanta-ga
Atlanta
GA
3
March
2,025
9
atlanta-ga
Atlanta
GA
4
April
2,016
13.1
atlanta-ga
Atlanta
GA
4
April
2,017
9
atlanta-ga
Atlanta
GA
4
April
2,018
14.1
atlanta-ga
Atlanta
GA
4
April
2,019
17.1
atlanta-ga
Atlanta
GA
4
April
2,020
16.1
atlanta-ga
Atlanta
GA
4
April
2,021
6
atlanta-ga
Atlanta
GA
4
April
2,022
6
atlanta-ga
Atlanta
GA
4
April
2,023
7
atlanta-ga
Atlanta
GA
4
April
2,024
11.1
atlanta-ga
Atlanta
GA
4
April
2,025
15.1
atlanta-ga
Atlanta
GA
5
May
2,016
10
atlanta-ga
Atlanta
GA
5
May
2,017
10
atlanta-ga
Atlanta
GA
5
May
2,018
10
atlanta-ga
Atlanta
GA
5
May
2,019
5
atlanta-ga
Atlanta
GA
5
May
2,020
12
atlanta-ga
Atlanta
GA
5
May
2,021
9
atlanta-ga
Atlanta
GA
5
May
2,022
9
atlanta-ga
Atlanta
GA
5
May
2,023
12
atlanta-ga
Atlanta
GA
5
May
2,024
9
atlanta-ga
Atlanta
GA
5
May
2,025
18
atlanta-ga
Atlanta
GA
6
June
2,016
5
atlanta-ga
Atlanta
GA
6
June
2,017
20
atlanta-ga
Atlanta
GA
6
June
2,018
17
atlanta-ga
Atlanta
GA
6
June
2,019
15
atlanta-ga
Atlanta
GA
6
June
2,020
17
atlanta-ga
Atlanta
GA
6
June
2,021
12
atlanta-ga
Atlanta
GA
6
June
2,022
8
atlanta-ga
Atlanta
GA
6
June
2,023
14
atlanta-ga
Atlanta
GA
6
June
2,024
4
atlanta-ga
Atlanta
GA
6
June
2,025
13
atlanta-ga
Atlanta
GA
7
July
2,016
15
atlanta-ga
Atlanta
GA
7
July
2,017
16
atlanta-ga
Atlanta
GA
7
July
2,018
15
atlanta-ga
Atlanta
GA
7
July
2,019
5
atlanta-ga
Atlanta
GA
7
July
2,020
17
atlanta-ga
Atlanta
GA
7
July
2,021
16
atlanta-ga
Atlanta
GA
7
July
2,022
18
atlanta-ga
Atlanta
GA
7
July
2,023
11
atlanta-ga
Atlanta
GA
7
July
2,024
15
atlanta-ga
Atlanta
GA
7
July
2,025
7
atlanta-ga
Atlanta
GA
8
August
2,016
12
atlanta-ga
Atlanta
GA
8
August
2,017
6
atlanta-ga
Atlanta
GA
8
August
2,018
9
atlanta-ga
Atlanta
GA
8
August
2,019
11
atlanta-ga
Atlanta
GA
8
August
2,020
19
atlanta-ga
Atlanta
GA
8
August
2,021
12
atlanta-ga
Atlanta
GA
8
August
2,022
22
atlanta-ga
Atlanta
GA
8
August
2,023
14
atlanta-ga
Atlanta
GA
8
August
2,024
9
atlanta-ga
Atlanta
GA
8
August
2,025
12
atlanta-ga
Atlanta
GA
9
September
2,016
12
atlanta-ga
Atlanta
GA
9
September
2,017
10
atlanta-ga
Atlanta
GA
9
September
2,018
2
atlanta-ga
Atlanta
GA
9
September
2,019
3
atlanta-ga
Atlanta
GA
9
September
2,020
14
atlanta-ga
Atlanta
GA
9
September
2,021
13
atlanta-ga
Atlanta
GA
9
September
2,022
8
atlanta-ga
Atlanta
GA
9
September
2,023
11
atlanta-ga
Atlanta
GA
9
September
2,024
3
atlanta-ga
Atlanta
GA
9
September
2,025
2
atlanta-ga
Atlanta
GA
10
October
2,016
0
atlanta-ga
Atlanta
GA
10
October
2,017
13
atlanta-ga
Atlanta
GA
10
October
2,018
6
atlanta-ga
Atlanta
GA
10
October
2,019
14
atlanta-ga
Atlanta
GA
10
October
2,020
11
atlanta-ga
Atlanta
GA
10
October
2,021
8
atlanta-ga
Atlanta
GA
10
October
2,022
6
atlanta-ga
Atlanta
GA
10
October
2,023
6
atlanta-ga
Atlanta
GA
10
October
2,024
2
atlanta-ga
Atlanta
GA
10
October
2,025
9
End of preview. Expand in Data Studio

US Construction Weather Delay Days by Metro (2016–2025)

How many workdays construction sites actually lose to weather, month by month, for 45 US metropolitan areas — derived from ten years of NOAA daily station observations run through a soil-specific drying model.

This is not a rainfall dataset. Rainfall is the input; the output is unworkable workdays, which is the unit construction schedules and contracts are actually written in. The distinction matters more than it sounds: in 26 of the 45 metros here, the wettest month is not the worst month.

Published by Ilystics. Landing page with per-metro breakdowns: https://ilystics.com/weather-delay-days

Files

weather_delay_days_monthly.csv — 540 rows (45 metros × 12 months)

Column Description
metro_slug Stable identifier, e.g. raleigh-durham-nc
metro, state Display name and USPS state code
lat, lng Metro centre; the NOAA station picker resolves from here
soil Representative soil for the metro: clay, silt or sand (see caveats)
base_drying_days Days to regain trafficability after meaningful rain: clay 3.0, silt 2.0, sand 0
baseline_start_year, baseline_end_year Observation window (2016–2025)
month, month_name Calendar month, 1–12
avg_precip_inches Ten-year mean monthly precipitation
lost_workdays_mean Ten-year mean of unworkable workdays. The headline figure.
lost_workdays_median Middle year of the ten; above the mean implies dry-year skew
abnormal_threshold Mean + 1 standard deviation (see caveat below)
drying_days_per_rain_day Additional unworkable days each rain day generates
workday_coverage_pct Share of workdays with a station reading

weather_delay_days_by_year.csv — 5,400 rows

The per-year detail behind every mean above (45 × 12 × 10). Published so the distribution can be inspected rather than taken on trust — a monthly average conceals whether ten years were alike or wildly different.

Method

A day counts as lost when it is a Monday–Friday on which any of the following holds:

  1. Precipitation exceeded 0.1 inch, which resets a drying clock
  2. The ground had not finished drying from earlier rain — duration set by soil type (clay 3.0 days, silt 2.0, mixed 1.5, sand/rock 0 — only clay, silt and sand occur in this dataset), adjusted for temperature, slope, exposure and antecedent moisture
  3. The ground was frozen (max temp < 32°F), with the clock reset on thaw

Weekends are excluded. Days with no station reading are excluded rather than assumed workable.

Full methodology: https://ilystics.com/methodology

Important caveats

Soil is one representative type per metro. Each metro is assigned a single governing soil applied to the whole market — clay (19 metros), silt (16) or sand (10). It is not a spatial average and not a per-site lookup. Real soils vary substantially within any metro, and because the drying clock runs 3.0 days on clay against 0 on sand, site-level results can differ considerably from the metro figure. For a specific location, resolve the actual NRCS map unit rather than using the metro row.

Concretely: this dataset lists Raleigh-Durham as clay with a 3.0-day clock, while an NRCS lookup for ZIP 27606 inside that same metro returns the Beltline-Urban land-Cecil complex and a 1.5-day clock. Both are correct at their own resolution. The metro row is a planning figure, not a site figure.

abnormal_threshold is a convention, not a standard. It is the ten-year mean plus one standard deviation. It is useful for operationalising the contractual phrase "abnormal" or "unusually severe", which appears undefined in AIA A201, FAR 52.249-10 and ConsensusDocs 200 alike. No court, board or contract has adopted this definition. The per-year file is published precisely so anyone can argue for a different line.

Scope is soil-dependent site work only — earthwork, grading, excavation, foundations and underground utilities. Enclosed and vertical construction, roofing, and paving laydown are not modelled.

Do not sum the months into an annual total. The monthly baselines are independent. Adding them assumes a site never improves over a year, when stone haul roads, stabilised pads and ditching go in over the first months of a job. A twelve-month sum produces a number no site contractor would recognise.

8 of 540 rows have an empty drying_days_per_rain_day. All are desert or Mediterranean-climate metros in their dry season (Phoenix in May, Las Vegas in July, Los Angeles and Sacramento in summer) where there were no rain workdays to divide by. Zero lost workdays, no divisor — the blank is correct.

Findings worth checking

  • The wettest month is not the worst month in 26 of 45 metros. Boston is the clearest case: July averages 4.28" and loses 8 workdays, while January averages 3.69" and loses 16. Less rain, double the loss. Winter rain arrives spread out onto cold ground and each event collects its own drying tail; summer storms cluster and their tails overlap.
  • Worst single month: Minneapolis in January, ~20 lost workdays.
  • Widest seasonal swing: Portland, 18 lost workdays in January against 1 in July.

Source and licence

Derived from NOAA National Centers for Environmental Information, Global Historical Climatology Network – Daily (GHCND) — US Government public domain station observations.

Released under CC BY 4.0. Attribution: Ilystics LLC, https://ilystics.com

Model version v2.3.0. Machine-readable per-metro JSON is also served at https://ilystics.com/data/weather-delay-days/{metro_slug}.json.

Downloads last month
45