Priority 3: Team Assignments & Individual Tasks (Nov 18-22)
Execution Date: Nov 18 (Monday) β Nov 22 (Friday) Approval Status: β Option C APPROVED First Daily Standup: Nov 18, 09:15 AM
TEAM 1: Design System Foundation (2 people-days)
Team Members
- Lead: Chief GUI Designer
- Support: Frontend Architect 3 (50% time)
Individual Assignments
Chief GUI Designer (Full-time, Mon-Fri)
Monday Nov 18 (0.5 days)
- 09:00-09:30: Attend kickoff meeting
- 09:30-10:30: Review existing components in codebase
- File:
apps/widget-board/components/**/*.tsx - Count and categorize all components
- File:
- 10:30-12:30: Start documenting component hierarchy
- Identify base components (Button, Input, Card, etc.)
- Identify composite components (Form, Modal, etc.)
- Identify layout components (Header, Sidebar, etc.)
- 13:30-17:00: Document naming conventions
- Prefix system for different component types
- Event handler naming (onSubmit, onChange, etc.)
- Prop naming standards
Tuesday Nov 19 (1 day)
- 09:00-12:00: Complete color system documentation
- Primary, secondary, accent colors
- Neutral palette (grays)
- Semantic colors (success, error, warning, info)
- Accessibility contrast checks
- 13:00-17:00: Document typography system
- Font families (primary, monospace, etc.)
- Font sizes (scale: xs, sm, base, lg, xl, 2xl, etc.)
- Font weights (regular, medium, semibold, bold)
- Line heights and letter spacing
Wednesday Nov 20 (0.5 days)
- 09:00-12:00: Document spacing system
- Base unit: 8px
- Scale: 4px (0.5), 8px (1), 16px (2), 24px (3), etc.
- Padding standards
- Margin standards
- Gap standards for flexbox/grid
- 13:00-17:00: Document accessibility requirements
- WCAG 2.1 AA compliance standards
- Color contrast ratios (4.5:1 for text)
- Focus states
- Keyboard navigation
- ARIA attributes
Thursday Nov 21 (0.5 days)
- 09:00-12:00: Create component documentation template
- Props documentation format
- Usage examples format
- Accessibility notes format
- 13:00-16:00: Write usage guidelines for 3-4 primary components (Button, Input, Card, Modal)
- 16:00-17:00: Final review with Frontend Architect 3
Friday Nov 22 (0.5 days)
- 09:00-11:00: Final polish and sign-off on standards document
- 11:00-12:00: Prepare handoff to Team 2
- 13:00-17:00: Available for Q&A and Storybook integration support
Frontend Architect 3 (50% time, support role)
Monday Nov 18 (0.25 days)
- 09:00-09:30: Attend kickoff meeting
- 09:30-10:30: Review current component implementations
- 10:30-12:00: Provide technical input on hierarchy
Tuesday-Wednesday (Nov 19-20) (0.75 days)
- 09:00-11:00: Technical review of color/typography systems
- 14:00-16:00: Accessibility standards review
Thursday Nov 21 (0.5 days)
- 14:00-17:00: Final technical review and QA
Friday Nov 22 (0.25 days)
- 09:00-11:00: Final sign-off
- 13:00-17:00: Available for support
Deliverable
File: design-system/DESIGN_SYSTEM_STANDARDS.md
- Component hierarchy (all 20+ components)
- Naming conventions with examples
- Color system (semantic + accessibility)
- Typography scale
- Spacing system (8px base)
- Accessibility requirements (WCAG 2.1 AA)
- Component documentation template
- Usage guidelines for primary components
Definition of Done
- Document complete and reviewed
- All team members have access
- Ready for Storybook integration
TEAM 2: Storybook Infrastructure (1.5 people-days)
Team Members
- Lead: Frontend Architect 3 (50% time, full dedication to this work)
- Support: Technical Writer (50% time)
Individual Assignments
Frontend Architect 3 (Full-time, Mon-Fri dedicated to Storybook)
Monday Nov 18 (0.5 days)
- 09:00-09:30: Attend kickoff meeting
- 10:00-12:30: Install Storybook 7.x
- Create
.storybook/main.tsconfiguration - Install required dependencies
- Configure Vite integration
- Set up static folder
- Create
- 13:30-17:00: Configure Chromatic
- Create Chromatic account/project
- Install Chromatic CLI
- Set up authentication tokens
Tuesday Nov 19 (0.5 days)
- 09:00-12:00: Set up Storybook addons
- @storybook/addon-links
- @storybook/addon-essentials
- @storybook/addon-interactions
- @storybook/addon-a11y (accessibility)
- @storybook/addon-controls
- 13:00-17:00: Create CSF (Component Story Format) templates
- Template for simple component story
- Template for interactive story with controls
- Template for accessibility story
Wednesday Nov 20 (0.25 days)
- 09:00-11:00: Configure Storybook build pipeline
- Set up npm script:
npm run storybook - Set up build script:
npm run build-storybook - Configure static hosting
- Set up npm script:
Thursday Nov 21 (0.25 days)
- 09:00-12:00: Test Storybook locally
- Verify all addons working
- Test Chromatic integration
- Document any issues
Friday Nov 22 (0.25 days)
- 09:00-11:00: Final testing and documentation
- 11:00-12:00: Handoff to story authors
Technical Writer (50% time, Mon-Fri)
Monday Nov 18 (0.25 days)
- 14:00-17:00: Attend kickoff and observe setup
Tuesday Nov 19 (0.5 days)
- 09:00-12:00: Document story writing standards
- CSF format explanation
- Props documentation in stories
- Accessibility considerations
- 13:00-17:00: Create quick-start guide for story authors
Wednesday-Thursday (Nov 20-21) (0.5 days)
- 09:00-11:00: Create component story examples
- 14:00-17:00: Review and refine documentation
Friday Nov 22 (0.25 days)
- 09:00-11:00: Final documentation polish
- 13:00-17:00: Available for Q&A
Deliverable
File: storybook/STORYBOOK_SETUP.md
- Installation steps completed
- Chromatic integration configured
- CSF templates ready
- Story writing standards documented
- Quick-start guide for authors
- Configuration files (
.storybook/main.ts, etc.)
Definition of Done
- Storybook running locally
- Chromatic integration verified
- Story templates ready for use
- 100+ stories can start writing Dec 8
TEAM 3: E2E Test Planning (3 people-days)
Team Members
- Lead: QA Engineer 1
- Support: QA Engineer 2
Individual Assignments
QA Engineer 1 (Lead, Mon-Fri)
Monday Nov 18 (0.75 days)
- 09:00-09:30: Attend kickoff meeting
- 09:30-11:00: Review Phase 1.C blocks and requirements
- Block 1: Design System (100+ stories, component library)
- Block 2: E2E Tests + Performance optimization
- Block 3: Security + GDPR compliance
- Block 4: Quality gate
- 11:00-12:30: Plan test coverage strategy
- 14:00-17:00: Start designing critical user journey tests
Tuesday Nov 19 (0.75 days)
- 09:00-12:00: Design E2E test scenarios (50+ scenarios)
- Critical path tests (core functionality)
- Happy path tests (normal use cases)
- Error handling tests
- Edge case tests
- 13:00-17:00: Continue scenario design (continue to 100+)
Wednesday Nov 20 (0.75 days)
- 09:00-12:00: Design cross-browser test matrix
- Chrome (latest 2 versions)
- Firefox (latest 2 versions)
- Safari (latest 2 versions)
- Edge (latest 2 versions)
- Mobile (iOS Safari, Chrome Mobile)
- 13:00-17:00: Design accessibility testing scenarios
- Keyboard navigation tests
- Screen reader compatibility
- WCAG 2.1 AA compliance tests
Thursday Nov 21 (0.5 days)
- 09:00-12:00: Document expected results for each test
- 13:00-16:00: Review all 100+ scenarios with QA Engineer 2
- 16:00-17:00: Finalize test plan
Friday Nov 22 (0.25 days)
- 09:00-11:00: Final sign-off and handoff
- 13:00-17:00: Available for Q&A
QA Engineer 2 (Support, Mon-Fri)
Monday Nov 18 (0.5 days)
- 09:00-09:30: Attend kickoff meeting
- 09:30-11:00: Review testing requirements
- 11:00-12:30: Map test environment needs
Tuesday-Wednesday (Nov 19-20) (1 day)
- 09:00-12:00: Create test data generators
- User fixtures (valid, invalid, edge cases)
- Mock data generators
- Test database setup scripts
- 13:00-17:00: Document test environment requirements
Thursday Nov 21 (0.5 days)
- 09:00-12:00: Create Playwright test templates
- Page object models
- Helper functions
- Assertion helpers
- 13:00-17:00: Review with QA Engineer 1
Friday Nov 22 (0.25 days)
- 09:00-11:00: Final documentation
- 13:00-17:00: Available for Q&A
Deliverable
File: testing/E2E_TEST_PLAN.md
- 100+ test scenarios documented
- Cross-browser testing matrix
- Test data generators
- Accessibility testing scenarios
- Playwright templates
- Test environment requirements
- Test execution checklist
Definition of Done
- 100+ scenarios documented with steps
- All browsers defined
- Test data generators created
- Execution ready for Phase 1.C Dec 8
TEAM 4: Performance Infrastructure (2 people-days)
Team Members
- Lead: Frontend Performance Specialist
- Support: DevOps Engineer 2 (50% time)
Individual Assignments
Frontend Performance Specialist (Full-time, Mon-Fri)
Monday Nov 18 (0.5 days)
- 09:00-09:30: Attend kickoff meeting
- 09:30-11:00: Review current performance baseline
- FCP (First Contentful Paint) current: _____
- LCP (Largest Contentful Paint) current: _____
- CLS (Cumulative Layout Shift) current: _____
- INP (Interaction to Next Paint) current: _____
- 11:00-12:30: Document performance targets
- FCP target: <1.5s
- LCP target: <2.5s
- CLS target: <0.1
- INP target: <200ms
- 13:30-17:00: Start setting up Core Web Vitals monitoring
Tuesday Nov 19 (0.75 days)
- 09:00-12:00: Complete Core Web Vitals monitoring setup
- web-vitals library integration
- Analytics collection
- Dashboard visualization
- 13:00-17:00: Set up performance profiling tools
- Lighthouse integration (automated)
- Browser DevTools configuration
- Performance API instrumentation
Wednesday Nov 20 (0.5 days)
- 09:00-12:00: Document optimization workflow
- How to identify bottlenecks
- How to profile performance
- How to implement optimizations
- 13:00-17:00: Create performance optimization guide
Thursday Nov 21 (0.25 days)
- 09:00-12:00: Test all monitoring dashboards
- 13:00-17:00: Review with DevOps Engineer 2
Friday Nov 22 (0.25 days)
- 09:00-11:00: Final documentation and sign-off
- 13:00-17:00: Available for support
DevOps Engineer 2 (50% time, support)
Monday Nov 18 (0.25 days)
- 14:00-17:00: Attend kickoff and understand requirements
Tuesday Nov 19 (0.5 days)
- 09:00-12:00: Configure CI/CD performance gates
- FCP <1.5s check in CI
- LCP <2.5s check in CI
- CLS <0.1 check in CI
- Bundle size tracking
- 13:00-17:00: Set up automated bundle size analysis
Wednesday-Thursday (Nov 20-21) (0.5 days)
- 09:00-12:00: Configure production monitoring
- Alerting rules
- Performance degradation detection
- 13:00-17:00: Test all CI/CD gates
Friday Nov 22 (0.25 days)
- 09:00-11:00: Final validation
- 13:00-17:00: Available for support
Deliverable
File: performance/PERFORMANCE_INFRASTRUCTURE.md
- Core Web Vitals monitoring operational
- CI/CD performance gates configured
- Bundle size tracking enabled
- Performance profiling tools ready
- Optimization workflow documented
- Dashboard and alerting configured
Definition of Done
- All monitoring operational
- CI/CD gates working
- Dashboards accessible
- Team trained on tools
π Daily Standup Format (09:15 AM Daily)
All Team Leads + System Director
Each team lead (2 minutes):
- β What was completed yesterday
- π― What's planned for today
- π¨ Any blockers or risks
Blocker Discussion (if any):
- 3-5 minutes per blocker
- Define action and owner
- Resolve or escalate
Total Time: 15 minutes max
π Friday Nov 22 Celebration
17:00 - End of Week 1 Celebration
All 4 teams complete their deliverables:
- β Design System Standards (Team 1)
- β Storybook Infrastructure (Team 2)
- β E2E Test Plan (Team 3)
- β Performance Infrastructure (Team 4)
Ready for Phase 1.C launch Dec 8 π
Generated: Nov 17, 2025 By: Claude Code - Priority 3 Execution Status: β READY TO EXECUTE (Nov 18)