π SPRINT TEMPLATE - Planning & Tracking
Use this template for every sprint
SPRINT HEADER
# Sprint [N] - [Sprint Name]
**Duration**: [Start Date] to [End Date] (2 weeks)
**Sprint Goal**: [What we're trying to achieve]
**Team**: [List team members]
**Lead**: Cursor (Implementation Lead)
**Status**: π’ On Track / π‘ At Risk / π΄ Off Track
## Sprint Metrics
- Target Velocity: [X story points]
- Capacity: [Y hours/person]
- Team Members: [N]
- Days: [10-12 working days]
SPRINT PLANNING SECTION
Sprint Goal
ONE sentence describing the sprint objective:
"We will deliver a working data ingestion pipeline
that processes 1000+ documents with >95% quality metrics"
Capacity Planning
| Member | Available Hours | Allocated | Remaining |
|---|---|---|---|
| DataEngineer | 80h | 60h (setup overhead) | 20h |
| MLEngineer | 80h | 70h | 10h |
| BackendEngineer | 80h | 50h | 30h |
| QAEngineer | 80h | 60h | 20h |
| DevOpsEngineer | 80h | 40h | 40h |
| TOTAL | 400h | 280h | 120h |
Risk Mitigation
| Risk | Probability | Impact | Mitigation |
|---|---|---|---|
| Data source API down | Medium | High | Use cached data |
| Team member unavailable | Low | High | Cross-training done |
| Scope creep | Medium | Medium | Cursor manages strictly |
BACKLOG SECTION
Sprint Backlog (In Progress)
βββββββββββββββββββββββββββββββββββββββββββββββββββββββ
β BACKLOG | TODO | IN PROGRESS | REVIEW | DONE β
β (15) | (8) | (2) | (1) | (0) β
βββββββββββββββββββββββββββββββββββββββββββββββββββββββ
Tasks by Epic
EPIC 2: Data Pipeline
| ID | Task | Owner | Points | Status | Notes |
|---|---|---|---|---|---|
| EP2-1 | Identify data sources | DataEng | 3 | β | Completed |
| EP2-2 | Design ingestion pipeline | DataEng | 5 | π‘ | In progress, 50% done |
| EP2-3 | Implement extraction logic | DataEng | 8 | β³ | Blocked on API credentials |
| EP2-4 | Data validation framework | DataEng | 5 | β³ | Ready to start |
EPIC 3: VectorDB
| ID | Task | Owner | Points | Status | Notes |
|---|---|---|---|---|---|
| EP3-1 | VectorDB selection | MLEng | 3 | π‘ | Testing 2 options |
| EP3-2 | Chunking strategy research | MLEng | 5 | β³ | Starts after EP3-1 |
EPIC 4: LLM Integration
| ID | Task | Owner | Points | Status | Notes |
|---|---|---|---|---|---|
| EP4-1 | LLM provider evaluation | BackendEng | 3 | β³ | Next priority |
Testing (QA)
| ID | Task | Owner | Points | Status | Notes |
|---|---|---|---|---|---|
| QA-1 | Test strategy creation | QAEng | 5 | β | Done |
| QA-2 | Unit test setup | QAEng | 3 | π‘ | 60% complete |
DAILY STANDUP LOG
Day 1 - [Date]
Standup Time: 09:00 UTC Attendance: All present β
Status Summary:
- π’ Backlog review complete
- π’ Sprint goal aligned
- π‘ 1 blocker identified: API credentials delayed
By Person:
DataEngineer:
- Yesterday: Sprint planning, backlog breakdown
- Today: Finalize data sources document
- Blockers: Waiting on API credentials from external team
- ETA: EOD tomorrow
MLEngineer:
- Yesterday: Started VectorDB comparison
- Today: Complete evaluation, decide between Pinecone & Weaviate
- Blockers: None
- Next: Design chunking strategy
BackendEngineer:
- Yesterday: Sprint setup, environment ready
- Today: Start LLM provider research
- Blockers: None
- Next: API endpoint design
QAEngineer:
- Yesterday: β Test strategy delivered
- Today: Setup test infrastructure
- Blockers: Need access to staging environment
- Next: Implement unit test framework
DevOpsEngineer:
- Yesterday: Infrastructure designed
- Today: Provision staging environment
- Blockers: AWS account access pending
- Next: Setup CI/CD pipeline
Cursor (Lead):
- Yesterday: Sprint planning completed
- Today: Manage blockers, coordinate team
- Blockers: 2 external dependencies (API creds, AWS access)
- Action: Escalating to HansPedder2 for expedited access
Day 2 - [Date]
Summary: π‘ At Risk - 2 blockers blocking progress
...
Day 5 - [Date] - MID-SPRINT CHECK
Sprint Progress: 2/10 days complete
Velocity Check:
- Planned: 20 points
- Completed: 5 points (25% of sprint)
- Projected: 12-15 points (below target)
Issues:
- API credentials still pending (blocking EP2)
- AWS access approved, sprint moving
Adjustments:
- Shifted to non-dependent tasks
- Started EP3 & EP4 work in parallel
- New blocker tracking enabled
Day 10 - [Date] - SPRINT END
Final Status: π‘ At Risk
Metrics:
- Planned: 20 story points
- Completed: 16 story points (80% - GOOD)
- Blockers Resolved: 2/2 (100%)
- Test Coverage: 82% (Target: 85%)
What Went Well:
- β Team parallelization worked
- β Blocker escalation was effective
- β Quality maintained
- β Documentation comprehensive
What to Improve:
- π΄ External dependency coordination (API credentials)
- π΄ Environment setup timing
- π‘ More buffer for unknown tasks
Next Sprint Adjustments:
- More external dependency buffer (2 days)
- Earlier environment setup (Day 1)
- Better vendor communication
SPRINT REVIEW
Demo/Review Meeting
Date: [Last day of sprint] Attendees: Team + HansPedder2 (Stakeholders)
Completed Items Review
| Item | Owner | Status | Quality |
|---|---|---|---|
| Data Sources Document | DataEng | β DONE | Good |
| Chunking Strategy | MLEng | β DONE | Excellent |
| API Design Document | BackendEng | β DONE | Good |
| Test Strategy | QAEng | β DONE | Excellent |
Outstanding Items
| Item | Why | Owner | Next Sprint |
|---|---|---|---|
| Data Pipeline Code | Blocked by API creds | DataEng | Sprint 2 |
| Evaluation Framework | Design only, code Sprint 2 | MLEng | Sprint 2 |
Feedback from Stakeholders
- HansPedder2: "Good progress despite blockers. External dependencies need better planning."
- No major concerns raised
- Continue current approach with improvements
SPRINT RETROSPECTIVE
What Went Well β
- Excellent cross-team coordination
- Blocker escalation was timely
- Documentation quality high
- Team communication clear
What Could Improve π
- External dependency management
- Earlier environment provisioning
- Buffer for unknowns
Action Items for Next Sprint
| Action | Owner | Sprint |
|---|---|---|
| Establish vendor coordination SLA | Cursor | Sprint 2 |
| Pre-provision environments earlier | DevOps | Sprint 2 |
| Add 15% buffer to estimates | Team | Sprint 2 |
METRICS & REPORTS
Sprint Velocity
Sprint 1: 16 pts
Sprint 2: [TBD]
Sprint 3: [TBD]
Avg: [TBD]
Burndown Chart (Template)
Points
20 |β
| β
15 | ββ
| β
10 | ββ
| β
5 | ββ
| ββ
0 |_____________________β (Done line)
Day1 Day2 Day3 Day4 Day5 Day6 Day7 Day8 Day9 Day10
Team Utilization
Target: 80%
Actual: 82% (GOOD)
NEXT SPRINT PREVIEW
Sprint 2 Focus
Primary Objective: Implement data pipeline + VectorDB setup
Planned Epics:
- EP2 Data Pipeline: Implementation phase
- EP3 VectorDB: Setup & testing
- EP4 LLM: Continued research
Estimated Velocity: 20-25 points
Key Dependencies:
- External data source confirmations
- Vendor API documentation
APPROVAL
Sprint Lead: Cursor - Approved β Project Director: HansPedder2 - Approved β Date Approved: [Date]
Template Version: 1.0 Last Updated: 2025-11-17 Next Sprint: [Date]