| section,item,description,unit,qty,rate | |
| Substructure,A1,Excavation for foundation (machine dig),m3,350,340 | |
| Substructure,A2,Blinding concrete grade 20,m3,40,1600 | |
| Substructure,A3,Concrete grade 35 in foundations,m3,120,1750 | |
| Substructure,A4,Reinforcement bar supply and fix (T16),kg,15000,11.5 | |
| Substructure,A5,Formwork to foundation faces,m2,800,460 | |
| Superstructure,B1,Masonry wall in cement sand mortar,m2,650,660 | |
| Superstructure,B2,Reinforced concrete column grade 35,m3,85,1850 | |
| Superstructure,B3,Formwork to columns,m2,900,470 | |
| Superstructure,B4,Reinforcement bar supply and fix (T20),kg,22000,12 | |
| Superstructure,B5,Precast concrete slab panel,m2,1400,1450 | |
| Finishes,C1,Cement sand plastering to wall,m2,1300,175 | |
| Finishes,C2,Emulsion painting to wall,m2,2400,52 | |
| Finishes,C3,Ceramic wall tiling,m2,900,2850 | |
| Finishes,C4,Waterproofing membrane to roof,m2,700,265 | |
| Finishes,C5,Ceiling false ceiling with metal frame,m2,1100,380 | |
| External Works,D1,Demolition of existing structures,m3,90,480 | |
| External Works,D2,Excavation and disposal of spoil,m3,420,355 | |
| External Works,D3,uPVC drainage pipe 110mm,m,320,285 | |
| External Works,D4,Road base and asphalt surfacing,m2,1500,620 | |
| External Works,D5,Scaffolding to external walls,m2,1200,115 | |
| Services,E1,Electrical installation point,no.,180,950 | |
| Services,E2,Plumbing installation point,no.,120,1050 | |
| Services,E3,Fire alarm detection point,no.,95,1250 | |
| Services,E4,LV switchboard supply and install,no.,2,185000 | |
| Joinery,F1,Hollow core door with frame and ironmongery,no.,45,2750 | |
| Joinery,F2,Aluminium window with glazing,m2,220,3100 | |
| Joinery,F3,Scaffolding to external walls,m2,1200,118 | |