4f4f10a1-f5cd-4d7f-9c27-a8ddce3d1a63
and 80 W correspond to entropy rates of 10 W/K and 40 W/K, respectively, for a total cold -stage entropy rate of 50 W/K. The dynamic contribution accounts for 80% of the total entropy rate and scales inversely with the intrinsic quality factor Q₀. A coefficient -of-performance analysis shows that 100 W at 2 K re...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7642.pdf
0
c155af58-e684-46a6-b5c4-403877bda7bf
surface resistance of a superconducting cavity is extremely small, it remains finite. As a result, part of the stored elec- tromagnetic energy is dissipated on the cavity wall and converted into heat. This RF wall loss appears as a dynamic heat load in the helium cooling system. Related studies on zero-temperature p...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7642.pdf
0
0246b9a5-7a8f-40db-aa52-60f98e6e7f82
ual-gas effects, and thermal radiation across the insulation vacuum. A conventional heat -load budget lists these con- tributions in watts at each temperature stage. From a ther- modynamic viewpoint, however, a watt deposited at 2 K is much more severe than a watt deposited at a higher tem- perature because the entrop...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7642.pdf
0
2d980cda-fb39-4694-b014-75e9adf784bf
for evaluating how RF -loss reduction, improved cryomod- ule thermal design, and higher cryogenic efficiency reduce entropy generation and improve overall accelerator perfor- mance [10 ]. SSR2 CRYOMODULE HEAT -LOAD BASIS The reference cryomodule considered here contains six SSR2 superconducting single -spoke reson...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7642.pdf
0
6d077bf2-a804-48b3-8ee2-34208f7f5d40
R/Q 252 Ω G 123 Ω Ncav 6 Static heat load 20 W Dynamic RF heat load 80 W The static load is controlled mainly by cryomodule hard- ware and thermal shielding. The dynamic load is controlled mainly by RF surface resistance and cavity operating field. For the reference case, the dynamic RF load is the domi- nan...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7642.pdf
0
bca11eb2-cdb9-4e97-a8c0-e6b8ca2f0baa
† kimht7@ibs.re.kr 17th International Particle Accelerator Conference, Deauville, France JACoW Publishing ISBN: 978-3-95450-252-3 ISSN: 2673-5350 doi: 10.18429/JACoW-IPAC2026-TUP7642 MC7.T07: Superconducting RF 1689TUP: Poster session TUP7642 Content from this work may be used under the terms of the CC BY 4.0 licence ...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7642.pdf
0
2cdfd024-1314-4011-9e6c-cf1d4317333b
where the numerator is the heat absorbed at the cold stage. At 2 K, each watt of heat corresponds to 0.5 W/K of en- tropy rate. When multiple heat loads are deposited at the same temperature, the entropy rates are additive: 𝑆𝑆̇tot=∑𝑖𝑖𝑄𝑄̇i 𝑇𝑇c. (2) For static heat leakage from a warm reservoir to the cold ...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7642.pdf
1
e10ff032-d082-4fd8-8a08-64718ef7e17b
RF L oss and Q uality F actor For an SRF cavity operated at a given accelerating volt- age, the RF power dissipated on the cavity surface is 𝑃𝑃diss =𝑉𝑉acc2 (𝑅𝑅/𝑄𝑄)𝑄𝑄0. (4) The corresponding dynamic entropy rate at the cold stage is 𝑆𝑆̇dyn=𝑉𝑉acc2 (𝑅𝑅/𝑄𝑄)𝑄𝑄0𝑇𝑇c. (5) At fixed accelerating vo...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7642.pdf
1
f9d15030-2390-41b6-80e5-a14f7dfc045a
Carnot COP: COPCarnot =𝑇𝑇c 𝑇𝑇h−𝑇𝑇c. (7) The minimum input power needed to remove heat from the cold stage is 𝑊𝑊̇min=𝑄𝑄̇c COPCarnot. (8) For a real refrigerator, the real COP is lower than the Carnot COP. The refrigerator entropy generation due to ir- reversibility can be expressed as 𝑆𝑆̇gen ,ref=�...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7642.pdf
1
685842cc-3b2f-4eac-b1c0-47120f65579c
Entropy R ates at 2 K At 2 K, the 20 W static load gives 10 W/K, while the 80 W dynamic load gives 40 W/K. The total 2 K heat load of 100 W corresponds to 50 W/K. As summarized in Ta- ble 2, the dynamic RF heat load accounts for 80% of both the total heat load and the total entropy rate. Table 2: Static, D...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7642.pdf
1
f3041275-d4d0-4e88-8111-be2d681a972d
Quantity Value Dynamic heat load, module 80 W Number of cavities 6 Dynamic heat load, cavity 13.33 W Entropy rate, cavity 6.67 W/K Dominant control Q₀ and RF surface resistance Effect of Q₀ I mprovement Because the dynamic load scales as 1/Q₀, changes in Q₀ produce nearly linear changes in dynamic e...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7642.pdf
1
e26f7e2c-7dc9-421f-89f6-87c6e79cc6c4
COP -Based I nterpretation The COP calculation shows the system -level penalty of a 2 K heat load. For a refrigerator operating between 2 K and 300 K, the Carnot COP is: COPCarnot =2 300−2=0.0067 . (10) 17th International Particle Accelerator Conference, Deauville, France JACoW Publishing ISBN: 978-3-95450-252-3 I...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7642.pdf
1
752b5aa3-1bca-44df-929f-1c863d490b9f
For a total 2 K heat load of 100 W, the ideal minimum work is approximately: 𝑊𝑊̇min=100 W 0.0067≈14.9 kW. (11) If a representative real 2 K COP of 0.001 is used, the real input work becomes: 𝑊𝑊̇real =100 W 0.001=100 kW. (12) The corresponding refrigerator entropy generation is ap- proximately 283.6 W/K. ...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7642.pdf
2
f26ee58a-813f-4f8c-bac8-3b51f50fdb5c
tive real 2 K COP of 0.001. The real -COP estimate is consistent with the published SRF cryogenic practice cited above. Saini et al. used ap-proximately 800 W of wall -plug power per watt dissipated at 2 K when evaluating radiation heat loads in a cryomod- ule. Chojnacki et al. estimated cryomodule wall -plug pow...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7642.pdf
2
15dc1708-2bc1-43e7-b879-5e762b19434f
intermediate -temperature stages are important, even when their heat loads are larger in watts. Dynamic entropy generation is reduced most effectively by improving cavity performance. Surface preparation, re- sidual -resistance reduction, trapped -flux mitigation, clean assembly, optimized cooldown, magnetic shiel...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7642.pdf
2
19f4da1f-23d5-4b5d-a8de-3d8d6910c6e7
crease heat leakage to the 2 K helium system. The main entropy -reduction design levers are summarized in Table 6. Table 6: Design Levers for Entropy Reduction Source Design lever Effect Dynamic RF Increase Q₀; reduce surface resistance Lower RF loss and dynamic entropy rate Conduction Long paths; low...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7642.pdf
2
a4b68b74-053d-4730-988f-13f560320607
load and 80 W dynamic RF load at 2 K, the corresponding cold-stage entropy rates are 10 W/K and 40 W/K, respec- tively. The total cold -stage entropy rate is 50 W/K. The dynamic RF heat load from six cavities contributes about 80% of the total entropy rate. Because the dynamic heat load scales inversely with Q₀, ...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7642.pdf
2
14137a74-7b2d-41c4-bfaa-ae3e4e8e704a
These results show that entropy analysis is a useful frame- work for connecting cavity RF performance, cryomodule heat-load reduction, and accelerat or cryogenic efficiency. REFERENCES [1] H. Padamsee, J. Knobloch, and T. Hays, RF Superconductivity for Accelerators , 2nd ed. Weinheim, Germany: Wiley -VCH, 2008. ...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7642.pdf
2
c67d8340-a600-4080-b60a-5455136c64ad
physics”, Quantum Beam Sci. , vol. 8, no. 3, p. 21, Aug. 2024. doi:10.3390/qubs8030021 [5] H. Kim and C. -S. Park, “Unified analysis of quantum and relativistic effects in superconducting cavities”, Appl. Phys. A, vol. 132, Mar. 2026. doi:10.1007/s00339- 026- 09507- 0 17th International Particle Accelerator...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7642.pdf
2
0dae285c-a53d-4466-8b94-0da6341a3110
[6] H. Kim, S. Jeon, and J. Kim, “Experimental performance evaluation of prototype single -spoke resonator superconducting RF cavities”, J. Korean Phys. Soc. , Mar. 2026. doi:10.1007/s40042- 026- 01617- 5 [7] A. Bejan, Advanced Engineering Thermodynamics , 4th ed. Hoboken, NJ, USA: Wiley, 2016. [8] A. Saini,...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7642.pdf
3
6cdcf5d3-c920-4233-908e-c6663763bb77
Germany, Sep. 2009, paper THPPO034, pp. 638-642. [10] P. Pierini, “Fundamental of cryogenics (for superconducting RF technology)”, Jul. 2013, arXiv:1307.8286. doi:10.48550/arXiv.1307.8286 17th International Particle Accelerator Conference, Deauville, France JACoW Publishing ISBN: 978-3-95450-252-3 ISSN: 2673-535...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7642.pdf
3
218db00d-750d-4740-9151-4f8df1795f16
DEVELOPMENT OF A NOVEL SOLID-STATE MODULATOR AND ITS APPLICATION IN HIGH-POWER KLYSTRONS∗ X. Chen, C. Liu†, F. Shang, L. Shang, W. Song, J. Pang, Z. He� Z. Zhong University of Science and Technology of China, Hefei, China Abstract Thispaperpresentsahighlyintegratedsolid-statemod- ulator designed to drive high-power kly...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7644.pdf
0
28ddecaa-363c-4b3f-9503-205cdcc9130c
achieving the required pulse waveform quality and stability. Inaddition,withlimitedmodification,thesamearchitecture can be adapted to higher repetition-rate applications such as theSuper Tau-Charm Facility(STCF)injector,demonstrat- ing its scalability for future large-scale accelerator facilities. INTRODUCTION High-pow...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7644.pdf
0
8ddb27ae-5938-478e-8182-a70ccdc05a62
mainstream solution in modern accelerator applications [ 2]. Their adoption in recent light-source facilities, including APS-U,MAXIV,andHEPS,hasdemonstratedtheadvan- tages of solid-state technology in reliability, controllability, and long-term operation [ 3–5]. Despitethisprogress,importantengineeringchallenges remain...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7644.pdf
0
107fe78a-d51d-4b5c-a3e2-310d07159774
accelerator facilities requiring high availability and efficient operation. ∗This work was supported in part by the Fundamental Research Funds fortheCentralUniversities(No. KY2310000050),inpartbytheHefei Advanced Light Facility Project, and in part by the Super Tau-Charm FacilityKeyTechnologyResearch Project. †chaoliu@...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7644.pdf
0
9c55bc44-1def-4452-83f3-245074dc82cb
power operation with an 80 MW S-band klystron at the Hefei Advanced Light Facility (HALF). In addition, the adaptabilityofthesametopologytohigherrepetition-rate applications, such as the STCF injector, is briefly discussed. SYSTEM ARCHITECTURE AND DESIGN To meet the stability, reliability, and maintainability re- quire...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7644.pdf
0
238f42b5-9428-49ec-8c25-8b4bff5c418a
solid-state power array, integrated pulse transformer, and central control unit. In operation, the primary chargingsupplyprovides a sta- ble and adjustable DC input to the solid-state module array. Whenasynchronoustriggerisapplied,theactivemodules conductsimultaneouslyandgenerateahigh-currentprimary pulse,whichisdelive...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7644.pdf
0
f630ab5e-bdee-4015-97d9-fb65e4ea77d8
ISBN: 978-3-95450-252-3 ISSN: 2673-5350 doi: 10.18429/JACoW-IPAC2026-TUP7644 MC7.T08: RF Power Sources 1693TUP: Poster session TUP7644 Content from this work may be used under the terms of the CC BY 4.0 licence (© 2026). Any distribution of this work must maintain attribution to the author(s), title of the work, publis...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7644.pdf
0
1b940c5d-83b0-4800-b951-37bde92f9879
the solid-state module array is assembled as an indepen- dent enclosure and mounted directly on top of the pulse transformeroiltank,asshowninFig. 2. Thisarrangement shortens the main pulse-current path and eliminates long externalhigh-voltagecableconnectionsbetweenthemodule arrayandthetransformer. Asaresult, distribute...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7644.pdf
1
754abf6e-e1b3-4d86-a18b-f6befa4bcdd2
marized in Table 1. The system is designed to deliver an output pulse voltageabove415 kV and an output pulse cur- rent above 485 A, with a pulse stability better than 200 ppm (RMS)andarisejitterbelow10ns. Thesespecificationsare settosatisfythebeamqualityrequirementsoftheinjector system. Table 1: Main Design Specificati...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7644.pdf
1
7f9b20f8-2e43-4345-9c80-b38697d184f2
combinedwiththepulsetransformer. Furthermore,partic- ular attention is also given to the control and health man- agement capability of the modulator, since reliable long- termoperationrequireseffectivesupervision,diagnosis,andmaintenanceofthelargeparallelmodulearray. Inthepresent system,thecentralcontrolunitcoordinates...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7644.pdf
1
870b89f4-5382-4a52-a2f8-63203feebeb7
remaining healthy modules continue operation under the re- dundant configuration. After isolation, the fault information is further mapped to the physical position of the module array,allowingrapididentificationofthefailedlocationand reducing maintenance time. Based on the real-time status distribution of the full modu...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7644.pdf
1
1a8a375f-4206-4bd9-846a-d63812a88ff9
and the calculated health index of the module array. Tofurthersupportpulse-to-pulsereproducibility,themod- ulator is supplied by a high-precision programmable SiC DC charging power supply, and a synchronous isolation mechanismisintroducedbetweenthechargingstageandthe modulatorarray. Byelectricallyisolatingtheprimarysup...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7644.pdf
1
2ebd8ae7-ab1d-415e-917f-b2fc0b0b31e8
tioning,servingasthehigh-powertestplatformattheHALF linac. The output high-voltage pulse was measured through a high-voltage divider, and the flattop stability was evaluated usingadifferentialamplifiertogetherwithadigitaloscillo- scope. A representative oscilloscope waveform used in the17th International Particle Accel...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7644.pdf
1
76f594b3-c895-4c00-9279-1780e8df2450
stabilitymeasurementisshowninFig. 5,wherethedifferen- tial flattop-fluctuation signal, the timing trigger, and the di- vided pulse-voltage waveform are simultaneously recorded. Figure 4: High-power test platform of the proposed solid- state modulator at the HALF linac facility. Figure 5: Representative oscilloscope tra...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7644.pdf
2
b4040325-ecb9-41b5-97e9-886bc98a7421
136ppm (RMS) at the flattop. This valueis wellbelowthe designlimitof200ppmandconfirmsthattheproposedmod- ulator can satisfy the stability requirement for high-power klystron operation in the HALF injector. The other key per- formanceparameters,includingoutputpulsevoltage,output pulse current, flattop width, repetition ...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7644.pdf
2
338f3b96-090d-45e7-ac8c-6bc2c51838e6
thebasisofthevalidatedintegratedtopology,theupgrade mainlyinvolvesenhancedcoolingforthesolid-statemodule arrayandhigh-voltagecomponents. Thisengineeringpath Figure 6: Measured pulse-to-pulse flattop stability of the modulatorover5,000 consecutivepulsesat rated operating conditions. preservesthestructuraladvantagesofthe...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7644.pdf
2
7a046da9-8b6d-4684-83d1-43a8b2fe6a02
uation,therebyimprovingmaintainabilityandoperational availability in accelerator service. High-power tests at the HALF linac has demonstrated stableoperationwithan80MWS-bandklystron,includinga measuredpulse-to-pulseflattopstabilityof136ppm(RMS), whichsatisfiesthedesignrequirement. Thesametopology canbeextendedtohigherr...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7644.pdf
2
4612de30-42b7-4740-ac5b-9042ce4a5d43
[2]R. L. Cassel, G. C. Pappas, M. N. Nguyen, and J. E. DeLa- mare, “A Solid State Induction Modulator for SLAC NLC”, in Proc. PAC’99 , New York, NY, USA, Mar. 1999, paper TUP9, pp. 1494–1496. doi:1/zero.alt4.11/zero.alt49/PAC.1999.794145 [3]T. J. Russell and A. Cours, “Klystron Modulator Operation and Upgrades for the ...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7644.pdf
2
e7f5ea02-bb3a-4ae6-ab23-1a6f30f5eff0
Proc.IPAC’23 , Venice, Italy, May 2023, pp. 2023–2026. doi:1/zero.alt4.18429/JACoW-IPAC2/zero.alt423-TUPL12617th International Particle Accelerator Conference, Deauville, France JACoW Publishing ISBN: 978-3-95450-252-3 ISSN: 2673-5350 doi: 10.18429/JACoW-IPAC2026-TUP7644 MC7.T08: RF Power Sources 1695TUP: Poster sessio...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7644.pdf
2
9fdc2953-449f-41a8-a528-a729a5713181
[6]S. Choroba, “Design and Status of the XFEL RF System”, inProc.PAC’07 ,Albuquerque,NM,USA,Jun.2007,paper TUXC03, pp. 841–845. [7]X.-C. Ai et al., “Conceptual design report of the Super Tau- Charm Facility: the accelerator”, Nucl. Sci. Tech. , vol. 36,no. 12, p. 242, 2025. doi:1/zero.alt4.1/zero.alt4/zero.alt47/s41365...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7644.pdf
3
43c515e7-5800-4e57-88f1-9a33bfdefd6e
CURRENT STATUS OF THE UPGRADE AND OPERATION OF THE NSRRC TPS LINAC PULSE HIGH -POWER RF SYSTEM W. Y . Chiang, Y . C. Chang, A. P. Lee, K . L. Tsai, C. L. Chen , H. P. Chang, M . C. Chou, H . P. Hsueh , NSRRC, Hsinchu, Taiwan H. Matsumoto , KEK, Ibaraki, Japan Abstract The NSRRC Taiwan Photon Source (TSP) pre -...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7647.pdf
0
73deb8f7-2eb6-4fb7-b235-7bb440645e09
CETD E37310A, and ensures the supply of the required RF power. In August 2023, using the THz FEL pulse RF sys- tem, NSRRC upgraded the TLS pre -injector pulse RF sys- tem. Following six months of stable operation, upgrades to all three TPS pre -injector pulse RF systems began in 2024. This paper presents instal...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7647.pdf
0
ad1d8e0f-6475-40b2-9fc7-d7ccb85afeb8
output charge 5 nC). The maximum repetition rate for both modes is 5 Hz. After acceleration in th e electron gun, the beam energy reaches 90 keV . 2. Sub-harmonic pre -buncher: a single -cavity resonator operating at 499.654 MHz that compresses the elec- tron beam pulse width to below 1 ns. 3. Primary buncher: co...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7647.pdf
0
c0ee0539-28e5-49c5-b5ac-dabc68c67bea
wave structure operating in the 2 π/3 mode at 2997.912 ± 0.03 MHz and maintained at 38 ~ 42 ± 0.1 °C. This final stage consists of three S -band accelerator sec- tions, which raise the beam energy to 150 MeV . Each section requires roughly 16 MW of RF power. Figure 1: TPS pre -injector system [1]. KLYSTRON U...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7647.pdf
0
dfa60d0f-5fa8-4c4e-bd5e-5c00b5e74dd8
TPS reliability. To address these issues and improve relia-bility, a Klystron Upgrade Program was launched in 2024 to replace the TH2100A with the E37310A Klystron (Fig. 2(b)) from Canon Electron Tubes & Devic es (CETD). Ta- ble 1 shows that the E37310A’s performance and operating parameters are similar to those of t...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7647.pdf
0
ef3fcc1f-369d-436d-a92e-b90c169bd572
ISBN: 978-3-95450-252-3 ISSN: 2673-5350 doi: 10.18429/JACoW-IPAC2026-TUP7647 MC7.T08: RF Power Sources 1697TUP: Poster session TUP7647 Content from this work may be used under the terms of the CC BY 4.0 licence (© 2026). Any distribution of this work must maintain attribution to the author(s), title of the work, publis...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7647.pdf
0
6b4c3d4c-dc2e-4d18-92be-9e7f9eb20706
Figure 3: Circuit model of the newly designed PFN in the pulsed modulator (1:14 turns ratio ). Table 1: Comparison of the Specifications of the Thales TH2100 and CETD E37310A K lystrons Measurement Thales TH2100 CETD E37310A Frequency 2998.5 ± 1 MHz 2998.5 ± 1 MHz Peak Cathode V oltage 272 kV 295 kV ...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7647.pdf
1
9c1f090b-d903-4be7-88f5-ea3bb1b0817c
an appro priate voltage breakdown margin . Under matched conditions, the maximum deliverable primary -side voltage is 22.5 kV . Understanding the klystron operating condi- tions to determine the pulse transformer turns ratio is an important step, and it also affects the design of the Klystron oil tank. Next, th...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7647.pdf
1
f0f49c73-b033-4c65-91e3-3df171f0255c
1:13 transformer gives a primary impedance of 5.62 Ω. E37310A runs at 291 kV and 315 A with a secondary im- pedance of 923.8 Ω; with a 1:13 turns ratio, the primary impedance is 5.47 Ω. Achieving −300 kV requires a 47 kV charging voltage, which is over the limit. With a 1:14 turns ratio, the primary impedance is ...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7647.pdf
1
cb87677b-2824-4c10-b78e-c90a49582c0c
quires a flat-top duration of over 2 μs. With a 1:15 ratio, FWHM is 3.73 μ s. Considering limits, a 1:14 ratio is opti- mal. A new inductor string is installed in parallel with the original inductors to achieve the required 552 nH. The final PFN configuration and installation are shown in Fig. 6. Figure 4: Out...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7647.pdf
1
7529f806-067c-44e0-b68c-c1c4e720cb2b
ISBN: 978-3-95450-252-3 ISSN: 2673-5350 doi: 10.18429/JACoW-IPAC2026-TUP7647 1698 MC7.T08: RF Power SourcesTUP7647 TUP: Poster session Content from this work may be used under the terms of the CC BY 4.0 licence (© 2026). Any distribution of this work must maintain attribution to the author(s), title of the work, publis...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7647.pdf
1
86290fe0-9ea4-486a-a57a-cf04c090a6d2
OPERATING STATUS OF THE NEW KLYSTRON AND MODULATOR Phase I of the TPS pre -injector upgrade concluded in February 2026, following the technical modifications de- scribed earlier. K1 and K2 Stations received the E37310A Klystron replacements and pulsed modulator upgrades. Figure 7 outlines the new K1 station s etup...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7647.pdf
2
0a800f9c-5ecb-4797-b291-09e6b219e76b
ing correct impedance matching and stable modul ator op- eration, as designed. Figure 7: Revised K1 Station configuration. Figure 8: Revised K1 Station . Figure 9: Comparison of voltage waveforms with PFN in- ductance tuning: no aluminium tube (blue); one aluminium tube (purple); two aluminium tubes (red). ...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7647.pdf
2
43d1ef02-47f8-4c04-8e8b-6d88c363ca79
testing of TH2100A and E37310A established standardized operating and maintenance procedures, raising safety, effi- ciency, and reliability. Building on these upgrades, a Phase II plan will be developed to assess enhancements to the LLRF and control systems. A robust, pulsed, high- power RF system will support stu...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7647.pdf
2
e79d58b8-bfe3-429b-bf90-e3b68a9234ca
wave_tube_catalog_EN.pdf 17th International Particle Accelerator Conference, Deauville, France JACoW Publishing ISBN: 978-3-95450-252-3 ISSN: 2673-5350 doi: 10.18429/JACoW-IPAC2026-TUP7647 MC7.T08: RF Power Sources 1699TUP: Poster session TUP7647 Content from this work may be used under the terms of the CC BY 4.0 lice...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7647.pdf
2
74f8bc9e-cdf7-437b-b66f-c6121eb79e6f
PROGRESS IN THE PM BASED LGBM MAGNETS FOR K-4GSR Y. G. Jung, B. J. Kim, S. H. Ahn, G. Hahn, I. Chun , W. W. Lee, Y. G. Choi, D. E. Kim∗ Pohang Accelerator Laboratory, POSTECH, Pohang, KyungBuk, Republic of Korea Abstract A 4th generation storage ring based light source is being developed in Korea since 2021. It feature...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7653.pdf
0
9468d7a6-6cc6-4b97-bc98-2d1dc9fb51f3
∼0.15Twithapproximately2mtotallength. Inthisreport, thecompensationschemeoftemperaturedependence,and field tuning to meet the bending angle, and apex points will be described. INTRODUCTION Third generation storage ring based light sources have been used as a bright light source for many years. Recently multi-bend achro...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7653.pdf
0
a9eb2aa1-5c0e-44e2-8a88-7fbf40319728
H7BA considering better nonlinear beam dynamics com- pared to the conventional 7BA and lower emittance com- pared to MH6BA [ 1–3]. K-4GSRconsistsoftotal28periodicsectors. Asshown in Fig.1, each sector is equipped with 1 center bending (CB) magnet, 4 longitudinal gradient bending (LGBM) magnets, 2 transverse gradient be...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7653.pdf
0
344ec44b-dadf-46ef-b5da-412b0c9f3212
advantageofcompactmagnetsize,andnearlyzerooperating energy costs. However, there is a possibility of long term degradation(althoughsmall)duetotheradiationdamage, ∗dekim@postech.ac.krandlackoftunability. ESRF-EBSandHEPSareadopting Sm2Co17for their magnet material which shows minimal radiation damage compared to NdFeB ba...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7653.pdf
0
7bf56fe0-91f7-47a1-87c8-0214892be572
shape has a 5-step profile which is not easy to match pre- cisely. Themagnetisdesignedtohavethedesignvalueofthe 1st integral (bend angle) and the 2nd integral (apex points). The beam dynamics study confirmed that exact profile is notimportantforbeamemitances. Itshouldbealsonoted that the upstream and downstream version...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7653.pdf
0
d26c717d-239f-48f6-95f1-a986c0343d52
the Table 1. Table 1: MajorParametersof LGBM1, LGBM2 Magnet Parameter LGBM1 LGBM2 Magnet Type LGBM1U/D LGBM2U/D PM type Sm2Co17 - Br 1.08∼1.12 T - Required Num. 28/28 28/28 B range 0.734 T-0.150T 0.312 T-0.153T Uni. |x| < 10 mm < 1.0E-3 < 1.0E-3 Min. Polegap. 24.4 mm 24.4 mm Total Bend 41.69 mrad 33.56 mrad Apex point ...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7653.pdf
0
b4186bd6-3ff1-4b11-96e8-660b9d84ee69
ISBN: 978-3-95450-252-3 ISSN: 2673-5350 doi: 10.18429/JACoW-IPAC2026-TUP7653 1700 MC7.T09: Normal Conducting MagnetsTUP7653 TUP: Poster session Content from this work may be used under the terms of the CC BY 4.0 licence (© 2026). Any distribution of this work must maintain attribution to the author(s), title of the wor...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7653.pdf
0
c633c536-7b9a-4092-9353-14f1b5b98b57
Figure 1: Lattice layoutof K-4GSR. magnet module where the field is most uniform. Hall probe is scanned along the magnet and the magnetic field from Hallsystemisextractedatthesameposition. Thefieldfrom NMRteslameter,andthecalculatedfieldfromHallprobe systemiscomparedforthecenterof5magnetmodules. The ratio between the N...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7653.pdf
1
69e26bfc-321a-4684-866a-ed3597329a4a
rare earth magnet. The advantage of the materiel compared to NdFeB type is that it has a strong long term radiation damage,weakertemperaturesensitivity( ∼-350ppm/K)and good corrosion resistance. The disadvantages are weaker remanancecomparedtoNdFeBtype,brittleness,andhigher costs. Due to the concern for long term radia...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7653.pdf
1
2069b5a8-f4de-41ca-bf25-a60876d04505
FeNiplateiscalculatedtobemostlylinearwithcentralfield with slope of 5.11 mm/T. The supplied shape of the FeNi fromthevendorisaplatewith1mm, and2mm. Usingthis calculation, the required volume of FeNi plate is calculated combining the two thickness and placed on the surface of the PM blocks. After placing the FeNi plate,...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7653.pdf
1
a845d5d5-bbd4-4b3c-95d0-1e15f8fbd9f6
is reduced to -36 ppm/K which is within the specification.All 5 modules went through this kind of thermal testing and the temperature coefficient of all modules were tuned to be less than -50 ppm/K. Figure2: Exampleofthecompensationoftemperatureeffect of FeNi plate of a module. Figure3: Impactofabolttuningsignaturefore...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7653.pdf
1
0cd1195a-cfa1-472f-9f91-f3519c63db4b
ISBN: 978-3-95450-252-3 ISSN: 2673-5350 doi: 10.18429/JACoW-IPAC2026-TUP7653 MC7.T09: Normal Conducting Magnets 1701TUP: Poster session TUP7653 Content from this work may be used under the terms of the CC BY 4.0 licence (© 2026). Any distribution of this work must maintain attribution to the author(s), title of the wor...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7653.pdf
1
91600ec0-7d1d-4a09-a492-b4e6b5bc0154
for LGBM2. When the origin of the longitudinal coordi- nateisthepoleface,andthefieldprofileisfrombiggerto lower direction, the ideal apex coordinate is 0.8500 m. The field profile is measured using NMR calibrated Hall system, andthe orbitis calculatedbased onthe measuredfield that includes the bend angle, and the apex ...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7653.pdf
2
c561d5bd-9ad9-4536-8cc6-c9173943697d
measured. Allthesignaturesareimplementedinasimple programtoexpectthefinalresultsfromaspecificbolttuning. Theangleerrorwerelessthan1.010-4,orbitdifferencefrom the ideal orbit at the end of the magnet was less than 10 µm. The field profile of the tuned magnet is shown in Fig. 4, and thedifferenceoridealorbitandrealmeasur...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7653.pdf
2
68a2a394-df80-4199-b94c-fd7f88ffed1f
NMRcalibratedHallprobescanningsystem. Fieldtuning wascarriedoutusingFeSiplateforroughfixedadjustments, andusingferromagneticboltsshuntingthepoleandreturn yokes. Signature of installed tuning bolts, and signature for each rotation of the tuning bolts are measured. Field profile is estimated for a set of tuning bolts arr...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7653.pdf
2
b5abfab7-b580-4d04-883f-d0a82e64838c
2022-00155836, Multipurpose Synchrotron Radiation Con- struction Project). REFERENCES [1]G.S.Jang,S. Shin,M.Yoon,J.Ko,Y.D.Yoon,J.Lee,B-H. Oh, “Low emittance lattice design for Korea-4GSR”, Nucl. Instrum. Methods Phys. Res., Sect. A , vol. 1034, p. 166779, 2022. doi:1/zero.alt4.1/zero.alt416/j.nima.2/zero.alt422.166779 ...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7653.pdf
2
8f397c62-9432-4e7e-8eae-4a099731f54f
design report”, Argonne Nat. Lab., Tech. Rep. APSU-2.01- RPT-003,May2019. doi:1/zero.alt4.2172/1543138 [5]C. Benabderrahmane et al., “Magnets for the ESRF-EBS project”, in Proc. IPAC’16 , Busan, Korea, May 2016, pp.1096–1099. doi:1/zero.alt4.18429/JACoW-IPAC2/zero.alt416-TUPMB/zero.alt4/zero.alt41 [6]Q. Li, F. Chen, C....
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7653.pdf
2
31f7e26e-c00e-4b6f-b6de-1272893d70c5
MEASUREMENTS OF MAGNET PROTOTYPES FOR STORAGE RING OF SIAM PHOTON SOURCE II P. Sunwong†, P. Chaithaweep, A. Kwankasem, T. Leetha, P. Numanoy, S. Prawanta P. Pruekthaisong, M. Sroison, N. Thiabsi, T. Yan Synchrotron Light Research Institute, Nakhon Ratchasima, Thailand Abstract A series of magnet prototyp...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7654.pdf
0
48d17ef2-c429-43ce-b699-cb4f1a5b7fe3
systems. Following some mechanical improvements , 10 out of 15 magnets met the specified field quality re quire- ments , while possible sourc es of field errors in the remain- ing magnet s were identified . This work represents a critical milestone toward SPS- II construction, as the storage ring magnets are pla...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7654.pdf
0
c7eaa587-e383-436a-a373-2937664ac89e
and fabricated through a collaboration between the Synchrotron Light Research Institute (SLRI) and a local manufacturer. These magnets comprise two dipole magnets (BM1, BM2) , one combined dipole magnet (DQ1) , eight quadrupole magnets (QF1, QD2, QD3, QF4, QF5, QD6, QF7, QF9) , three sextupole magnets (SD1, S...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7654.pdf
0
57bee8a2-9648-4eb9-b226-fde7c737cbbf
MAGNET REQUIREMENTS The m agnetic field strength and required field quality of magnet prototype for SPS -II storage ring are summariz ed in Table 1. For the combined dipole magnet (DQ1), the de- sign is based on the offset quadrupole concept as imple- ment ed in s ome facilities [ 4, 5]. In this approach, t he r...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7654.pdf
0
726ae005-59d5-48b3-a78c-143de9bf7ca8
evaluated at the mid -plane (y = 0). For quadrupole, sextu- pole and octupole magnets, the values correspond to the normalized integrated multipole components obtained from Fourier analysis. Table 1: Magnet Requirement s for SPS- II Storage Ring Magnet Field Strength GFR (mm) Normalized Field Error BM1 ...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7654.pdf
0
f172d63f-95e5-4d82-b911-2122d829c3b8
the magnet bending angle and along a straight trajectory outside the magnet . The magnetic field was then integrated along these trajectories at various horizontal (X) positions . The resulting normalized integrated field error s for the di- pole and combined dipole magnets are presented in Fig. 1 and Fig.2, re...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7654.pdf
0
183f0081-a702-4c24-8b40-510f77d2dbc2
†prapaiwan@slri.or.th 17th International Particle Accelerator Conference, Deauville, France JACoW Publishing ISBN: 978-3-95450-252-3 ISSN: 2673-5350 doi: 10.18429/JACoW-IPAC2026-TUP7654 MC7.T09: Normal Conducting Magnets 1703TUP: Poster session TUP7654 Content from this work may be used under the terms of the CC BY ...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7654.pdf
0
e020a950-3c09-41a9-9b85-0965aef07090
Figure 1: Normalized integrated field error of dipole BM1 and BM2 magnets . Figure 2: Normalized integrated field error of combined di- pole DQ1 magnet . QUADRUPOLE MAGNETS A stretched wire system [6] was employed to measure the magnetic field integrals of the quadrupole, sextupole and octupole magnet proto...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7654.pdf
1
6ce43d6b-d543-403d-afbe-f5ff6433d5ec
totype s for the SPS- II storage ring. Only higher -order mul- tipole terms (n > 2) are shown, as lower -order terms may be influenced by magnet misalignment during field map- ping. The r epeatability of the field center measurement is better than 5 µm for all quadrupole magnets. For some magnets, the sextupole...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7654.pdf
1
5d77a598-172e-488e-856f-6e3de19d6c83
SEXTUPOLE MAGNETS The integrated multipole components of the sextupole magnet prototype s are presented in Fig. 5. For SD1 and SF2, the higher -order multipole components (n > 3) are within the specified tolerance. In contrast, SD3 exhibits significantly larger normal and skew components for n = 4 and n = 5 (o...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7654.pdf
1
0e65f242-32c7-484b-9cd8-30aa8cf2bf40
QD2 QD3 QF4 QF5 QD6 QF7 QF9Normalized multipole ( ×10-4) n 4567891011121314-60-40-200204060Normal SD1 SF2 SD3 Skew SD1 SF2 SD3Normalized multipole ( ×10-4) n17th International Particle Accelerator Conference, Deauville, France JACoW Publishing ISBN: 978-3-95450-252-3 ISSN: 2673-5350 doi: 10.18429/JACoW-IPAC...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7654.pdf
1
c233a9bf-531b-4b74-92cb-6faae723dc2c
The large octupole and decapole terms observed in SD3 are attributed prima rily to coil excitation errors . This inter- pretation is supported by the fact that the assembly errors of SD1 and SD3 are comparable (27 µm for SD1 and 28 µm for SD3), while electrical measurement s indicate a sub- stantially larger d...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7654.pdf
2
406256ee-0bb5-4943-b2db-a1f779ffa6e7
tolerance of 5×10-3. Due to the relatively flat magnetic field distribution near the magnet center in an octupole magnet , the accuracy of the field center determination is lower than that achieved for the quadrupole and sextupole magnets. Consequently, the repeatability of the field center measure- ment for the...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7654.pdf
2
974d60a6-f119-44d8-96f4-aa8b858cd847
net (12 cases) • Excitation error s in a quadrupole magnet (4 cases) • Excitation errors in a sextupole magnet (4 cases) • Misalignment errors in quadrupole, sextupole and oc-tupole magnets The simulations indicate that fabrication and assembly errors associated with a single pole can generate sextupole and...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7654.pdf
2
ad688598-d0b5-4286-b4e4-ead346c973f9
iations in the number of coil turns and deficiencies in elec- trical insulation. The results show that asymmetric excita- tion errors produce sextupole and skew sextupole compo- nents in quadrupole magnets, as well as normal and skew octupole and decapole components in sextupole magnets, while the impact on higher -o...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7654.pdf
2
6aad234e-2ead-4398-9c22-ac1609b5d217
mechanisms and offer guidance for improving the magnet prototype design and manufacturing process . CONCLUSION The measurement s of magnet prototype s for SPS- II stor- age ring demonstrate that, for each magnet type (dipole, combined dipole, quadrupole, sextupole and octupole), at least one magnet satisfies t...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7654.pdf
2
a4aab08f-4a7a-45c0-9a13-adb561eacecc
vide valuable guidance for refining the design, fabrication and assembly processes prior to mass production. ACKNOWLEDGEMENT The authors would like to express their sincere gratitude to J.C. Jan and colleagues at the National Synchrotron Ra- diation Research Center (NSRRC), Taiwan, for their valu- able support an...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7654.pdf
2
01369b28-206f-4713-8968-17e8498d2a65
[2] P. Sunwong et al. , “Design of dipole magnets for Siam Pho- ton Source II ”, J. Phys .: Conf . Ser., vol. 2431 , pp. 012072 , 2023. doi:10.1088/1742- 6596/2431/1/012072 [3] P. Sunwong et al. , “Development of type A quadrupole mag- net for Siam Photon Source II ”, Particles , vol. 6, pp. 664 -673, 2023. doi:10...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7654.pdf
2
ed7fd034-2ad3-42ab-935b-ba0bf4368a10
[4] G. Le Bec et al , “Single sided dipole -quadrupole magnet for the Extremely Brilliant Source storage ring at the European Synchrotron Radiation Facility”, Phys. Rev. Accel. Beams., vol. 22, pp. 102402, 2019. doi:10.1103/PhysRevAccelBeams.22.102402 [5] Z. Ren et al, “Design of the combined function dipole -q...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7654.pdf
3
08efc2f3-8534-4637-b2c9-5d5a0a30f6e5
ISBN: 978-3-95450-252-3 ISSN: 2673-5350 doi: 10.18429/JACoW-IPAC2026-TUP7654 1706 MC7.T09: Normal Conducting MagnetsTUP7654 TUP: Poster session Content from this work may be used under the terms of the CC BY 4.0 licence (© 2026). Any distribution of this work must maintain attribution to the author(s), title of the wor...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7654.pdf
3
8cdd845a-d128-45bc-b8e1-4eaacf09082e
VALIDATION OF AN IMPROVED QUADRUPOLE DESIGN FOR THE 3 GeV SPS -II STORAGE RING T. Leetha†, P. Numanoy , T. Phimsen , S. Prawanta, P . Sunwong Synchrotron Light Research Institute (Public Organization) , Nakhon Ratchasima, Thailand Abstract Achieving high beam stability in the 3 GeV SPS -II storage ring crit...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7655.pdf
0
c314bb6d-e5e9-4bd7-a820-5ccdfd6d0773
pole removal and re -assembly for coil installation to solve this specific problem, an improved quadrupole design was employed. The new symmetrical geometry eliminates the pole -removal step, thus intrinsically preventing the assembly error and significantly increasing structural stability and field quality. Coup...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7655.pdf
0
b7609c62-d16f-42c3-8bf5-b2a441f27cea
comparison of magnetic field measurements from both the initial and the improved prototypes, definitively verifying the enhanced performance necessary for SPS -II commissioning. INTRODUCTION The Siam Photon Source II (SPS II), Thailand’s second synchrotron light source, is a 3.0 GeV fourth generation facility base...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7655.pdf
0
7adb5182-2215-41d0-b7ab-0d9a7dcfcd5b
of DTBA storage rings, providing strong focusing required for ultralow emittance and precise control of functions and dispersion in compact lattices. [1, 2] Their field quality is critical for nonlinear cancellation, dynamic aperture, and beam lifetime, while the compact layout increases sensitivity to magnetic ...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7655.pdf
0
4307876b-5e74-42ed-b229-b65f20a7d1d1
improved design. MAGNET DESIGN The mechanical design of the quadrupole magnet was developed using SOLIDWORKS, where the iron‑core geometry and mounting interfaces were refined following the prescribed pole‑profile specifications. Structural integrity and natural frequencies were subsequently evaluated using ANSY...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7655.pdf
0
26c4f17e-dc4b-4f57-a66d-3470a3a6818b
non‑correctable multipole components, particularly problematic in the compact DTBA environment. [3, 4] In this study, Magnet Type  A was designed and fabricated; magnetic‑field measurements revealed assembly‑related errors, as illustrated in Fig . 1. Consequently, Magnet Type  B was developed with fully symmetric...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7655.pdf
0
e8f06357-3988-4f43-9e61-8717a49e8945
RESULTS Magnet Deformation Structural simulation was performed to evaluate the mechanical stability of the quadrupole magnet under realistic conditions. The AISI 1006 steel core was modelled as isotropic, with appropriate contact definitions, assembly loads, and support boundary conditions applied to assess str...
D:\Daily_ihep\Conferences\IPAC2026\TUP\TUP7655.pdf
1