Datasets:
Formwork has a dual function in concrete construction – it supports the plastic and hardening concrete until it is sufficiently strong to support the actions/loads imposed upon it, and it imparts a finish to the concrete surface. This Section describes the different types of formwork used in modern concrete construction and outlines the requirements which must be met for formwork to perform satisfactorily. The special requirements associated with the achievement of visually satisfying surface finishes are discussed in Part V, Section 16 ‘Control of Surface Finishes’ in this Guide. 7.2 UNDISTURBED SHORES............ 12 CONTENTS 7.3 RESHORING SYSTEMS .............. 13
- INTRODUCTION ................................... 2 8. CONSTRUCTION OF FORMWORK ... 13
- BASIC COMPONENTS OF 8.1 ERECTION .................................. 13 FORMWORK ........................................ 3 8.2 PREPARATION FOR
- REQUIREMENTS FOR FORMWORK ... 4 CONCRETING ............................. 13 3.1 GENERAL ...................................... 4 8.3 EXTERNAL VIBRATION .............. 14 3.2 STRENGTH .................................... 4 8.4 STRIPPING FORMWORK............ 15 3.3 STIFFNESS .................................... 5 9. FORMWORK DOCUMENTATION ...... 15 3.4 ACCURACY ................................... 5 10. SUMMARY – CONSTRUCTION CHECKLIST ....................................... 17 3.5 WATER-TIGHTNESS ..................... 5
- RELEVANT AUSTRALIAN 3.6 PERMEABILITY.............................. 5 STANDARDS ..................................... 18 3.7 ROBUSTNESS ............................... 5 3.8 EASE OF STRIPPING .................... 6
- INTRODUCTION 3.9 STANDARDISATION ...................... 6 3.10 SAFETY ......................................... 6 Formwork is the temporary structure which (a)
- MATERIALS FOR FORMWORK ........... 6 moulds concrete into the desired shape and (b) holds it in the correct position until it is able to 4.1 GENERAL ...................................... 6 support the loads imposed upon it. It also 4.2 CHOICE OF MATERIALS ............... 6 imparts the required surface finish. Importantly, 4.3 FORM LINERS ............................... 7 formwork also provides safe working areas and access ways for construction personnel.
- FORMWORK SYSTEMS ....................... 8 Formwork and its supports (known as 5.1 MODULAR FORMWORK ............... 8 falsework) is a structural system and must be designed and built accordingly. The actions 5.2 GANG FORMS ............................... 8 (loads) imposed on it may be temporary, but 5.3 TABLE FORMS............................... 8 they can be extremely large. Frequently they 5.4 JUMP/CLIMB FORMS .................... 9 are different in nature to those imposed on the finished concrete structure. 5.5 SLIP-FORMS.................................. 9 5.6 PERMANENT FORMWORK ......... 10 Concrete is an extremely plastic and mouldable material which will accurately reflect the shape,
- DESIGN OF FORMWORK ................... 10 texture and finish of the surface against which it 6.1 GENERAL .................................... 10 is cast. Any imperfection or inaccuracy in this surface will be indelibly inscribed onto the 6.2 LOADS ON FORMWORK ............. 10 concrete surface. Form-face materials must
- FALSEWORK...................................... 12 therefore be chosen both to achieve the 7.1 DESIGN OF SUPPORT required surface finish and, in conjunction with STRUCTURES ............................. 12 all the supporting elements, to maintain PAGE 2 > Guide to Concrete Construction — Part IX-Section 27 – Formwork Version 1.0
accuracy and stability under all of the loads • Walers or bearers – which brace the imposed during erection and placing – typically studs or support the joists and prevent for at least several days into the life of the bulging or bowing in the other direction. concrete structure.
| An important | facet of formwork | design and | |||||||
|---|---|---|---|---|---|---|---|---|---|
| At early ages, the concrete will not be able to construction is the choice of spans (or centres) | |||||||||
| support the loads imposed on it. Until the between studs, and also centres between | |||||||||
| concrete is able to support the imposed loads | |||||||||
| walers or bearers – both of which are important | |||||||||
| the formwork (and falsework) will be the primary in preventing bulging and bowing. | |||||||||
| loadbearing structure. Only when the concrete | |||||||||
| has | achieved | sufficient | strength | can | the | ||||
| ---- | --------- | ----------- | --- | --------- | ---- | ---- | --- | --- | --- |
| formwork be removed without detriment to the | |||||||||
| safety or performance of the concrete structure. | |||||||||
| Failure to meet accuracy, stability and strength | |||||||||
| requirements will lead to formwork failures in | |||||||||
| the form of bowing, warping or misalignment | |||||||||
| which will be reflected in the final structure. | |||||||||
| Such | problems | could | even | lead | to the | ||||
| ------------- | --------- | --------- | --- | ---------- | ----- | -------- | --- | --- | --- |
| catastrophic | collapse | of | part (or | all) | of the | ||||
| formwork. | |||||||||
| The | cost | of formwork | is | generally | a very | ||||
| ---- | ----- | ------------- | --- | ---------- | --- | -------- | --- | --- | --- |
| significant item in the overall cost of a project. | |||||||||
| The | formwork | system | should | be | the | most | |||
| ---- | --------- | ------- | ------- | --- | ---- | ----- | --- | --- | --- |
| Figure 27.1 – Wall Forms | |||||||||
| economical | available | – | but cost | concerns | |||||
| ----------- | ------ | ---------- | ---------- | ---------- | --------- | ---- | --- | --- | --- |
| should | never | be | permitted | to | overrule | the | |||
| criteria governing safety, strength and stability. | |||||||||
| In reality, the initial cost of formwork may be a | |||||||||
| very poor guide to its suitability for a project. | |||||||||
| Multiple | uses of good | quality | formwork | can | |||||
| --------- | --- | --------------- | -------- | --------- | --- | ---- | --- | --- | --- |
| result in improved overall project economies. | |||||||||
| Formwork | design and | selection | of materials | ||||||
| --------- | --- | ------------ | ---------- | --- | -------------- | --- | --- | --- | --- |
| should therefore always be approached on the | |||||||||
| basis of ‘cost per use’. |
- BASIC COMPONENTS OF
FORMWORK Figure 27.2 – Beam Form and Supports
The basic components of formwork for typical concrete elements are shown in Figures 27.1 to 27.4. The basic structure of almost all formwork is the same. It comprises: • Form-face – which creates the surface finish e.g. metal or plywood sheet, sawn timber; • Studs, or joists – lengths of sawn timber
| or | (sometimes) | metal | sections | which | |||||
|---|---|---|---|---|---|---|---|---|---|
| support the form-face and prevent it from | |||||||||
| bulging or bowing in one direction; and | |||||||||
| Figure 27.3 – Column Forms |
PAGE 3 > Guide to Concrete Construction — Part IX-Section 27 – Formwork Version 1.0
However, even metal components may become loose fitting or broken due to wear. All formwork materials and components must be checked regularly to ensure that they are sound and safe. Table 27.1 – Requirements for Formwork
| Property | Purpose | ||||||
|---|---|---|---|---|---|---|---|
| Strength | Carry imposed loads | ||||||
| Stiffness | Maintain specified | ||||||
| shape and avoid | |||||||
| Figure 27.4 – Typical Soffit Forms and Falsework distortion of concrete | |||||||
| elements | |||||||
| (diagrammatic only; bracing not shown) | |||||||
| Accuracy | Ensure shape and size | ||||||
| --------------------- | --- | --- | --- | --- | --- | --------- | ---------------------- |
| 3. REQUIREMENTS FOR | of concrete elements; | ||||||
| Ensure specified cover | |||||||
| FORMWORK | |||||||
| to reinforcement. | |||||||
| 3.1 GENERAL | |||||||
| Watertightness | Avoid grout loss and | ||||||
| --- | --- | --- | --- | --- | --- | --------------- | --------------------- |
| subsequent | |||||||
| Although | formwork | is | constructed | only to | |||
| --------- | --------- | --- | ------------ | --- | --------- | --- | --- |
| honeycombing of the | |||||||
| contain | and support | concrete | until | the cast | |||
| -------- | ------------- | --------- | --- | ------ | ---------- | --- | --- |
| concrete | |||||||
| structure | is strong | enough | to support | the | |||
| ---------- | ----------- | ------- | --- | ------------ | ---- | --- | --- |
| imposed loads itself, it must provide a safe Permeability When used, permeable | |||||||
| formwork allows water | |||||||
| environment for all those working on or around | |||||||
| it. In addition to being strong enough, it must and air to be removed | |||||||
| also be stable against overturning, uplift, and from the formed surface | |||||||
| sideways movements. It must also meet all | |||||||
| statutory requirements for access ladders, Robustness Enable re-use | |||||||
| guardrails, | working | platforms, | etc. | Where | |||
| ------------ | -------- | ----------- | --- | ----- | ------ | ------------------ | ---------------- |
| Ease of stripping | Avoid damage to | ||||||
| Importance Level II and Importance Level III | |||||||
| criteria (see AS 3610.1 – Appendix A) are met, concrete surfaces | |||||||
| formwork documentation that (a) sets out the | |||||||
| Standardisation | Promote economy | ||||||
| --- | --- | --- | --- | --- | --- | ---------------- | ---------------- |
| requirements of the formwork design, (b) states | |||||||
| that the | design | conforms | with AS | 3610 | |||
| ---------- | ------- | --------- | --- | --------- | ----- | ------- | ---------------------- |
| Safety | Ensure a safe working | ||||||
| requirements, and (c) allows the formwork to be | |||||||
| verified | and | inspected, | is | a mandatory | environment | ||
| ------------ | ---- | ----------- | ------ | ------------- | --- | --- | ------------ |
| requirement | of | AS 3610. | Where | proprietary | |||
| 3.2 STRENGTH | |||||||
| formwork | systems | are | used, | formwork | |||
| -------------- | -------- | ---- | -------- | ---------- | --------- | --- | --- |
| documentation | can | contain | brochures | ||||
| All components should be designed to cater for | |||||||
| describing | the | formwork | – | provided | these | ||
| ----------- | ---- | --------- | --- | --------- | ------ | --- | --- |
| the most severe loads that are likely to be | |||||||
| contain | a suite | of information | described | in | |||
| -------- | --------- | ---------------- | --- | ---------- | ---- | --- | --- |
| AS 3610 (see also sub-section 9). imposed on the formwork. To achieve this, the | |||||||
| formwork design should be carried out by a | |||||||
| The general requirements for formwork are person experienced and competent in such | |||||||
| summarised | in Table | 27.1. | Additional | design. | |||
| ----------- | --- | ---------- | ------ | --- | ----------- | -------- | --- |
| information is contained in AS 3610. | |||||||
| Care should then be taken to ensure that the | |||||||
| With new materials, these requirements may be design details are met and that the construction | |||||||
| readily met. With re-use, all materials (except loads imposed on the formwork are within the | |||||||
| perhaps metal components) may be weakened. | |||||||
| limits nominated by the designer. |
PAGE 4 > Guide to Concrete Construction — Part IX-Section 27 – Formwork Version 1.0
Sound materials should always be used. Re- 3.4 ACCURACY used material may be satisfactory but should be checked regularly to ensure it is in good In general, formwork should always be built to condition and adequate for the job in hand. The an accuracy greater than that desired in the strength of each item of formwork material finished concrete structure or element. All contributes to the overall safety of the support structures should be sufficient to temporary structure. ensure that this accuracy is maintained until the concrete has hardened. Particular care is required with formwork design and application where flowing concrete (also The accuracy required may affect the selection known as Super Workable Concrete or Self of the material from which the formwork is to be Compacting Concrete – see Section 22 ‘Super- built, as some materials may be able to be Workable Concrete’ in this Guide) as these assembled to tighter tolerances than others. materials can exert full hydrostatic pressure on the formwork, resulting in significantly higher 3.5 WATER-TIGHTNESS pressures on the formwork than are seen with conventional ‘slumped’ concrete. This is All joints should be sealed to stop grout (cement particularly the case for formwork in vertical and water) leaking from the formwork. Grout structures such as columns and walls. loss causes ragged edges, hydration staining and honeycombing which can affect strength, 3.3 STIFFNESS durability and appearance in the final structure. These issues can be exacerbated when using Formwork should not bow, bulge, sag or flowing concretes of the types described in sub- otherwise move to the extent that the section 3.2. completed concrete element falls outside the tolerances specified for the work. 3.6 PERMEABILITY The formwork designer should detail the formwork elements to have adequate stiffness, Systems using formwork with high permeability but site personnel are responsible for ensuring have some advantages. There are several that (a) the correct materials are used, (b) they systems available, but they may be as simple are of adequate quality, and (c) they are used as a fabric material attached to plywood in the proper manner. For example – plywood backing which contains drain holes. This type of sheeting for general formwork use has a formwork allows ‘bleed’ water and air to escape greater strength in one direction relative to the through the formed faces with the effects of (a) other. It should always be used in the correct lowering W/C ratio in the areas adjacent (to a orientation, as shown in Figure 27.5. depth of about 20 mm) to the formwork, (b) increasing the strength and reducing sorptivity and permeability in these outer areas, and (c) improving the finish at these surfaces. 3.7 ROBUSTNESS Formwork should be robust enough to withstand repeated stripping, storing and erection. Re-use of formwork is an important element in improving the overall economy of the structure. The extent of possible re-use varies with formwork materials – with ranges from ‘up to 5 times’ for plywood to 20-30 times for Figure 27.5 – Orientation of Plywood fibreglass and 50-100 times for steel. For form liners (see 4.3), re-use can vary from 1-20 times PAGE 5 > Guide to Concrete Construction — Part IX-Section 27 – Formwork Version 1.0
for timber (with varying surface treatments) to The stripping procedures (see 8.4) specified up to 100 times for rubber. must not be modified and limits placed on stacked materials anywhere on the formwork
must not be exceeded. 3.8 EASE OF STRIPPING
Formwork should be easy to remove – to avoid 4. MATERIALS FOR FORMWORK or minimise damage to the concrete and/or to the forms. Consideration should therefore be 4.1 GENERAL given to providing adequate draw (taper) on vertical faces and also to the movement which Formwork can be constructed in a variety of must be allowed in supports to facilitate easy ways and from a number of materials. The size removal of horizontal soffit forms and specialist
| and nature | of | the | project | will most | likely | |||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| systems such as table forms. | ||||||||||||
| determine which materials and which systems | ||||||||||||
| are likely to maximise technical and economic | ||||||||||||
| --- | --- | --- | --- | --- | --- | --- | ---------------------------------------------- | --- | --- | --- | --- | --- |
| imperatives. For example, on some projects, | ||||||||||||
| 3.9 STANDARDISATION | ||||||||||||
| particularly | small | ones, | certain | formwork | ||||||||
| --- | --- | --- | --- | --- | --- | --- | ------------- | ------ | ------ | --- | -------- | --------- |
| As far as possible, formwork components elements are likely to be used only a relatively | ||||||||||||
| small number of times. Considerable cutting | ||||||||||||
| should | be standardised | in size | to | avoid | ||||||||
| ------- | ----------------- | --- | --- | --------- | --- | ------ | --- | --- | --- | --- | --- | --- |
| unnecessary cutting. They should be able to be and fitting may be involved with consequent | ||||||||||||
| wastage | of | materials. | The | use | of lower | |||||||
| --- | --- | --- | --- | --- | --- | --- | -------- | --- | ----------- | ---- | ---- | ---------- |
| stripped, shifted and re-erected rapidly if speed | ||||||||||||
| grade/cost materials may then be justified – | ||||||||||||
| of construction | is | to be | maintained. | This | ||||||||
| ----------------- | --- | --- | ------- | ------------ | --- | ----- | --- | --- | --- | --- | --- | --- |
| necessitates a system that comes apart easily, provided safety is not jeopardised. | ||||||||||||
| has a | minimum | of | elements | needing | to be | |||||||
| ------- | -------- | --- | --------- | -------- | --- | ------- | --- | --- | --- | --- | --- | --- |
| On larger projects, or with multiple projects, the | ||||||||||||
| replaced (i.e. those damaged during removal) | ||||||||||||
| use of specifically designed and constructed | ||||||||||||
| and is | easily | shifted | with the | available | ||||||||
| ----------- | ------- | -------- | ----- | ---------- | ---------- | -------- | --------- | --------- | ---------------- | ---------- | --- | --------- |
| formwork | elements | can lead | to | improved | ||||||||
| equipment. | On | small | jobs | this | will | involve | ||||||
| economy. | Standardisation | and | ||||||||||
| ‘manhandling’, but on large jobs crane capacity | ||||||||||||
| interchangeability | then | become | particularly | |||||||||
| --- | --- | --- | --- | --- | --- | --- | ------------------- | --- | ----- | ------- | ------------- | --- |
| may be used to improve efficiencies. | ||||||||||||
| important selection criteria. | ||||||||||||
| Standardisation | for | speed | of | construction | ||||||||
| ---------------- | --- | ---- | ------ | --- | ------------- | --- | --- | --- | --- | --- | --- | --- |
frequently requires more expensive formwork 4.2 CHOICE OF MATERIALS but, once re-use is taken into account, lower overall project costs can be achieved.
| Many materials | may | be used | for formwork. | |||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Table 27.2 provides a brief overview of the | ||||||||||||
| 3.10 | SAFETY | characteristics of those in common use. | ||||||||||
| Before | the final | selection | of the | formwork | ||||||||
| Formwork | must | provide | a safe | working | ||||||||
| material | is made | for | a particular | project, | a | |||||||
| environment | for all | those | working | on and | ||||||||
| number | of factors | should | be considered, | |||||||||
| around | it. In | addition | to | being | of adequate | |||||||
| including: | ||||||||||||
| strength, | it | must | also | be stable | against | |||||||
| ------------- | --- | -------- | ----- | ----------- | --- | -------- | --- | --- | --- | --- | --- | --- |
| overturning, | uplift, | and | sideways | or | sliding | |||||||
| • The size of the forms; | ||||||||||||
| movements. | Properly | guarded | walkways | |||||||||
| ----------- | --- | --------- | --- | -------- | --------- | --- | --- | --- | --- | --- | --- | --- |
| • The shape of the forms; | ||||||||||||
| should | be | provided | around | all areas | of | |||||||
| ------- | --- | --------- | ------- | --- | ----------- | --- | --- | --- | --- | --- | --- | --- |
| • The surface finish quality required; | ||||||||||||
| suspended work to provide safe access to them | ||||||||||||
| • The accuracy required; | ||||||||||||
| during construction, as should a safe means of | ||||||||||||
| • The number of re-uses required; | ||||||||||||
| withdrawal | as | concreting | progresses. | All | ||||||||
| ----------- | --- | ----------- | --- | ------------ | --- | ---- | --- | --- | --- | --- | --- | --- |
| • The handling methods proposed; | ||||||||||||
| statutory requirements must be met. | ||||||||||||
| • The methods of compaction proposed; | ||||||||||||
| The tightness of all components must be • The methods of curing proposed; and | ||||||||||||
| thoroughly checked prior to pouring concrete. | ||||||||||||
| • Safety. |
PAGE 6 > Guide to Concrete Construction — Part IX-Section 27 – Formwork Version 1.0
The weighting given to each factor will vary from textures and patterns on the concrete surface – project to project. On small projects, where typically a scene or portrait. multiple uses of formwork elements are unlikely and a great deal of cutting and fitting may be required, timber sections may well be appropriate. On major projects, where standardised components can be employed and multiple re-use achieved, heavier steel sections may well be warranted. Modular units may also be viable in such circumstances. In the final analysis, the choice of formwork materials is a matter of cost, suitability and availability. Most of the commonly accepted materials can be made to work in most situations. The quality of the finish required, and the overall cost of the formwork, are likely to be the principal determinants in choosing materials. (a) 4.3 FORM LINERS Form liners are effectively a mould placed on the inside of formwork and are used to create simple or complex designs or textures on the surface of concrete (Figure 27.6). The use of form liners has expanded the architectural applications of concrete hugely, and it is really open to the designer to create as complex a pattern as can reasonably be imposed on a concrete surface. When combined with coloured concrete the architectural scope expands even further. A wide variety of materials can be used as form liners, with important considerations being (a) the complexity of the design required, and (b) the extent of re-use of the form liner that is required. (b) For low levels of re-use materials like Figure 27.6 – Variety of Textures and Patterns achieved cardboard, rigid plastics, polystyrene or by Using Form Liners tempered hardboard have been used. These will generally only provide one or two castings. Detailed information on the use of form liners For high levels of re-use, rubbers and synthetic and their range of applicability is given in the polymers are common. Patterns can also be CCAA Briefing 06 ‘Form Liners – Achieving created when form liners are coated (partially) Surface Relief and Texture’ (June 2002). with a retarding agent to create different PAGE 7 > Guide to Concrete Construction — Part IX-Section 27 – Formwork Version 1.0
Table 27.2 – Formwork Materials Material Uses Timber Commonly used for studs, bearers, joists, walers etc. as it is readily available and easily worked with conventional tools. Has good load-carrying capacity and some suitable species are relatively light-weight, e.g. Oregon. Australian hardwoods tend to be heavier and more susceptible to warping. Some species of pine also tend to splinter or split when nailed. Steel Steel sections are used in formwork framing, particularly in patented systems. Strong and robust, steel-framed formwork is capable of multiple re-uses but requires a degree of standardisation to warrant its additional cost. It is commonly used in precasting yards, particularly for repetitive work. Coated plywood Commonly used for soffits or as form liners in beams, columns and similar elements. Readily worked, coated plywood (properly handled) is capable of multiple re-uses. Cardboard Has been used in column and waffle forms. Normally suitable for one-off use only. Glass reinforced concrete Commonly used as permanent formwork, where it provides a decorative finish, or in (GRC) or plastic moulds to achieve intricate shapes – particularly for precast elements. Generally, it is relatively durable and capable of multiple re-uses. Concrete Precast concrete elements are used as permanent formwork – where the precast element is exposed to view in the completed structure. Also used to provide permanent forms in precast concrete factories where it is very economical for standard elements or components. Rubber, thermoplastic and Used as form liners to provide intricate effects and for decorative finishes. Rubber and polystyrene materials thermoplastic sheeting are used for decorative finishes and are suitable for multiple uses. 5. FORMWORK SYSTEMS Adequate cranage is essential for handling gang forms but the cost of the cranage is offset 5.1 MODULAR FORMWORK by the increased speed of construction offered by moving large units of formwork from one A number of formwork systems comprising location to another. modular units are available on a sale or hire 5.3 TABLE FORMS basis. The systems generally incorporate modular panels so that they can be re-used on Table forms are a type of gang form used to a wide variety of jobs. Panels may use a steel form soffits. Large sections of soffit form, frame with plywood facing which can be complete with propping and bracing elements, replaced when necessary. Generally, such can be fabricated into a single unit which, after systems incorporate simple but effective means use, can be lowered from the soffit, transported of support and fixing. to the edge of the floor, lifted to the next level 5.2 GANG FORMS by the crane and realigned ready for the next concrete placement (Figure 27.7). Gang forms are individual components, often modular, made up into large panels that are then tied and braced so that they can be moved as a complete unit. PAGE 8 > Guide to Concrete Construction — Part IX-Section 27 – Formwork Version 1.0
| free from | the slipform. | Slip-forming | can be | |||||||
|---|---|---|---|---|---|---|---|---|---|---|
| undertaken | either | vertically | (e.g. | for silos, | ||||||
| towers and lift shafts) or horizontally (e.g. for | ||||||||||
| roads and safety barriers). | ||||||||||
| Figure 27.7 – Typical Use of Table Forms |
A 'transporter' is often used to wheel the table forms to the edge of the building, where a special rig enables the crane to handle them efficiently. Table form systems are of particular use in Figure 27.8 – Typical Self-climbing Formwork System multi-storey building construction where speed
is important, adequate cranage is available and the initial cost of formwork can be offset by On vertical elements, the slipform has shutters multiple re-uses. on both faces that are lifted vertically, at a
| predetermined | rate | by a | series | of hydraulic | ||||||
|---|---|---|---|---|---|---|---|---|---|---|
| 5.4 JUMP/CLIMB FORMS jacks (Figure 27.9). Typical rates of slip- | ||||||||||
| forming vary from 300-400 mm per hour. Some | ||||||||||
| Jump or climb forms are gang forms for casting | ||||||||||
| projects are slip-formed continuously, whilst on | ||||||||||
| vertical elements such as walls and shafts. others the free-standing height is limited to a | ||||||||||
| They are | equipped | with | simple | and | rapid | |||||
| ---------- | --------- | ----- | ------- | ---- | ------ | --- | --- | --- | --- | --- |
| few storeys. | ||||||||||
| mechanical | means | of | handling, | require | a | |||||
| ----------- | ------ | --- | ---------- | -------- | --- | --- | --- | --- | --- | --- |
| Slip-forming is not recommended where a high | ||||||||||
| minimum | of labour | and | do | not rely | on the | |||||
| -------- | ----------- | ---- | --- | ---------- | -------- | --- | --- | --- | --- | --- |
| availability of cranage (Figure 27.8). degree of colour control on the finished surface | ||||||||||
| is necessary as colour banding is very difficult | ||||||||||
| The system strips the form, shifts it to the new | to avoid. | |||||||||
| ------------------------------------------------- | ---------- | ---------- | --- | ---------- | --------- | ---------- | --- | --- | --- | --- |
| position | and then | re-aligns | it using | its own | ||||||
| On horizontal construction, it can be used in its | ||||||||||
| inbuilt jacking system. Daily casting cycles are | ||||||||||
| common. | most simple | form | to construct | kerbs and | ||||||
| -------- | --- | --- | --- | --- | --- | ------------- | ----- | -------------- | --- | ----------- |
| channels and, in the more sophisticated form, | ||||||||||
| Jump or climb form systems are capable of to construct roads or channel linings. Horizontal | ||||||||||
| producing a high-quality finish with good colour | ||||||||||
| paving rates of up to 2 km per day have been | ||||||||||
| control. | ||||||||||
| achieved on large projects but an average rate | ||||||||||
| of 300-500 m per day is more common. No |
edge forming is generally used for this work and 5.5 SLIP-FORMS the concrete must be made to a consistency sufficient to avoid slumping once it is free of the
| Slipform | systems | incorporate | continuously | |||||||
|---|---|---|---|---|---|---|---|---|---|---|
| machine. | Slip-forming | is | discussed | in more | ||||||
| moving formwork to speed construction and to | ||||||||||
| detail in Section 19 ‘Slip-formed Concrete’ of | ||||||||||
| eliminate the need for large areas of formwork. | ||||||||||
| this Guide. | ||||||||||
| The concrete | being | 'extruded' | must | have | ||||||
| ------------------------------------------------ | ------ | --- | ----------- | ----- | ----- | --- | --- | --- | --- | --- |
| adequate stiffness to hold its shape once it is |
| Version 1.0 | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|
| PAGE 9 > Guide to Concrete Construction — Part IX-Section 27 – Formwork |
Precast concrete and glass reinforced concrete
| (GRC) | are commonly | used for permanent | ||
|---|---|---|---|---|
| formwork – the former being used where the | ||||
| form takes part of the structural loads and the | ||||
| latter | where decorative | finishes | only are | |
| ---------- | ------------------ | -------- | ---------- | ---------- |
| required. | The | use of | permanent | forms |
| minimises subsequent finishing operations and | ||||
| often reduces | the scaffolding | and | falsework | |
| --------------- | ---------------- | --- | ---- | ---------- |
| required for these operations. |
- DESIGN OF FORMWORK
6.1 GENERAL
The design of formwork, particularly on large
projects, calls for a considerable degree of skill
and experience. Not only can the loads on it be
both large and complex, but stripping procedures, and the way they cause loads to be transferred to the concrete structure, are of considerable complexity and importance. Whilst the actual design should always be ------- ------------ ------- --------------- --- Figure 27.9 – Slip-forming a Vertical Element undertaken by a specialist formwork designer,
all involved with either the erection or removal 5.6 PERMANENT FORMWORK of formwork on the construction site should be
| aware | of the | factors | which affect | its |
|---|---|---|---|---|
| Permanent formwork is a type of formwork performance, and in particular its strength and | ||||
| which is left in place to become part of the stability – and hence its safety. AS 3610.1 sets | ||||
| out requirements | for | the design | and | |
| ------------------ | --- | ---- | ------------ | ---- |
| finished structure (Figure 27.10). It may assist | ||||
| in taking some of the structural load or simply construction of formwork which are aimed at | ||||
| provide a permanent decorative finish. ensuring its effectiveness and safety. |
6.2 LOADS ON FORMWORK Formwork should be designed to support both
| the vertical | and | horizontal | loads which | are |
|---|---|---|---|---|
| imposed on it whilst it is being erected and while | ||||
| it is in position. In supporting these loads, the | ||||
| formwork | should | not | deflect excessively, | |
| --------- | ------- | ---- | ---------------------- | --- |
| buckle, bulge or otherwise move out of position. | ||||
| The most severe loading generally occurs when | ||||
| the concrete is being placed. However, this is | ||||
| not always | the | case, so | it is common | to |
| ------------ | ---- | ---------- | --------------- | --- |
| consider the loads on formwork at three stages | ||||
| of construction: | ||||
| During Erection – Loads on formwork during | ||||
| erection can arise from two principal sources, | ||||
| Figure 27.10 – Precast Permanent Formwork used | ||||
| for an Edge beam of a Multi-storey Building (a) the weight of material, equipment etc. which | ||||
| may be stacked on it prior to concreting; and (b) |
| Version 1.0 | ||||
|---|---|---|---|---|
| PAGE 10 > Guide to Concrete Construction — Part IX-Section 27 – Formwork |
the effect of wind which may exert both vertical on the formwork, and particularly on the props and horizontal forces on the formwork and its supporting lower floors (see 7.3). supports. Care should therefore be taken to Of prime importance, however, is the lateral
| avoid excessive | load | concentrations | and | to | |||||
|---|---|---|---|---|---|---|---|---|---|
| pressure exerted on side forms during and after | |||||||||
| ensure that | bracing | is installed | as early | as | |||||
| ------------- | -------- | -------------- | ---------- | --- | --------- | ------------ | ---------- | ---------- | ---- |
| concrete | compaction. | Vibration | liquefies | the | |||||
| possible, and certainly before the formwork is | |||||||||
| concrete and increases the pressure exerted on | |||||||||
| used as a working platform (Figure 27.11). | |||||||||
| the forms | (Figure | 27.13). | Due | allowance | |||||
| --- | --- | --- | --- | --- | ----------- | -------- | -------- | ---- | ---------- |
| should be made for this, particularly with deep | |||||||||
| pours, such as columns. | |||||||||
| Figure 27.11 – Loads on Formwork prior to | |||||||||
| Construction |
During Concreting – During concreting, the concrete itself imposes a considerable dead weight on the forms. In addition, the weight of men and equipment on the platform should be Figure 27.13 - Lateral Pressures on Formwork taken into account. At this stage, lateral stability during Compaction should also be considered. The formwork with
its load of plastic concrete is inevitably top- heavy and therefore particularly susceptible to The lateral pressure exerted by fluid concrete sideways movement. The possibility of impact during compaction is by far the most severe
| arising from | a wayward | concrete | bucket | or | |||||
|---|---|---|---|---|---|---|---|---|---|
| loading | experienced | by | vertical | forms. | |||||
| similar mishap | should | also be | considered | ||||||
| Problems | such as | form | liners bulging | and | |||||
| (Figure 27.12). deflecting between supports frequently arise | |||||||||
| because the magnitude of the lateral pressure | |||||||||
| is underestimated. This is particularly the case | |||||||||
| with deep | narrow | forms, | where it | is often | |||||
| --- | --- | --- | --- | --- | ----------- | ------- | ------- | ---------- | ---------- |
| assumed the loads will be less than in (say) | |||||||||
| heavy columns. In fact, the width of formwork | |||||||||
| has little influence on lateral pressure, with the | |||||||||
| principal consideration being the height of the | |||||||||
| fluid concrete. | Factors | influencing | lateral | ||||||
| --- | --- | --- | --- | --- | ----------------- | -------- | --- | ------------ | -------- |
| pressure are set out in Table 27.3. | |||||||||
| In general terms, any factor which increases the | |||||||||
| fluidity of the concrete, or the height of fluid | |||||||||
| Figure 27.12 – Loads on Formwork during concrete, increases the lateral pressure on the | |||||||||
| Construction | formwork (see also comments about flowing | ||||||||
| ------------- | --- | --- | --- | --- | ---------------------------------------------- | -------- | ------- | -------- | -------- |
| concrete in sub-section 3.2). Conversely, any | |||||||||
| factor which | reduces | these, | reduces | lateral | |||||
| After Concreting – On multi-storey projects, it | |||||||||
| pressure (Figure 27.13 and Table 27.3). | |||||||||
| is usual for work to proceed on upper floors | |||||||||
| while the concrete structure below is still gaining | |||||||||
| ---------------------------------------------------- | -------------- | ------- | ---------- | --- | --- | --- | --- | --- | --- |
| strength. | Consideration | should | therefore | be | |||||
| given to these additional loads being imposed |
| Version 1.0 | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| PAGE 11 > Guide to Concrete Construction — Part IX-Section 27 – Formwork |
Table 27.3 – Formwork Materials during the placing activities. Problems during reshoring operations and premature falsework Effect on or formwork removal have also been significant
| Factor | lateral | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| pressure | causes of structural failures. | ||||||||||
| Increasing concrete | Increases | ||||||||||
| All support | systems | should | be | adequately | |||||||
| density | |||||||||||
| braced | to | ensure | stability | and | prevent | ||||||
| --- | --- | --- | --- | --- | --- | ------- | --- | ------- | ---------- | ---- | -------- |
| Increased rates of Increases progressive collapse. Bracing should be | |||||||||||
| placing | provided in two directions at right angles to | ||||||||||
| -------- | --- | --- | --- | --- | --- | ---------------------------------------------- | --- | --- | --- | --- | --- |
| each other and be provided near the edges of | |||||||||||
| Increased heights of pour | Increases | ||||||||||
| -------------------------- | --- | --- | ---------- | --- | --- | --- | --- | --- | --- | --- | --- |
| the system where concrete placement is likely | |||||||||||
| Internal vibration Increases to commence. All bracing should be between | |||||||||||
| 30° and 60° to the horizontal. | |||||||||||
| Increased slump | Increases | ||||||||||
| ---------------- | --- | --- | ---------- | --- | --- | --- | --- | --- | --- | --- | --- |
| Design of falsework systems should also take | |||||||||||
| Increased fluidity, e.g. Increases account of the final support conditions (e.g. the | |||||||||||
| flowing concrete | |||||||||||
| ground) | and | detail | the | size | of base | ||||||
| ------------------- | --- | --- | ---------- | --- | --- | ---------------- | ---- | ------- | ------- | ----- | ---------- |
| plates/spreader | beams | needed | to | take the | |||||||
| Increased concrete | Decreases | ||||||||||
| loads without sustaining excessive deflections. | |||||||||||
| temperatures | |||||||||||
| In multi-storey | construction, | the | propping | ||||||||
| ----------------------- | --- | --- | ---------- | --- | --- | ----------------- | ------- | -------------- | -------------- | ---- | ----------- |
| Faster setting cements | Decreases | ||||||||||
| should | extend | down | a sufficient | number of | |||||||
| (including use of | |||||||||||
| floors to ensure the loads are supported without | |||||||||||
| accelerators) | |||||||||||
| excessive | stress | on, | or | deflection | of, the | ||||||
| --- | --- | --- | --- | --- | --- | ---------- | ------- | ---- | --- | ----------- | --------- |
recently cast structure. This design should take 7. FALSEWORK account of the rate of concrete strength gain with age and the effect that local environmental conditions may have on it (e.g. concrete gains 7.1 DESIGN OF SUPPORT strength more slowly in cold weather). STRUCTURES The design of support structures should also
| All propping, | bracing | and | fixing | elements | |||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| consider the method to be used for stripping the | |||||||||||
| (collectively the ‘falsework’) that support the formwork. It is normal practice to strip soffit | |||||||||||
| formwork and transmit load to the supporting formwork in two stages – (1) the sheet/form- | |||||||||||
| foundation (usually the ground) – should be face elements which are to be re-used quickly, | |||||||||||
| considered as part of the total formwork and (2) the support structure which is to remain | |||||||||||
| system. | |||||||||||
| in place until the concrete can carry the loads. | |||||||||||
| NOTE: The term ‘shoring’ used below refers to the | |||||||||||
| -------------------------------------------------- | ---------------- | ----------- | --- | ------------ | --- | --- | --- | --- | --- | --- | --- |
| process | of temporarily | supporting | a building | or | |||||||
| 7.2 UNDISTURBED SHORES | |||||||||||
| structure | with ‘shores’ | or | props | to prevent | the | ||||||
| ---------- | ----------------- | ------- | ------ | ------------- | ---- | --- | --- | --- | --- | --- | --- |
| structure | from collapsing | during | construction | or | |||||||
| Proprietary systems are available that enable | |||||||||||
| renovation. | |||||||||||
| the support structure to remain in place while | |||||||||||
| Falsework | must also | be | able | to resist | any | ||||||
| ---------- | ----------- | --- | ----- | ----------- | ---- | --- | --- | --- | --- | --- | --- |
| the form-face materials are removed for re-use. | |||||||||||
| tendency to overturn, i.e. the formwork system | |||||||||||
| must be kept stable during erection and In these systems the props (or shores) extend | |||||||||||
| concrete placement. Assessments of falsework from the base to the soffit of the concrete slab | |||||||||||
| and the deck system is removed around them. | |||||||||||
| failures | during construction | show | that | the | |||||||
| --------- | --------------------- | --- | ----- | ----- | ---- | --- | --- | --- | --- | --- | --- |
| majority of failures occur during concrete This is a preferred system, as the props remain | |||||||||||
| untouched until removal at an appropriate later | |||||||||||
| placement. These failures can be a result of | |||||||||||
| date. Thus, the risk of deflection and stress | |||||||||||
| designers | not properly | estimating | the | loads | |||||||
| ---------- | -------------- | ----------- | --- | ---- | ------ | --- | --- | --- | --- | --- | --- |
| (both live and dead loads) that the falsework changes in the concrete slab during reshoring | |||||||||||
| is eliminated. It also ensures that the props for | |||||||||||
| structure must support – including additional | |||||||||||
| successive storeys remain in vertical alignment | |||||||||||
| loads and vibration effects that are experienced | |||||||||||
| and there | is | no | chance | of props | being | ||||||
| --- | --- | --- | --- | --- | --- | ----------- | --- | --- | ------- | ---------- | ------ |
| Version 1.0 | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| PAGE 12 > Guide to Concrete Construction — Part IX-Section 27 – Formwork |
overtightened, causing reverse stresses in the • Limitations on the stacking of materials concrete slab. on either partially completed formwork, completed formwork, or on freshly placed 7.3 RESHORING SYSTEMS concrete. These loads can be substantial and, unless controlled, can lead to Reshoring systems involve the removal of a overloading of partially completed section of the formwork and support structure, structures; following which the support structure is then • Limitations on the bracing of formwork replaced once the formwork is clear. With against concrete elements of the proper control and good supervision these permanent structure. Depending on the systems can give acceptable results. Props age of such elements they may not be must be replaced in the original pattern and not able to support such loading without overtightened to avoid causing undesirable damage; stresses in the concrete. • Protection of surface finishes on existing The three usual methods of reshoring are: work; • Safety – The maintenance of a safe • Secondary reshoring – in which shores working environment is the responsibility are placed before any formwork or props of all involved with the project. Attention are moved. They are placed under the may therefore need to be given to such soffit form as close as possible to the matters as (a) the provision of access original props. The original props and ladders, guardrails and working forms are then removed, taking care to platforms; (b) safe-load areas and mark the location of the original elements overhead protection for those working – as the final step is to replace the original below; and (c) suitable lighting and props and remove the secondary props; similar facilities. • Partial reshoring – in which the soffit is stripped, bay by bay, and props are replaced on the correct grid and 8.2 PREPARATION FOR CONCRETING retightened. Typical bays are 2-3 m in width; Cleanliness – Once the formwork is erected • Total reshoring – which involves complete and set in the correct position, all enclosed stripping of the soffit and subsequent areas and surfaces should be cleaned of all replacement of the props. This is the least foreign debris that may affect the finished desirable method as it can impose severe surface, including timber, reinforcing steel, tie stresses on the relatively immature wires, sawdust, sand, mortar etc. This may concrete and give rise to excessive necessitate a 'window' at the base of the form deflections. through which such material can be discarded. Where form faces will be inaccessible after 8. CONSTRUCTION OF erection (e.g. wall forms) release agents should be applied to them before they are erected. FORMWORK Immediately formwork has been stripped, it 8.1 ERECTION should be cleaned without damaging the form face. If necessary, any repairs should then be On many projects the formwork is supplied and made to restore the surface. Formwork should erected by a specialist subcontractor. While this be stored to avoid damage and should be has many advantages, it can also cause some stored/stacked to enable easy retrieval. problems if there is not good communication between the project designer, the main Release Agents – Most surfaces require the contractor and the formwork contractor. application of a release agent to allow the formwork to part easily from the concrete after it Specific matters to which attention should be has hardened – without damage to either given include: PAGE 13 > Guide to Concrete Construction — Part IX-Section 27 – Formwork Version 1.0
surface. However, there are a few specialist • The forms are clean; plastic form-liners that may not need a release • Repairs have been completed;
| agent. | • The correct release agent has been used | |||||||||
|---|---|---|---|---|---|---|---|---|---|---|
| and properly applied to vertical forms; | ||||||||||
| Release agents permit easy separation of the | ||||||||||
| and | ||||||||||
| formwork | from | the concrete | and | help to | ||||||
| --------- | --- | ----- | -------------- | --- | ---- | --------- | --- | --- | --- | --- |
| • Joints have been sealed. | ||||||||||
| preserve the formwork. In selecting a release | ||||||||||
| agent for a given project, care should be taken | ||||||||||
| Before concreting commences it is important to | ||||||||||
| to check that it will not: | ||||||||||
| check that: | ||||||||||
| • Cause unacceptable discolouration to the | ||||||||||
| • The line, level and plumb are correct; | ||||||||||
| concrete surface; and/or | ||||||||||
| • Dimensions are correct; | ||||||||||
| • Leave | any | material | on the concrete | |||||||
| --- | --------- | ---- | --------- | --- | ------------------ | --- | --- | --- | --- | --- |
| • All ties are at correct centres and tight; | ||||||||||
| surface | which will | prevent | bonding | of | ||||||
| --- | -------- | --- | ------------ | -------- | -------- | --- | --- | --- | --- | --- |
| • Props and supports are in the correct | ||||||||||
| subsequent coatings (e.g. Render, paint). | ||||||||||
| locations; | ||||||||||
| • All bracing systems are in place; | ||||||||||
| In the case of wall and column forms, release | ||||||||||
| agents should be applied to clean formwork • All wedges are nailed; | ||||||||||
| • All clamps are tight; | ||||||||||
| before it is erected. In the case of soffit forms, | ||||||||||
| • All bolts, jacks etc are tight; | ||||||||||
| release | agents | are | applied | before | the | |||||
| -------- | --- | ------- | ---- | -------- | ------- | ---- | --- | --- | --- | --- |
| reinforcing steel is placed (Figure 27.14). The • The supports are founded on a solid | ||||||||||
| release | agent(s) | can | be applied | by | spray, | base; | ||||
| -------- | --- | --------- | ---- | ------------ | --- | ------- | --- | ------ | --- | --- |
| brush, roller, squeegee etc., depending on its • All foreign material has been removed | ||||||||||
| characteristics, but on no account should it be | from forms; | |||||||||
| ------------------------------------------------ | --- | --- | --- | --- | --- | --- | --- | ------------ | --- | --- |
| allowed to coat reinforcing steel or any • Release agent has been correctly applied | ||||||||||
| construction joint. | to soffits; and | |||||||||
| -------------------- | --- | --- | --- | --- | --- | --- | --- | ---------------------------------------- | --- | --- |
| • Joints are sealed and cramped/wedged | ||||||||||
| tight. | ||||||||||
| During concreting checking is required for: | ||||||||||
| • Line, level, and plumb maintenance; | ||||||||||
| • Any settlement; | ||||||||||
| • Any leakage; and | ||||||||||
| • Any loosening of wedges, bolts, nails. |
8.3 EXTERNAL VIBRATION In some circumstances, external vibration may Figure 27.14 – Release Agent being applied to Soffit Form before Reinforcement is placed be applied to formwork – e.g. in some precast
operations, or when placing concrete in thin sections. In these situations, both the formwork Inspection – Formwork must be set accurately and the concrete are vibrated. Where external
| in | plan | and be | capable | of | maintaining | the | ||||
|---|---|---|---|---|---|---|---|---|---|---|
| vibration is used, it is important that (a) the | ||||||||||
| correct line, level, plumb, shape and tolerance | ||||||||||
| concrete is placed in controlled lifts so that | ||||||||||
| during | concreting | and | until | the hardened | ||||||
| ------- | --- | ----------- | ---- | ------ | -------------- | --- | --- | --- | --- | --- |
| when vibrated, the air can be expelled from the | ||||||||||
| concrete | can | take the | required | loads. | This | |||||
| --------- | --- | ---- | ---------- | --------- | ------- | ----- | --- | --- | --- | --- |
| concrete, and (b) the formwork be very rigid and | ||||||||||
| requires | a detailed | inspection | procedure | to | ||||||
| --------- | --- | ------------ | ----------- | --- | ---------- | --- | ----- | --------------------- | --------------- | --- |
| leak | free. The formwork | designer must | be | |||||||
| ensure that all elements of the formwork are | ||||||||||
| aware of the need to use external vibration | ||||||||||
| adequate, | clean, | in the | correct | place | and | |||||
| ---------- | --- | ------- | -------- | -------- | ------ | ---- | --- | --- | --- | --- |
| when doing the design. External vibration can | ||||||||||
| wedged/bolted tight. | ||||||||||
| be used to obtain high quality off-form finishes | ||||||||||
| Before the formwork is assembled it is and also when low slump concrete is being | ||||||||||
| necessary to check that: | placed. | |||||||||
| ------------------------- | --- | --- | --- | --- | --- | --- | -------- | --- | --- | --- |
Version 1.0 PAGE 14 > Guide to Concrete Construction — Part IX-Section 27 – Formwork
Vibrating tables constitute a form of ‘external desired to leave vertical formwork in place, vibration’. In these situations, the formwork is either to assist in curing the concrete, or attached to the vibrator (and not the vibrator to because it suits the construction sequence to the formwork as above). The use of vibrating do so, it is desirable to ease the forms from the tables is common in the manufacture of concrete surface as soon as possible to concrete products (e.g. concrete blocks) and in minimise colour variations.
| precast | operations | and | is used | to obtain | a | ||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| Multi-storey | Construction | – | While the | ||||||||
| consistent level of compaction. | |||||||||||
| Standards | provide | some | guidance | on the | |||||||
| --- | --- | --- | --- | --- | --- | ---------- | ---------- | ----- | --------- | --------- | -------- |
| minimum | stripping | times | required | for | |||||||
| multistorey construction, they also point out that | |||||||||||
| 8.4 STRIPPING FORMWORK | |||||||||||
| the construction | and | stripping | of | formwork | |||||||
| --- | --- | --- | --- | --- | --- | ------------------ | --- | ---- | ---------- | --- | --------- |
| systems which involve reshoring should be in | |||||||||||
| General – The project designer is normally | |||||||||||
| required to provide a schedule of stripping accordance with the project and formwork | |||||||||||
| times for formwork which is in accord with the documentation. Consequently, it is incumbent | |||||||||||
| on the | project | designer | to provide | this | |||||||
| --- | --- | --- | --- | --- | --- | -------- | -------- | --------- | --- | ------------ | ----- |
| requirements of AS 3600. Reference is also | |||||||||||
| made in AS 3600 to the requirements for information. Reshoring is a hazardous | |||||||||||
| stripping detailed in AS 3610, and it notes that operation which, unless carried out in a correct | |||||||||||
| and systematic | manner, | can | lead to | ||||||||
| --- | --- | --- | --- | --- | --- | ---------------- | --- | -------- | --- | ---- | --------- |
| where stripping requirements in AS 3600 are | |||||||||||
| more stringent than in AS 3610, then the unacceptable loads being placed on the | |||||||||||
| AS 3600 requirements will prevail. The concrete at an early age. | |||||||||||
| nominated times are minimum stripping times | |||||||||||
| This is particularly so for prestressed concrete | |||||||||||
| designed to ensure that the structure remains | |||||||||||
| as the stressing operations can cause quite | |||||||||||
| secure from collapse (under its own weight plus | |||||||||||
| substantial | loads | to | be transferred | to the | |||||||
| --- | --- | --- | --- | --- | --- | ------------ | ------ | --- | ---------------- | --- | -------- |
| that from any additional super-imposed loads) | |||||||||||
| shores, | re-shores, | back-props | and other | ||||||||
| --- | --- | --- | --- | --- | --- | -------- | ----------- | ----------- | --- | --- | ----------- |
| and from damage which might affect its later | |||||||||||
| temporary supports. | |||||||||||
| performance (e.g. cracking or deformation in | |||||||||||
| excess of that anticipated by the designer). The advice of the project designer should | |||||||||||
| Stripping must be carried out in a planned and therefore always be sought for both reinforced | |||||||||||
| controlled manner to ensure the proper and and prestressed concrete construction before | |||||||||||
| controlled | transfer | of | loads | from | the | ||||||
| ----------- | --------- | --- | ------ | ----- | ---- | --- | --- | --- | --- | --- | --- |
| specified procedures are changed in any way. If | |||||||||||
| formwork/falsework to the permanent or specific procedures are not provided in the | |||||||||||
| existing structure. project documentation, they should be sought. | |||||||||||
| AS 3610.1 also provides guidance on stripping | |||||||||||
| 9. FORMWORK DOCUMENTATION | |||||||||||
| times, which, while compatible with AS 3600, | |||||||||||
| refines the requirements to take account of the | |||||||||||
| AS 3610.1 contains a number of requirements | |||||||||||
| specified class of surface finish (Table 27.4). | |||||||||||
| in relation | to | documentation | including | (a) | |||||||
| --- | --- | --- | --- | --- | --- | ------------- | --- | -------------- | --- | ---------- | ---- |
| The stripping times for formwork removal noted documentation requirements will vary | |||||||||||
| depending on the complexity of the project, (b) | |||||||||||
| in AS 3600 and shown in Table 27.4 shall be | |||||||||||
| it is expected that all aspects of the formwork | |||||||||||
| increased where L | s /D > 280/(D +100) (where | ||||||||||
| ----------------- | --- | ---------------------------- | --- | --- | --- | --- | --- | --- | --- | --- | --- |
| L is the span between formwork supports and design, fabrication, stripping etc. will be | |||||||||||
| s | |||||||||||
| included in the documentation which is to be | |||||||||||
| D is the overall depth of the member); and the | |||||||||||
| prepared by ‘competent persons’ (as defined in | |||||||||||
| superimposed construction load is >2.0 kPa. | |||||||||||
| section 1.5.1.5 of AS 3610.1), and (c) where | |||||||||||
| Subject to these general provisions, stripping of elements of the design are done by different | |||||||||||
| formwork should be done at the earliest time – | |||||||||||
| persons, | or where | proprietary | information | is | |||||||
| --------- | ---------- | --------- | --- | --------------- | --- | --------- | ---------- | ------------ | --- | ------------ | --- |
| provided | that the | concrete | has developed | ||||||||
| included, all elements need to be collected and | |||||||||||
| sufficient strength to prevent damage to the collated into a single comprehensive document | |||||||||||
| surface of the element. For vertical surfaces, if | |||||||||||
| that fully describes formwork requirements. | |||||||||||
| formwork is stripped less than 18 hours after |
casting then special care needs to be taken to
| ensure the surface is not damaged. Where it is |
|---|
| Version 1.0 | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| PAGE 15 > Guide to Concrete Construction — Part IX-Section 27 – Formwork |
Table 27.4 – Minimum Formwork Stripping Times – In-situ Concrete (from AS 3600 and AS 3610.1) Surface finish Hot conditions Average conditions Cold conditions Formed surface
| classification | > 20°C | 20°C ≥ x > 12°C | 12°C ≥ x > 5°C | |
|---|---|---|---|---|
| Vertical faces | Classes 1, 2, 3* | 1 day | 2 days | 3 days |
| Classes 4, 5 | 9 hours | 12 hours | 18 hours | |
| A minimum of one day applies to the stripping of vertical faces where frost damage is likely. | ||||
| Beam and slab Formwork removal of beams and slab soffits must be in accordance with AS 3600 section | ||||
| soffits elements – 17.6.2.3 and 17.6.2.4 (and not less than 3 days) as well as conforming to AS 3610.1 | ||||
| reinforced slabs of | Appendix C3. | |||
| -------------------- | ------------- | --- | --- | --- |
| Normal Class | ||||
| concrete |
NOTE: *Where colour control on surface finishes has been specified it is advisable to strip forms early, subject to the limitations given.
Version 1.0 PAGE 16 > Guide to Concrete Construction — Part IX-Section 27 – Formwork
- SUMMARY – CONSTRUCTION CHECKLIST
• Loads • Watertightness − What are the stacked load limits at all stages? − Are all joints properly sealed and cramped? − Are the stacked materials on spreaders? − Are the construction joints sealed? − Will the loads be exceeded by any construction --- -------------------------------------------------- --- --- --- --- --- --- procedure? • Reinforcing Steel/Inserts
− Is the reinforcement correct? • Materials − Are all inserts/blockouts in the correct location?
| − Are the correct form materials being used? | |||||||
|---|---|---|---|---|---|---|---|
| − Is the form face | appropriate | for the finish | |||||
| • Concrete/Concreting | |||||||
| required? | |||||||
| − Is | the mix design | in accordance | with the | ||||
| --- | --- | --- | --- | ------ | ----------------- | --------------- | ---------- |
| specification? | |||||||
| • Position | − What | is the maximum | rate of placement | ||||
| ------------ | ------------------------------------------ | --- | --- | ----------- | ----------------- | --- | -------------------- |
| − Are the forms in the correct location? | permitted? | ||||||
| − Are they to dimension and within tolerance? − Are the forms maintaining line, level, plumb, | |||||||
| − Are they accurate to line, level and plumb? shape etc. during concreting? | |||||||
| ---------- | --- | --- | --- | ---------- | --- | --- | --- |
| • Fixing | • | Stripping | |||||
| − Is the nailing/screwing adequate? − What are the minimum stripping times? | |||||||
| − Are the ties the correct type? − Has the project designer permitted modification | |||||||
| − Are they on the correct grid? | of these? | ||||||
| --- | --------------------------------- | --- | --- | ---------- | --- | --- | --- |
| − Are all ties, clamps and bolts tight? − Do the procedures enable stripping without | |||||||
| damage to form or concrete? | |||||||
| − Are wedges tight and nailed? | |||||||
| --- | -------------------------------- | --- | --- | ------- | ---------------- | ----------- | ----------------- |
| − Are | the provisions | consistent | with the re-use | ||||
| times required? | |||||||
| • Bracing/Props | |||||||
| − Has the crane the necessary slings etc. to move | |||||||
| − Are the props plumb? | the forms quickly? | ||||||
| --- | ------------------------ | --- | --- | ------------------- | --- | --- | --- |
| − Are all loads centrally placed? − What curing methods are to be used once the | |||||||
| − Are supported elements wedged and nailed? formwork is removed? | |||||||
| − Are props straight? − Is the storage area for the formwork properly | |||||||
| − Are base plates on adequate foundations? | organised? | ||||||
| --------------- | -------------------------------------------- | --- | --- | ---------------------------------- | ---------------- | ------------ | ----------- |
| − Is the bracing correct? | |||||||
| − Is the bracing firmly connected? | |||||||
| • | Safety | ||||||
| − Are | there adequate | guardrails, | handrails, | ||||
| • Cleanliness | walkways, signs etc. in position? | ||||||
| − Are the form faces cleaned? | |||||||
| − Is any damage correctly repaired? | |||||||
| • Inspection | |||||||
| − Is the correct release agent in use? | |||||||
| --- | ---------------------------------------- | --- | --- | --- | --- | --- | --- |
| − Are there enough experienced inspectors on the | |||||||
| − Is it being correctly applied? | |||||||
| --- | ---------------------------------- | --- | --- | --- | --- | --- | --- |
| job to provide appropriate supervision? | |||||||
| − Has all debris been removed from within the | |||||||
| --- | ----------------------------------------------- | --- | --- | --- | --- | --- | --- |
form?
PAGE 17 > Guide to Concrete Construction — Part IX-Section 27 – Formwork Version 1.0
- RELEVANT AUSTRALIAN STANDARDS CCAA OFFICES
- AS 3600 – Concrete structures
- AS 3610.1 – Formwork for concrete, Part 1: NATIONAL OFFICE (NSW) Specifications Level 10 163 -175 O’Riordan Street Mascot NSW 2020 POSTAL ADDRESS PO Box 124 Mascot NSW 1460 Telephone: (02) 9667 8300 QUEENSLAND Level 14, 300 Ann Street, Brisbane QLD 4000 Telephone: (07) 3227 5200 VICTORIA Suite 910/1 Queens Road Melbourne VIC 3004 Telephone: (03) 9825 0200 WESTERN AUSTRALIA 45 Ventnor Avenue West Perth WA 6005 Telephone: (08) 9389 4452 SOUTH AUSTRALIA Level 30, Westpac House 91 King William Street Adelaide SA 5000 Telephone: (02) 9667 8300 TASMANIA PO Box 1441 Lindisfarne TAS 7015 Telephone: (03) 6491 2529 ONLINE DETAILS www.ccaa.com.au Email: info@ccaa.com.au Since the information provided is intended for general guidance only and in no way replaces the services of professional consultants on particular projects, no legal liability can be accepted by Cement Concrete & Aggregates Australia for its use. © Cement Concrete & Aggregates Australia PAGE 18 > Guide to Concrete Construction — Part IX-Section 27 – Formwork Version 1.0