luoojason's picture
Add files using upload-large-folder tool
3b138e6 verified
|
Raw
History Blame Contribute Delete
73.7 kB
Formwork has a dual function in concrete construction – it supports the plastic and hardening concrete
until it is sufficiently strong to support the actions/loads imposed upon it, and it imparts a finish to the
concrete surface. This Section describes the different types of formwork used in modern concrete
construction and outlines the requirements which must be met for formwork to perform satisfactorily.
The special requirements associated with the achievement of visually satisfying surface finishes are
discussed in Part V, Section 16 ‘Control of Surface Finishes’ in this Guide.
7.2 UNDISTURBED SHORES............ 12
CONTENTS
7.3 RESHORING SYSTEMS .............. 13
1. INTRODUCTION ................................... 2 8. CONSTRUCTION OF FORMWORK ... 13
2. BASIC COMPONENTS OF 8.1 ERECTION .................................. 13
FORMWORK ........................................ 3 8.2 PREPARATION FOR
3. REQUIREMENTS FOR FORMWORK ... 4 CONCRETING ............................. 13
3.1 GENERAL ...................................... 4 8.3 EXTERNAL VIBRATION .............. 14
3.2 STRENGTH .................................... 4 8.4 STRIPPING FORMWORK............ 15
3.3 STIFFNESS .................................... 5 9. FORMWORK DOCUMENTATION ...... 15
3.4 ACCURACY ................................... 5 10. SUMMARY – CONSTRUCTION
CHECKLIST ....................................... 17
3.5 WATER-TIGHTNESS ..................... 5
11. RELEVANT AUSTRALIAN
3.6 PERMEABILITY.............................. 5
STANDARDS ..................................... 18
3.7 ROBUSTNESS ............................... 5
3.8 EASE OF STRIPPING .................... 6
1. INTRODUCTION
3.9 STANDARDISATION ...................... 6
3.10 SAFETY ......................................... 6
Formwork is the temporary structure which (a)
4. MATERIALS FOR FORMWORK ........... 6 moulds concrete into the desired shape and (b)
holds it in the correct position until it is able to
4.1 GENERAL ...................................... 6
support the loads imposed upon it. It also
4.2 CHOICE OF MATERIALS ............... 6 imparts the required surface finish. Importantly,
4.3 FORM LINERS ............................... 7 formwork also provides safe working areas and
access ways for construction personnel.
5. FORMWORK SYSTEMS ....................... 8
Formwork and its supports (known as
5.1 MODULAR FORMWORK ............... 8 falsework) is a structural system and must be
designed and built accordingly. The actions
5.2 GANG FORMS ............................... 8
(loads) imposed on it may be temporary, but
5.3 TABLE FORMS............................... 8
they can be extremely large. Frequently they
5.4 JUMP/CLIMB FORMS .................... 9 are different in nature to those imposed on the
finished concrete structure.
5.5 SLIP-FORMS.................................. 9
5.6 PERMANENT FORMWORK ......... 10
Concrete is an extremely plastic and mouldable
material which will accurately reflect the shape,
6. DESIGN OF FORMWORK ................... 10
texture and finish of the surface against which it
6.1 GENERAL .................................... 10 is cast. Any imperfection or inaccuracy in this
surface will be indelibly inscribed onto the
6.2 LOADS ON FORMWORK ............. 10
concrete surface. Form-face materials must
7. FALSEWORK...................................... 12
therefore be chosen both to achieve the
7.1 DESIGN OF SUPPORT required surface finish and, in conjunction with
STRUCTURES ............................. 12 all the supporting elements, to maintain
PAGE 2 > Guide to Concrete Construction — Part IX-Section 27 – Formwork Version 1.0
accuracy and stability under all of the loads • Walers or bearers – which brace the
imposed during erection and placing – typically studs or support the joists and prevent
for at least several days into the life of the bulging or bowing in the other direction.
concrete structure.
| | | | | | | | An important | facet of formwork | design and |
| --- | --- | --- | --- | --- | --- | --- | -------------- | -------------------- | ------------ |
At early ages, the concrete will not be able to construction is the choice of spans (or centres)
support the loads imposed on it. Until the between studs, and also centres between
concrete is able to support the imposed loads
walers or bearers – both of which are important
the formwork (and falsework) will be the primary in preventing bulging and bowing.
loadbearing structure. Only when the concrete
| has | achieved | sufficient | | strength | can | the | | | |
| ---- | --------- | ----------- | --- | --------- | ---- | ---- | --- | --- | --- |
formwork be removed without detriment to the
safety or performance of the concrete structure.
Failure to meet accuracy, stability and strength
requirements will lead to formwork failures in
the form of bowing, warping or misalignment
which will be reflected in the final structure.
| Such | problems | could | | even | lead | to the | | | |
| ------------- | --------- | --------- | --- | ---------- | ----- | -------- | --- | --- | --- |
| catastrophic | | collapse | of | part (or | all) | of the | | | |
formwork.
| The | cost | of formwork | is | generally | | a very | | | |
| ---- | ----- | ------------- | --- | ---------- | --- | -------- | --- | --- | --- |
significant item in the overall cost of a project.
| The | formwork | system | should | be | the | most | | | |
| ---- | --------- | ------- | ------- | --- | ---- | ----- | --- | --- | --- |
Figure 27.1 – Wall Forms
| economical | | available | – | but cost | concerns | | | | |
| ----------- | ------ | ---------- | ---------- | ---------- | --------- | ---- | --- | --- | --- |
| should | never | be | permitted | to | overrule | the | | | |
criteria governing safety, strength and stability.
In reality, the initial cost of formwork may be a
very poor guide to its suitability for a project.
| Multiple | | uses of good | quality | formwork | | can | | | |
| --------- | --- | --------------- | -------- | --------- | --- | ---- | --- | --- | --- |
result in improved overall project economies.
| Formwork | | design and | selection | | of materials | | | | |
| --------- | --- | ------------ | ---------- | --- | -------------- | --- | --- | --- | --- |
should therefore always be approached on the
basis of ‘cost per use’.
2. BASIC COMPONENTS OF
| | FORMWORK | | | | | | Figure 27.2 – Beam Form and Supports | | |
| --- | --------- | --- | --- | --- | --- | --- | ------------------------------------- | --- | --- |
The basic components of formwork for typical
concrete elements are shown in Figures 27.1
to 27.4.
The basic structure of almost all formwork is the
same. It comprises:
• Form-face – which creates the surface
finish e.g. metal or plywood sheet, sawn
timber;
• Studs, or joists – lengths of sawn timber
| | or | (sometimes) | metal | sections | | which | | | |
| --- | --- | ------------ | ------ | --------- | --- | ------ | --- | --- | --- |
support the form-face and prevent it from
bulging or bowing in one direction; and
Figure 27.3 – Column Forms
PAGE 3 > Guide to Concrete Construction — Part IX-Section 27 – Formwork Version 1.0
However, even metal components may become
loose fitting or broken due to wear. All formwork
materials and components must be checked
regularly to ensure that they are sound and
safe.
Table 27.1 – Requirements for Formwork
| | | | | | | Property | Purpose |
| --- | --- | --- | --- | --- | --- | ---------- | -------------------- |
| | | | | | | Strength | Carry imposed loads |
| | | | | | | Stiffness | Maintain specified |
shape and avoid
Figure 27.4 – Typical Soffit Forms and Falsework distortion of concrete
elements
(diagrammatic only; bracing not shown)
| | | | | | | Accuracy | Ensure shape and size |
| --------------------- | --- | --- | --- | --- | --- | --------- | ---------------------- |
| 3. REQUIREMENTS FOR | | | | | | | of concrete elements; |
Ensure specified cover
FORMWORK
to reinforcement.
3.1 GENERAL
| | | | | | | Watertightness | Avoid grout loss and |
| --- | --- | --- | --- | --- | --- | --------------- | --------------------- |
subsequent
| Although | formwork | is | constructed | | only to | | |
| --------- | --------- | --- | ------------ | --- | --------- | --- | --- |
honeycombing of the
| contain | and support | concrete | | until | the cast | | |
| -------- | ------------- | --------- | --- | ------ | ---------- | --- | --- |
concrete
| structure | is strong | enough | | to support | the | | |
| ---------- | ----------- | ------- | --- | ------------ | ---- | --- | --- |
imposed loads itself, it must provide a safe Permeability When used, permeable
formwork allows water
environment for all those working on or around
it. In addition to being strong enough, it must and air to be removed
also be stable against overturning, uplift, and from the formed surface
sideways movements. It must also meet all
statutory requirements for access ladders, Robustness Enable re-use
| guardrails, | working | platforms, | | etc. | Where | | |
| ------------ | -------- | ----------- | --- | ----- | ------ | ------------------ | ---------------- |
| | | | | | | Ease of stripping | Avoid damage to |
Importance Level II and Importance Level III
criteria (see AS 3610.1 – Appendix A) are met, concrete surfaces
formwork documentation that (a) sets out the
| | | | | | | Standardisation | Promote economy |
| --- | --- | --- | --- | --- | --- | ---------------- | ---------------- |
requirements of the formwork design, (b) states
| that the | design | conforms | | with AS | 3610 | | |
| ---------- | ------- | --------- | --- | --------- | ----- | ------- | ---------------------- |
| | | | | | | Safety | Ensure a safe working |
requirements, and (c) allows the formwork to be
| verified | and | inspected, | is | a mandatory | | | environment |
| ------------ | ---- | ----------- | ------ | ------------- | --- | --- | ------------ |
| requirement | of | AS 3610. | Where | proprietary | | | |
3.2 STRENGTH
| formwork | systems | are | used, | | formwork | | |
| -------------- | -------- | ---- | -------- | ---------- | --------- | --- | --- |
| documentation | | can | contain | brochures | | | |
All components should be designed to cater for
| describing | the | formwork | – | provided | these | | |
| ----------- | ---- | --------- | --- | --------- | ------ | --- | --- |
the most severe loads that are likely to be
| contain | a suite | of information | | described | in | | |
| -------- | --------- | ---------------- | --- | ---------- | ---- | --- | --- |
AS 3610 (see also sub-section 9). imposed on the formwork. To achieve this, the
formwork design should be carried out by a
The general requirements for formwork are person experienced and competent in such
| summarised | | in Table | 27.1. | | Additional | design. | |
| ----------- | --- | ---------- | ------ | --- | ----------- | -------- | --- |
information is contained in AS 3610.
Care should then be taken to ensure that the
With new materials, these requirements may be design details are met and that the construction
readily met. With re-use, all materials (except loads imposed on the formwork are within the
perhaps metal components) may be weakened.
limits nominated by the designer.
PAGE 4 > Guide to Concrete Construction — Part IX-Section 27 – Formwork Version 1.0
Sound materials should always be used. Re- 3.4 ACCURACY
used material may be satisfactory but should be
checked regularly to ensure it is in good In general, formwork should always be built to
condition and adequate for the job in hand. The an accuracy greater than that desired in the
strength of each item of formwork material finished concrete structure or element. All
contributes to the overall safety of the support structures should be sufficient to
temporary structure. ensure that this accuracy is maintained until the
concrete has hardened.
Particular care is required with formwork design
and application where flowing concrete (also The accuracy required may affect the selection
known as Super Workable Concrete or Self of the material from which the formwork is to be
Compacting Concrete – see Section 22 ‘Super- built, as some materials may be able to be
Workable Concrete’ in this Guide) as these assembled to tighter tolerances than others.
materials can exert full hydrostatic pressure on
the formwork, resulting in significantly higher
3.5 WATER-TIGHTNESS
pressures on the formwork than are seen with
conventional ‘slumped’ concrete. This is
All joints should be sealed to stop grout (cement
particularly the case for formwork in vertical
and water) leaking from the formwork. Grout
structures such as columns and walls.
loss causes ragged edges, hydration staining
and honeycombing which can affect strength,
3.3 STIFFNESS durability and appearance in the final structure.
These issues can be exacerbated when using
Formwork should not bow, bulge, sag or flowing concretes of the types described in sub-
otherwise move to the extent that the section 3.2.
completed concrete element falls outside the
tolerances specified for the work.
3.6 PERMEABILITY
The formwork designer should detail the
formwork elements to have adequate stiffness, Systems using formwork with high permeability
but site personnel are responsible for ensuring have some advantages. There are several
that (a) the correct materials are used, (b) they systems available, but they may be as simple
are of adequate quality, and (c) they are used as a fabric material attached to plywood
in the proper manner. For example – plywood backing which contains drain holes. This type of
sheeting for general formwork use has a formwork allows ‘bleed’ water and air to escape
greater strength in one direction relative to the through the formed faces with the effects of (a)
other. It should always be used in the correct lowering W/C ratio in the areas adjacent (to a
orientation, as shown in Figure 27.5. depth of about 20 mm) to the formwork, (b)
increasing the strength and reducing sorptivity
and permeability in these outer areas, and (c)
improving the finish at these surfaces.
3.7 ROBUSTNESS
Formwork should be robust enough to
withstand repeated stripping, storing and
erection. Re-use of formwork is an important
element in improving the overall economy of the
structure. The extent of possible re-use varies
with formwork materials – with ranges from ‘up
to 5 times’ for plywood to 20-30 times for
Figure 27.5 – Orientation of Plywood
fibreglass and 50-100 times for steel. For form
liners (see 4.3), re-use can vary from 1-20 times
PAGE 5 > Guide to Concrete Construction — Part IX-Section 27 – Formwork Version 1.0
for timber (with varying surface treatments) to The stripping procedures (see 8.4) specified
up to 100 times for rubber. must not be modified and limits placed on
stacked materials anywhere on the formwork
must not be exceeded.
3.8 EASE OF STRIPPING
Formwork should be easy to remove – to avoid
4. MATERIALS FOR FORMWORK
or minimise damage to the concrete and/or to
the forms. Consideration should therefore be
4.1 GENERAL
given to providing adequate draw (taper) on
vertical faces and also to the movement which
Formwork can be constructed in a variety of
must be allowed in supports to facilitate easy
ways and from a number of materials. The size
removal of horizontal soffit forms and specialist
| | | | | | | | and nature | of | the | project | will most | likely |
| --- | --- | --- | --- | --- | --- | --- | ------------ | --- | ---- | -------- | ----------- | ------- |
systems such as table forms.
determine which materials and which systems
| | | | | | | | are likely to maximise technical and economic | | | | | |
| --- | --- | --- | --- | --- | --- | --- | ---------------------------------------------- | --- | --- | --- | --- | --- |
imperatives. For example, on some projects,
3.9 STANDARDISATION
| | | | | | | | particularly | small | ones, | | certain | formwork |
| --- | --- | --- | --- | --- | --- | --- | ------------- | ------ | ------ | --- | -------- | --------- |
As far as possible, formwork components elements are likely to be used only a relatively
small number of times. Considerable cutting
| should | be standardised | | | in size | to | avoid | | | | | | |
| ------- | ----------------- | --- | --- | --------- | --- | ------ | --- | --- | --- | --- | --- | --- |
unnecessary cutting. They should be able to be and fitting may be involved with consequent
| | | | | | | | wastage | of | materials. | The | use | of lower |
| --- | --- | --- | --- | --- | --- | --- | -------- | --- | ----------- | ---- | ---- | ---------- |
stripped, shifted and re-erected rapidly if speed
grade/cost materials may then be justified –
| of construction | | is | to be | maintained. | | This | | | | | | |
| ----------------- | --- | --- | ------- | ------------ | --- | ----- | --- | --- | --- | --- | --- | --- |
necessitates a system that comes apart easily, provided safety is not jeopardised.
| has a | minimum | of | elements | needing | | to be | | | | | | |
| ------- | -------- | --- | --------- | -------- | --- | ------- | --- | --- | --- | --- | --- | --- |
On larger projects, or with multiple projects, the
replaced (i.e. those damaged during removal)
use of specifically designed and constructed
| and is | easily | shifted | | with the | available | | | | | | | |
| ----------- | ------- | -------- | ----- | ---------- | ---------- | -------- | --------- | --------- | ---------------- | ---------- | --- | --------- |
| | | | | | | | formwork | elements | | can lead | to | improved |
| equipment. | On | small | jobs | this | will | involve | | | | | | |
| | | | | | | | economy. | | Standardisation | | | and |
‘manhandling’, but on large jobs crane capacity
| | | | | | | | interchangeability | | then | become | particularly | |
| --- | --- | --- | --- | --- | --- | --- | ------------------- | --- | ----- | ------- | ------------- | --- |
may be used to improve efficiencies.
important selection criteria.
| Standardisation | | for | speed | of | construction | | | | | | | |
| ---------------- | --- | ---- | ------ | --- | ------------- | --- | --- | --- | --- | --- | --- | --- |
frequently requires more expensive formwork
4.2 CHOICE OF MATERIALS
but, once re-use is taken into account, lower
overall project costs can be achieved.
| | | | | | | | Many materials | | may | be used | for formwork. | |
| ------------ | -------- | --------- | ------ | -------- | ------------- | -------- | -------------------------------------------- | ------------ | ---------- | -------------- | ---------------- | --------- |
| | | | | | | | Table 27.2 provides a brief overview of the | | | | | |
| 3.10 | SAFETY | | | | | | characteristics of those in common use. | | | | | |
| | | | | | | | Before | the final | selection | | of the | formwork |
| Formwork | must | provide | | a safe | | working | | | | | | |
| | | | | | | | material | is made | for | a particular | project, | a |
| environment | | for all | those | working | | on and | | | | | | |
| | | | | | | | number | of factors | | should | be considered, | |
| around | it. In | addition | to | being | of adequate | | | | | | | |
including:
| strength, | it | must | also | be stable | | against | | | | | | |
| ------------- | --- | -------- | ----- | ----------- | --- | -------- | --- | --- | --- | --- | --- | --- |
| overturning, | | uplift, | and | sideways | or | sliding | | | | | | |
• The size of the forms;
| movements. | | Properly | | guarded | walkways | | | | | | | |
| ----------- | --- | --------- | --- | -------- | --------- | --- | --- | --- | --- | --- | --- | --- |
• The shape of the forms;
| should | be | provided | around | | all areas | of | | | | | | |
| ------- | --- | --------- | ------- | --- | ----------- | --- | --- | --- | --- | --- | --- | --- |
• The surface finish quality required;
suspended work to provide safe access to them
• The accuracy required;
during construction, as should a safe means of
• The number of re-uses required;
| withdrawal | as | concreting | | progresses. | | All | | | | | | |
| ----------- | --- | ----------- | --- | ------------ | --- | ---- | --- | --- | --- | --- | --- | --- |
• The handling methods proposed;
statutory requirements must be met.
• The methods of compaction proposed;
The tightness of all components must be • The methods of curing proposed; and
thoroughly checked prior to pouring concrete.
• Safety.
PAGE 6 > Guide to Concrete Construction — Part IX-Section 27 – Formwork Version 1.0
The weighting given to each factor will vary from textures and patterns on the concrete surface –
project to project. On small projects, where typically a scene or portrait.
multiple uses of formwork elements are unlikely
and a great deal of cutting and fitting may be
required, timber sections may well be
appropriate. On major projects, where
standardised components can be employed
and multiple re-use achieved, heavier steel
sections may well be warranted. Modular units
may also be viable in such circumstances. In
the final analysis, the choice of formwork
materials is a matter of cost, suitability and
availability. Most of the commonly accepted
materials can be made to work in most
situations. The quality of the finish required, and
the overall cost of the formwork, are likely to be
the principal determinants in choosing
materials.
(a)
4.3 FORM LINERS
Form liners are effectively a mould placed on
the inside of formwork and are used to create
simple or complex designs or textures on the
surface of concrete (Figure 27.6). The use of
form liners has expanded the architectural
applications of concrete hugely, and it is really
open to the designer to create as complex a
pattern as can reasonably be imposed on a
concrete surface. When combined with
coloured concrete the architectural scope
expands even further. A wide variety of
materials can be used as form liners, with
important considerations being (a) the
complexity of the design required, and (b) the
extent of re-use of the form liner that is required. (b)
For low levels of re-use materials like
Figure 27.6 – Variety of Textures and Patterns achieved
cardboard, rigid plastics, polystyrene or by Using Form Liners
tempered hardboard have been used. These
will generally only provide one or two castings. Detailed information on the use of form liners
For high levels of re-use, rubbers and synthetic and their range of applicability is given in the
polymers are common. Patterns can also be CCAA Briefing 06 ‘Form Liners – Achieving
created when form liners are coated (partially) Surface Relief and Texture’ (June 2002).
with a retarding agent to create different
PAGE 7 > Guide to Concrete Construction — Part IX-Section 27 – Formwork Version 1.0
Table 27.2 – Formwork Materials
Material Uses
Timber Commonly used for studs, bearers, joists, walers etc. as it is readily available and
easily worked with conventional tools. Has good load-carrying capacity and some
suitable species are relatively light-weight, e.g. Oregon. Australian hardwoods tend to
be heavier and more susceptible to warping. Some species of pine also tend to
splinter or split when nailed.
Steel Steel sections are used in formwork framing, particularly in patented systems. Strong
and robust, steel-framed formwork is capable of multiple re-uses but requires a
degree of standardisation to warrant its additional cost. It is commonly used in
precasting yards, particularly for repetitive work.
Coated plywood Commonly used for soffits or as form liners in beams, columns and similar elements.
Readily worked, coated plywood (properly handled) is capable of multiple re-uses.
Cardboard Has been used in column and waffle forms.
Normally suitable for one-off use only.
Glass reinforced concrete Commonly used as permanent formwork, where it provides a decorative finish, or in
(GRC) or plastic moulds to achieve intricate shapes – particularly for precast elements. Generally, it is
relatively durable and capable of multiple re-uses.
Concrete Precast concrete elements are used as permanent formwork – where the precast
element is exposed to view in the completed structure. Also used to provide
permanent forms in precast concrete factories where it is very economical for
standard elements or components.
Rubber, thermoplastic and Used as form liners to provide intricate effects and for decorative finishes. Rubber and
polystyrene materials thermoplastic sheeting are used for decorative finishes and are suitable for multiple
uses.
5. FORMWORK SYSTEMS Adequate cranage is essential for handling
gang forms but the cost of the cranage is offset
5.1 MODULAR FORMWORK by the increased speed of construction offered
by moving large units of formwork from one
A number of formwork systems comprising location to another.
modular units are available on a sale or hire
5.3 TABLE FORMS
basis. The systems generally incorporate
modular panels so that they can be re-used on
Table forms are a type of gang form used to
a wide variety of jobs. Panels may use a steel
form soffits. Large sections of soffit form,
frame with plywood facing which can be
complete with propping and bracing elements,
replaced when necessary. Generally, such
can be fabricated into a single unit which, after
systems incorporate simple but effective means
use, can be lowered from the soffit, transported
of support and fixing.
to the edge of the floor, lifted to the next level
5.2 GANG FORMS by the crane and realigned ready for the next
concrete placement (Figure 27.7).
Gang forms are individual components, often
modular, made up into large panels that are
then tied and braced so that they can be moved
as a complete unit.
PAGE 8 > Guide to Concrete Construction — Part IX-Section 27 – Formwork Version 1.0
| | | | | | | free from | the slipform. | Slip-forming | | can be |
| --- | --- | --- | --- | --- | --- | ----------- | --------------- | ------------- | ------ | ------------ |
| | | | | | | undertaken | either | vertically | (e.g. | for silos, |
towers and lift shafts) or horizontally (e.g. for
roads and safety barriers).
Figure 27.7 – Typical Use of Table Forms
A 'transporter' is often used to wheel the table
forms to the edge of the building, where a
special rig enables the crane to handle them
efficiently.
Table form systems are of particular use in
Figure 27.8 – Typical Self-climbing Formwork System
multi-storey building construction where speed
is important, adequate cranage is available and
the initial cost of formwork can be offset by
On vertical elements, the slipform has shutters
multiple re-uses.
on both faces that are lifted vertically, at a
| | | | | | | predetermined | rate | by a | series | of hydraulic |
| --- | --- | --- | --- | --- | --- | -------------- | ----- | ------ | ------- | -------------- |
5.4 JUMP/CLIMB FORMS jacks (Figure 27.9). Typical rates of slip-
forming vary from 300-400 mm per hour. Some
Jump or climb forms are gang forms for casting
projects are slip-formed continuously, whilst on
vertical elements such as walls and shafts. others the free-standing height is limited to a
| They are | equipped | with | simple | and | rapid | | | | | |
| ---------- | --------- | ----- | ------- | ---- | ------ | --- | --- | --- | --- | --- |
few storeys.
| mechanical | means | of | handling, | require | a | | | | | |
| ----------- | ------ | --- | ---------- | -------- | --- | --- | --- | --- | --- | --- |
Slip-forming is not recommended where a high
| minimum | of labour | and | do | not rely | on the | | | | | |
| -------- | ----------- | ---- | --- | ---------- | -------- | --- | --- | --- | --- | --- |
availability of cranage (Figure 27.8). degree of colour control on the finished surface
is necessary as colour banding is very difficult
| The system strips the form, shifts it to the new | | | | | | to avoid. | | | | |
| ------------------------------------------------- | ---------- | ---------- | --- | ---------- | --------- | ---------- | --- | --- | --- | --- |
| position | and then | re-aligns | | it using | its own | | | | | |
On horizontal construction, it can be used in its
inbuilt jacking system. Daily casting cycles are
| common. | | | | | | most simple | form | to construct | | kerbs and |
| -------- | --- | --- | --- | --- | --- | ------------- | ----- | -------------- | --- | ----------- |
channels and, in the more sophisticated form,
Jump or climb form systems are capable of to construct roads or channel linings. Horizontal
producing a high-quality finish with good colour
paving rates of up to 2 km per day have been
control.
achieved on large projects but an average rate
of 300-500 m per day is more common. No
edge forming is generally used for this work and
5.5 SLIP-FORMS
the concrete must be made to a consistency
sufficient to avoid slumping once it is free of the
| Slipform | systems | incorporate | | continuously | | | | | | |
| --------- | -------- | ------------ | --- | ------------- | --- | --------- | ------------- | --- | ---------- | --------- |
| | | | | | | machine. | Slip-forming | is | discussed | in more |
moving formwork to speed construction and to
detail in Section 19 ‘Slip-formed Concrete’ of
eliminate the need for large areas of formwork.
this Guide.
| The concrete | being | | 'extruded' | must | have | | | | | |
| ------------------------------------------------ | ------ | --- | ----------- | ----- | ----- | --- | --- | --- | --- | --- |
| adequate stiffness to hold its shape once it is | | | | | | | | | | |
| | | | | | | | | | | Version 1.0 |
| --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | ------------- |
PAGE 9 > Guide to Concrete Construction — Part IX-Section 27 – Formwork
Precast concrete and glass reinforced concrete
| (GRC) | are commonly | | used for permanent | |
| ------ | -------------- | --- | --------------------- | --- |
formwork – the former being used where the
form takes part of the structural loads and the
| latter | where decorative | | finishes | only are |
| ---------- | ------------------ | -------- | ---------- | ---------- |
| required. | The | use of | permanent | forms |
minimises subsequent finishing operations and
| often reduces | the scaffolding | | and | falsework |
| --------------- | ---------------- | --- | ---- | ---------- |
required for these operations.
6. DESIGN OF FORMWORK
6.1 GENERAL
The design of formwork, particularly on large
projects, calls for a considerable degree of skill
and experience. Not only can the loads on it be
| both | large and | complex, | but | stripping |
| ----- | ----------- | --------- | ---- | ---------- |
procedures, and the way they cause loads to be
transferred to the concrete structure, are of
considerable complexity and importance.
| Whilst | the actual | design | should always | be |
| ------- | ------------ | ------- | --------------- | --- |
Figure 27.9 – Slip-forming a Vertical Element
undertaken by a specialist formwork designer,
all involved with either the erection or removal
5.6 PERMANENT FORMWORK of formwork on the construction site should be
| aware | of the | factors | which affect | its |
| ------ | -------- | -------- | -------------- | ---- |
Permanent formwork is a type of formwork performance, and in particular its strength and
which is left in place to become part of the stability – and hence its safety. AS 3610.1 sets
| out requirements | | for | the design | and |
| ------------------ | --- | ---- | ------------ | ---- |
finished structure (Figure 27.10). It may assist
in taking some of the structural load or simply construction of formwork which are aimed at
provide a permanent decorative finish. ensuring its effectiveness and safety.
6.2 LOADS ON FORMWORK
Formwork should be designed to support both
| the vertical | and | horizontal | loads which | are |
| -------------- | ---- | ----------- | ------------- | ---- |
imposed on it whilst it is being erected and while
it is in position. In supporting these loads, the
| formwork | should | not | deflect excessively, | |
| --------- | ------- | ---- | ---------------------- | --- |
buckle, bulge or otherwise move out of position.
The most severe loading generally occurs when
the concrete is being placed. However, this is
| not always | the | case, so | it is common | to |
| ------------ | ---- | ---------- | --------------- | --- |
consider the loads on formwork at three stages
of construction:
During Erection – Loads on formwork during
erection can arise from two principal sources,
Figure 27.10 – Precast Permanent Formwork used
for an Edge beam of a Multi-storey Building (a) the weight of material, equipment etc. which
may be stacked on it prior to concreting; and (b)
| | | | | Version 1.0 |
| --- | --- | --- | --- | ------------- |
PAGE 10 > Guide to Concrete Construction — Part IX-Section 27 – Formwork
the effect of wind which may exert both vertical on the formwork, and particularly on the props
and horizontal forces on the formwork and its supporting lower floors (see 7.3).
supports. Care should therefore be taken to
Of prime importance, however, is the lateral
| avoid excessive | load | concentrations | and | to | | | | | |
| ----------------- | ----- | --------------- | ---- | --- | --- | --- | --- | --- | --- |
pressure exerted on side forms during and after
| ensure that | bracing | is installed | as early | as | | | | | |
| ------------- | -------- | -------------- | ---------- | --- | --------- | ------------ | ---------- | ---------- | ---- |
| | | | | | concrete | compaction. | Vibration | liquefies | the |
possible, and certainly before the formwork is
concrete and increases the pressure exerted on
used as a working platform (Figure 27.11).
| | | | | | the forms | (Figure | 27.13). | Due | allowance |
| --- | --- | --- | --- | --- | ----------- | -------- | -------- | ---- | ---------- |
should be made for this, particularly with deep
pours, such as columns.
Figure 27.11 – Loads on Formwork prior to
Construction
During Concreting – During concreting, the
concrete itself imposes a considerable dead
weight on the forms. In addition, the weight of
men and equipment on the platform should be
Figure 27.13 - Lateral Pressures on Formwork
taken into account. At this stage, lateral stability
during Compaction
should also be considered. The formwork with
its load of plastic concrete is inevitably top-
heavy and therefore particularly susceptible to
The lateral pressure exerted by fluid concrete
sideways movement. The possibility of impact during compaction is by far the most severe
| arising from | a wayward | concrete | bucket | or | | | | | |
| ---------------- | ----------- | --------- | ----------- | --- | --------- | ------------ | ----- | ---------------- | ------- |
| | | | | | loading | experienced | by | vertical | forms. |
| similar mishap | should | also be | considered | | | | | | |
| | | | | | Problems | such as | form | liners bulging | and |
(Figure 27.12). deflecting between supports frequently arise
because the magnitude of the lateral pressure
is underestimated. This is particularly the case
| | | | | | with deep | narrow | forms, | where it | is often |
| --- | --- | --- | --- | --- | ----------- | ------- | ------- | ---------- | ---------- |
assumed the loads will be less than in (say)
heavy columns. In fact, the width of formwork
has little influence on lateral pressure, with the
principal consideration being the height of the
| | | | | | fluid concrete. | Factors | | influencing | lateral |
| --- | --- | --- | --- | --- | ----------------- | -------- | --- | ------------ | -------- |
pressure are set out in Table 27.3.
In general terms, any factor which increases the
fluidity of the concrete, or the height of fluid
Figure 27.12 – Loads on Formwork during concrete, increases the lateral pressure on the
| Construction | | | | | formwork (see also comments about flowing | | | | |
| ------------- | --- | --- | --- | --- | ---------------------------------------------- | -------- | ------- | -------- | -------- |
| | | | | | concrete in sub-section 3.2). Conversely, any | | | | |
| | | | | | factor which | reduces | these, | reduces | lateral |
After Concreting – On multi-storey projects, it
pressure (Figure 27.13 and Table 27.3).
is usual for work to proceed on upper floors
| while the concrete structure below is still gaining | | | | | | | | | |
| ---------------------------------------------------- | -------------- | ------- | ---------- | --- | --- | --- | --- | --- | --- |
| strength. | Consideration | should | therefore | be | | | | | |
| given to these additional loads being imposed | | | | | | | | | |
| | | | | | | | | | Version 1.0 |
| --- | --- | --- | --- | --- | --- | --- | --- | --- | ------------- |
PAGE 11 > Guide to Concrete Construction — Part IX-Section 27 – Formwork
Table 27.3 – Formwork Materials during the placing activities. Problems during
reshoring operations and premature falsework
Effect on
or formwork removal have also been significant
| Factor | | | lateral | | | | | | | | |
| -------------------- | --- | --- | ---------- | --- | --- | ------------------------------- | -------- | --- | ------- | --- | ----------- |
| | | | pressure | | | causes of structural failures. | | | | | |
| Increasing concrete | | | Increases | | | | | | | | |
| | | | | | | All support | systems | | should | be | adequately |
density
| | | | | | | braced | to | ensure | stability | and | prevent |
| --- | --- | --- | --- | --- | --- | ------- | --- | ------- | ---------- | ---- | -------- |
Increased rates of Increases progressive collapse. Bracing should be
| placing | | | | | | provided in two directions at right angles to | | | | | |
| -------- | --- | --- | --- | --- | --- | ---------------------------------------------- | --- | --- | --- | --- | --- |
each other and be provided near the edges of
| Increased heights of pour | | | Increases | | | | | | | | |
| -------------------------- | --- | --- | ---------- | --- | --- | --- | --- | --- | --- | --- | --- |
the system where concrete placement is likely
Internal vibration Increases to commence. All bracing should be between
30° and 60° to the horizontal.
| Increased slump | | | Increases | | | | | | | | |
| ---------------- | --- | --- | ---------- | --- | --- | --- | --- | --- | --- | --- | --- |
Design of falsework systems should also take
Increased fluidity, e.g. Increases account of the final support conditions (e.g. the
flowing concrete
| | | | | | | ground) | and | detail | the | size | of base |
| ------------------- | --- | --- | ---------- | --- | --- | ---------------- | ---- | ------- | ------- | ----- | ---------- |
| | | | | | | plates/spreader | | beams | needed | to | take the |
| Increased concrete | | | Decreases | | | | | | | | |
loads without sustaining excessive deflections.
temperatures
| | | | | | | In multi-storey | | construction, | | the | propping |
| ----------------------- | --- | --- | ---------- | --- | --- | ----------------- | ------- | -------------- | -------------- | ---- | ----------- |
| Faster setting cements | | | Decreases | | | | | | | | |
| | | | | | | should | extend | down | a sufficient | | number of |
(including use of
floors to ensure the loads are supported without
accelerators)
| | | | | | | excessive | stress | on, | or | deflection | of, the |
| --- | --- | --- | --- | --- | --- | ---------- | ------- | ---- | --- | ----------- | --------- |
recently cast structure. This design should take
7. FALSEWORK account of the rate of concrete strength gain
with age and the effect that local environmental
conditions may have on it (e.g. concrete gains
7.1 DESIGN OF SUPPORT
strength more slowly in cold weather).
STRUCTURES
The design of support structures should also
| All propping, | bracing | and | fixing | elements | | | | | | | |
| --------------- | -------- | ---- | ------- | --------- | --- | --- | --- | --- | --- | --- | --- |
consider the method to be used for stripping the
(collectively the ‘falsework’) that support the formwork. It is normal practice to strip soffit
formwork and transmit load to the supporting formwork in two stages – (1) the sheet/form-
foundation (usually the ground) – should be face elements which are to be re-used quickly,
considered as part of the total formwork and (2) the support structure which is to remain
system.
in place until the concrete can carry the loads.
| NOTE: The term ‘shoring’ used below refers to the | | | | | | | | | | | |
| -------------------------------------------------- | ---------------- | ----------- | --- | ------------ | --- | --- | --- | --- | --- | --- | --- |
| process | of temporarily | supporting | | a building | or | | | | | | |
7.2 UNDISTURBED SHORES
| structure | with ‘shores’ | or | props | to prevent | the | | | | | | |
| ---------- | ----------------- | ------- | ------ | ------------- | ---- | --- | --- | --- | --- | --- | --- |
| structure | from collapsing | during | | construction | or | | | | | | |
Proprietary systems are available that enable
renovation.
the support structure to remain in place while
| Falsework | must also | be | able | to resist | any | | | | | | |
| ---------- | ----------- | --- | ----- | ----------- | ---- | --- | --- | --- | --- | --- | --- |
the form-face materials are removed for re-use.
tendency to overturn, i.e. the formwork system
must be kept stable during erection and In these systems the props (or shores) extend
concrete placement. Assessments of falsework from the base to the soffit of the concrete slab
and the deck system is removed around them.
| failures | during construction | | show | that | the | | | | | | |
| --------- | --------------------- | --- | ----- | ----- | ---- | --- | --- | --- | --- | --- | --- |
majority of failures occur during concrete This is a preferred system, as the props remain
untouched until removal at an appropriate later
placement. These failures can be a result of
date. Thus, the risk of deflection and stress
| designers | not properly | estimating | | the | loads | | | | | | |
| ---------- | -------------- | ----------- | --- | ---- | ------ | --- | --- | --- | --- | --- | --- |
(both live and dead loads) that the falsework changes in the concrete slab during reshoring
is eliminated. It also ensures that the props for
structure must support – including additional
successive storeys remain in vertical alignment
loads and vibration effects that are experienced
| | | | | | | and there | is | no | chance | of props | being |
| --- | --- | --- | --- | --- | --- | ----------- | --- | --- | ------- | ---------- | ------ |
| | | | | | | | | | | | Version 1.0 |
| --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | ------------- |
PAGE 12 > Guide to Concrete Construction — Part IX-Section 27 – Formwork
overtightened, causing reverse stresses in the • Limitations on the stacking of materials
concrete slab. on either partially completed formwork,
completed formwork, or on freshly placed
7.3 RESHORING SYSTEMS
concrete. These loads can be substantial
and, unless controlled, can lead to
Reshoring systems involve the removal of a
overloading of partially completed
section of the formwork and support structure,
structures;
following which the support structure is then
• Limitations on the bracing of formwork
replaced once the formwork is clear. With
against concrete elements of the
proper control and good supervision these
permanent structure. Depending on the
systems can give acceptable results. Props
age of such elements they may not be
must be replaced in the original pattern and not
able to support such loading without
overtightened to avoid causing undesirable
damage;
stresses in the concrete.
• Protection of surface finishes on existing
The three usual methods of reshoring are: work;
• Safety – The maintenance of a safe
• Secondary reshoring – in which shores
working environment is the responsibility
are placed before any formwork or props
of all involved with the project. Attention
are moved. They are placed under the
may therefore need to be given to such
soffit form as close as possible to the
matters as (a) the provision of access
original props. The original props and
ladders, guardrails and working
forms are then removed, taking care to
platforms; (b) safe-load areas and
mark the location of the original elements
overhead protection for those working
– as the final step is to replace the original
below; and (c) suitable lighting and
props and remove the secondary props;
similar facilities.
• Partial reshoring – in which the soffit is
stripped, bay by bay, and props are
replaced on the correct grid and 8.2 PREPARATION FOR CONCRETING
retightened. Typical bays are 2-3 m in
width; Cleanliness – Once the formwork is erected
• Total reshoring – which involves complete and set in the correct position, all enclosed
stripping of the soffit and subsequent areas and surfaces should be cleaned of all
replacement of the props. This is the least foreign debris that may affect the finished
desirable method as it can impose severe surface, including timber, reinforcing steel, tie
stresses on the relatively immature wires, sawdust, sand, mortar etc. This may
concrete and give rise to excessive necessitate a 'window' at the base of the form
deflections. through which such material can be discarded.
Where form faces will be inaccessible after
8. CONSTRUCTION OF erection (e.g. wall forms) release agents should
be applied to them before they are erected.
FORMWORK
Immediately formwork has been stripped, it
8.1 ERECTION
should be cleaned without damaging the form
face. If necessary, any repairs should then be
On many projects the formwork is supplied and
made to restore the surface. Formwork should
erected by a specialist subcontractor. While this
be stored to avoid damage and should be
has many advantages, it can also cause some
stored/stacked to enable easy retrieval.
problems if there is not good communication
between the project designer, the main Release Agents – Most surfaces require the
contractor and the formwork contractor. application of a release agent to allow the
formwork to part easily from the concrete after it
Specific matters to which attention should be
has hardened – without damage to either
given include:
PAGE 13 > Guide to Concrete Construction — Part IX-Section 27 – Formwork Version 1.0
surface. However, there are a few specialist • The forms are clean;
plastic form-liners that may not need a release
• Repairs have been completed;
| agent. | | | | | | | | • The correct release agent has been used | | |
| ------- | --- | --- | --- | --- | --- | --- | --- | ------------------------------------------- | --- | --- |
and properly applied to vertical forms;
Release agents permit easy separation of the
and
| formwork | | from | the concrete | | and | help to | | | | |
| --------- | --- | ----- | -------------- | --- | ---- | --------- | --- | --- | --- | --- |
• Joints have been sealed.
preserve the formwork. In selecting a release
agent for a given project, care should be taken
Before concreting commences it is important to
to check that it will not:
check that:
• Cause unacceptable discolouration to the
• The line, level and plumb are correct;
concrete surface; and/or
• Dimensions are correct;
| | • Leave | any | material | | on the concrete | | | | | |
| --- | --------- | ---- | --------- | --- | ------------------ | --- | --- | --- | --- | --- |
• All ties are at correct centres and tight;
| | surface | | which will | prevent | bonding | of | | | | |
| --- | -------- | --- | ------------ | -------- | -------- | --- | --- | --- | --- | --- |
• Props and supports are in the correct
subsequent coatings (e.g. Render, paint).
locations;
• All bracing systems are in place;
In the case of wall and column forms, release
agents should be applied to clean formwork • All wedges are nailed;
• All clamps are tight;
before it is erected. In the case of soffit forms,
• All bolts, jacks etc are tight;
| release | | agents | are | applied | before | the | | | | |
| -------- | --- | ------- | ---- | -------- | ------- | ---- | --- | --- | --- | --- |
reinforcing steel is placed (Figure 27.14). The • The supports are founded on a solid
| release | | agent(s) | can | be applied | by | spray, | | base; | | |
| -------- | --- | --------- | ---- | ------------ | --- | ------- | --- | ------ | --- | --- |
brush, roller, squeegee etc., depending on its • All foreign material has been removed
| characteristics, but on no account should it be | | | | | | | | from forms; | | |
| ------------------------------------------------ | --- | --- | --- | --- | --- | --- | --- | ------------ | --- | --- |
allowed to coat reinforcing steel or any • Release agent has been correctly applied
| construction joint. | | | | | | | | to soffits; and | | |
| -------------------- | --- | --- | --- | --- | --- | --- | --- | ---------------------------------------- | --- | --- |
| | | | | | | | | • Joints are sealed and cramped/wedged | | |
tight.
During concreting checking is required for:
• Line, level, and plumb maintenance;
• Any settlement;
• Any leakage; and
• Any loosening of wedges, bolts, nails.
8.3 EXTERNAL VIBRATION
In some circumstances, external vibration may
Figure 27.14 – Release Agent being applied to Soffit
Form before Reinforcement is placed
be applied to formwork – e.g. in some precast
operations, or when placing concrete in thin
sections. In these situations, both the formwork
Inspection – Formwork must be set accurately
and the concrete are vibrated. Where external
| in | plan | and be | capable | of | maintaining | the | | | | |
| --- | ----- | -------- | -------- | --- | ------------ | ---- | --- | --- | --- | --- |
vibration is used, it is important that (a) the
correct line, level, plumb, shape and tolerance
concrete is placed in controlled lifts so that
| during | | concreting | and | until | the hardened | | | | | |
| ------- | --- | ----------- | ---- | ------ | -------------- | --- | --- | --- | --- | --- |
when vibrated, the air can be expelled from the
| concrete | | can | take the | required | loads. | This | | | | |
| --------- | --- | ---- | ---------- | --------- | ------- | ----- | --- | --- | --- | --- |
concrete, and (b) the formwork be very rigid and
| requires | | a detailed | inspection | | procedure | to | | | | |
| --------- | --- | ------------ | ----------- | --- | ---------- | --- | ----- | --------------------- | --------------- | --- |
| | | | | | | | leak | free. The formwork | designer must | be |
ensure that all elements of the formwork are
aware of the need to use external vibration
| adequate, | | clean, | in the | correct | place | and | | | | |
| ---------- | --- | ------- | -------- | -------- | ------ | ---- | --- | --- | --- | --- |
when doing the design. External vibration can
wedged/bolted tight.
be used to obtain high quality off-form finishes
Before the formwork is assembled it is and also when low slump concrete is being
| necessary to check that: | | | | | | | placed. | | | |
| ------------------------- | --- | --- | --- | --- | --- | --- | -------- | --- | --- | --- |
Version 1.0
PAGE 14 > Guide to Concrete Construction — Part IX-Section 27 – Formwork
Vibrating tables constitute a form of ‘external desired to leave vertical formwork in place,
vibration’. In these situations, the formwork is either to assist in curing the concrete, or
attached to the vibrator (and not the vibrator to because it suits the construction sequence to
the formwork as above). The use of vibrating do so, it is desirable to ease the forms from the
tables is common in the manufacture of concrete surface as soon as possible to
concrete products (e.g. concrete blocks) and in minimise colour variations.
| precast | operations | and | is used | to obtain | a | | | | | | |
| -------- | ----------- | ---- | --------- | ----------- | --- | ------------- | --- | ------------- | --- | --- | ----------- |
| | | | | | | Multi-storey | | Construction | | – | While the |
consistent level of compaction.
| | | | | | | Standards | provide | some | guidance | | on the |
| --- | --- | --- | --- | --- | --- | ---------- | ---------- | ----- | --------- | --------- | -------- |
| | | | | | | minimum | stripping | | times | required | for |
multistorey construction, they also point out that
8.4 STRIPPING FORMWORK
| | | | | | | the construction | | and | stripping | of | formwork |
| --- | --- | --- | --- | --- | --- | ------------------ | --- | ---- | ---------- | --- | --------- |
systems which involve reshoring should be in
General – The project designer is normally
required to provide a schedule of stripping accordance with the project and formwork
times for formwork which is in accord with the documentation. Consequently, it is incumbent
| | | | | | | on the | project | designer | | to provide | this |
| --- | --- | --- | --- | --- | --- | -------- | -------- | --------- | --- | ------------ | ----- |
requirements of AS 3600. Reference is also
made in AS 3600 to the requirements for information. Reshoring is a hazardous
stripping detailed in AS 3610, and it notes that operation which, unless carried out in a correct
| | | | | | | and systematic | | manner, | | can | lead to |
| --- | --- | --- | --- | --- | --- | ---------------- | --- | -------- | --- | ---- | --------- |
where stripping requirements in AS 3600 are
more stringent than in AS 3610, then the unacceptable loads being placed on the
AS 3600 requirements will prevail. The concrete at an early age.
nominated times are minimum stripping times
This is particularly so for prestressed concrete
designed to ensure that the structure remains
as the stressing operations can cause quite
secure from collapse (under its own weight plus
| | | | | | | substantial | loads | to | be transferred | | to the |
| --- | --- | --- | --- | --- | --- | ------------ | ------ | --- | ---------------- | --- | -------- |
that from any additional super-imposed loads)
| | | | | | | shores, | re-shores, | back-props | | | and other |
| --- | --- | --- | --- | --- | --- | -------- | ----------- | ----------- | --- | --- | ----------- |
and from damage which might affect its later
temporary supports.
performance (e.g. cracking or deformation in
excess of that anticipated by the designer). The advice of the project designer should
Stripping must be carried out in a planned and therefore always be sought for both reinforced
controlled manner to ensure the proper and and prestressed concrete construction before
| controlled | transfer | of | loads | from | the | | | | | | |
| ----------- | --------- | --- | ------ | ----- | ---- | --- | --- | --- | --- | --- | --- |
specified procedures are changed in any way. If
formwork/falsework to the permanent or specific procedures are not provided in the
existing structure. project documentation, they should be sought.
AS 3610.1 also provides guidance on stripping
9. FORMWORK DOCUMENTATION
times, which, while compatible with AS 3600,
refines the requirements to take account of the
AS 3610.1 contains a number of requirements
specified class of surface finish (Table 27.4).
| | | | | | | in relation | to | documentation | | including | (a) |
| --- | --- | --- | --- | --- | --- | ------------- | --- | -------------- | --- | ---------- | ---- |
The stripping times for formwork removal noted documentation requirements will vary
depending on the complexity of the project, (b)
in AS 3600 and shown in Table 27.4 shall be
it is expected that all aspects of the formwork
| increased where L | | s /D > 280/(D +100) (where | | | | | | | | | |
| ----------------- | --- | ---------------------------- | --- | --- | --- | --- | --- | --- | --- | --- | --- |
L is the span between formwork supports and design, fabrication, stripping etc. will be
s
included in the documentation which is to be
D is the overall depth of the member); and the
prepared by ‘competent persons’ (as defined in
superimposed construction load is >2.0 kPa.
section 1.5.1.5 of AS 3610.1), and (c) where
Subject to these general provisions, stripping of elements of the design are done by different
formwork should be done at the earliest time –
| | | | | | | persons, | or where | proprietary | | information | is |
| --------- | ---------- | --------- | --- | --------------- | --- | --------- | ---------- | ------------ | --- | ------------ | --- |
| provided | that the | concrete | | has developed | | | | | | | |
included, all elements need to be collected and
sufficient strength to prevent damage to the collated into a single comprehensive document
surface of the element. For vertical surfaces, if
that fully describes formwork requirements.
formwork is stripped less than 18 hours after
casting then special care needs to be taken to
| ensure the surface is not damaged. Where it is | | | | | | | | | | | |
| ----------------------------------------------- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- |
| | | | | | | | | | | | Version 1.0 |
| --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | ------------- |
PAGE 15 > Guide to Concrete Construction — Part IX-Section 27 – Formwork
Table 27.4 – Minimum Formwork Stripping Times – In-situ Concrete (from AS 3600 and AS 3610.1)
Surface finish Hot conditions Average conditions Cold conditions
Formed surface
| | classification | > 20°C | 20°C ≥ x > 12°C | 12°C ≥ x > 5°C |
| --------------- | ----------------- | -------- | ---------------- | --------------- |
| Vertical faces | Classes 1, 2, 3* | 1 day | 2 days | 3 days |
| | | | | |
| | Classes 4, 5 | 9 hours | 12 hours | 18 hours |
A minimum of one day applies to the stripping of vertical faces where frost damage is likely.
Beam and slab Formwork removal of beams and slab soffits must be in accordance with AS 3600 section
soffits elements – 17.6.2.3 and 17.6.2.4 (and not less than 3 days) as well as conforming to AS 3610.1
| reinforced slabs of | Appendix C3. | | | |
| -------------------- | ------------- | --- | --- | --- |
| Normal Class | | | | |
| concrete | | | | |
NOTE: *Where colour control on surface finishes has been specified it is advisable to strip forms early, subject to the limitations
given.
Version 1.0
PAGE 16 > Guide to Concrete Construction — Part IX-Section 27 – Formwork
10. SUMMARY – CONSTRUCTION CHECKLIST
| • Loads | | | • | Watertightness | | | |
| --------- | --- | --- | --- | --------------- | --- | --- | --- |
− What are the stacked load limits at all stages? − Are all joints properly sealed and cramped?
− Are the stacked materials on spreaders? − Are the construction joints sealed?
| | − Will the loads be exceeded by any construction | | | | | | |
| --- | -------------------------------------------------- | --- | --- | --- | --- | --- | --- |
procedure?
• Reinforcing Steel/Inserts
− Is the reinforcement correct?
• Materials − Are all inserts/blockouts in the correct location?
| | − Are the correct form materials being used? | | | | | | |
| --- | ---------------------------------------------- | ------------ | ----------------- | --- | --- | --- | --- |
| | − Is the form face | appropriate | for the finish | | | | |
• Concrete/Concreting
required?
| | | | | − Is | the mix design | in accordance | with the |
| --- | --- | --- | --- | ------ | ----------------- | --------------- | ---------- |
specification?
| • Position | | | | − What | is the maximum | | rate of placement |
| ------------ | ------------------------------------------ | --- | --- | ----------- | ----------------- | --- | -------------------- |
| | − Are the forms in the correct location? | | | permitted? | | | |
− Are they to dimension and within tolerance? − Are the forms maintaining line, level, plumb,
− Are they accurate to line, level and plumb? shape etc. during concreting?
| | | | | | | | |
| ---------- | --- | --- | --- | ---------- | --- | --- | --- |
| • Fixing | | | • | Stripping | | | |
− Is the nailing/screwing adequate? − What are the minimum stripping times?
− Are the ties the correct type? − Has the project designer permitted modification
| | − Are they on the correct grid? | | | of these? | | | |
| --- | --------------------------------- | --- | --- | ---------- | --- | --- | --- |
− Are all ties, clamps and bolts tight? − Do the procedures enable stripping without
damage to form or concrete?
| | − Are wedges tight and nailed? | | | | | | |
| --- | -------------------------------- | --- | --- | ------- | ---------------- | ----------- | ----------------- |
| | | | | − Are | the provisions | consistent | with the re-use |
times required?
• Bracing/Props
− Has the crane the necessary slings etc. to move
| | − Are the props plumb? | | | the forms quickly? | | | |
| --- | ------------------------ | --- | --- | ------------------- | --- | --- | --- |
− Are all loads centrally placed? − What curing methods are to be used once the
− Are supported elements wedged and nailed? formwork is removed?
− Are props straight? − Is the storage area for the formwork properly
| | − Are base plates on adequate foundations? | | | organised? | | | |
| --------------- | -------------------------------------------- | --- | --- | ---------------------------------- | ---------------- | ------------ | ----------- |
| | − Is the bracing correct? | | | | | | |
| | − Is the bracing firmly connected? | | | | | | |
| | | | • | Safety | | | |
| | | | | − Are | there adequate | guardrails, | handrails, |
| • Cleanliness | | | | walkways, signs etc. in position? | | | |
| | − Are the form faces cleaned? | | | | | | |
| | − Is any damage correctly repaired? | | | | | | |
• Inspection
| | − Is the correct release agent in use? | | | | | | |
| --- | ---------------------------------------- | --- | --- | --- | --- | --- | --- |
− Are there enough experienced inspectors on the
| | − Is it being correctly applied? | | | | | | |
| --- | ---------------------------------- | --- | --- | --- | --- | --- | --- |
job to provide appropriate supervision?
| | − Has all debris been removed from within the | | | | | | |
| --- | ----------------------------------------------- | --- | --- | --- | --- | --- | --- |
form?
| | | | | | | | |
| --- | --- | --- | --- | --- | --- | --- | --- |
PAGE 17 > Guide to Concrete Construction — Part IX-Section 27 – Formwork Version 1.0
11. RELEVANT AUSTRALIAN STANDARDS CCAA OFFICES
1) AS 3600 – Concrete structures
2) AS 3610.1 – Formwork for concrete, Part 1: NATIONAL OFFICE (NSW)
Specifications Level 10
163 -175 O’Riordan Street
Mascot NSW 2020
POSTAL ADDRESS
PO Box 124
Mascot NSW 1460
Telephone: (02) 9667 8300
QUEENSLAND
Level 14, 300 Ann Street,
Brisbane QLD 4000
Telephone: (07) 3227 5200
VICTORIA
Suite 910/1 Queens Road
Melbourne VIC 3004
Telephone: (03) 9825 0200
WESTERN AUSTRALIA
45 Ventnor Avenue
West Perth WA 6005
Telephone: (08) 9389 4452
SOUTH AUSTRALIA
Level 30, Westpac House
91 King William Street
Adelaide SA 5000
Telephone: (02) 9667 8300
TASMANIA
PO Box 1441
Lindisfarne TAS 7015
Telephone: (03) 6491 2529
ONLINE DETAILS
www.ccaa.com.au
Email: info@ccaa.com.au
Since the information provided is intended for general
guidance only and in no way replaces the services of
professional consultants on particular projects, no legal
liability can be accepted by Cement Concrete & Aggregates
Australia for its use.
© Cement Concrete & Aggregates Australia
PAGE 18 > Guide to Concrete Construction — Part IX-Section 27 – Formwork Version 1.0