Priority 3: "Start Now" Work - Week 1 Kickoff (Nov 18-22)

Status: βœ… APPROVED - LAUNCHING TODAY (Nov 18) Goal: Complete 8.5 people-days of prep work in parallel for Phase 1.C fast-track Timeline: Nov 18 (Mon) - Nov 22 (Fri) Phase 1.C Launch: Dec 8, 2025


🎯 Mission

Prepare for Phase 1.C acceleration (Dec 8-13) by running 4 independent prep teams in parallel. This eliminates bottlenecks and compresses Phase 1.C execution from 5 days β†’ 4.5 effective days.

Success = Dec 13 Phase 1 completion with all quality gates passed (95%+ coverage, 0 critical vulns)


πŸ‘₯ Team Assignments & Daily Tasks

βœ… TEAM 1: Design System Foundation (2 people-days)

Lead: Chief GUI Designer Support: Frontend Architect 3

Deliverable: Design System Standards Document (100% complete by Fri)

Monday Nov 18

  • 09:00 - Kickoff meeting (30 min)
  • 10:00 - Review existing component patterns in codebase
  • 11:00 - Document component hierarchy (20+ components identified)
  • 14:00 - Define naming conventions (consistent across system)
  • 16:00 - Checkpoint: Hierarchy + naming doc ready

Tuesday-Wednesday (Nov 19-20)

  • Review color palette usage across codebase
  • Document color system (semantic naming, accessibility standards)
  • Establish typography system (font families, sizes, weights)
  • Define spacing scale (8px base unit system)
  • Document accessibility requirements (WCAG 2.1 AA compliance)

Thursday-Friday (Nov 21-22)

  • Create component documentation template
  • Write usage guidelines for 3-4 primary components
  • Finalize and review complete standards document
  • Prepare Storybook integration checklist for Team 2

Deliverable File: design-system/DESIGN_SYSTEM_STANDARDS.md

Definition of Done:

  • βœ… Component hierarchy documented (all 20+ components)
  • βœ… Naming conventions established and examples given
  • βœ… Color system with semantic naming
  • βœ… Typography scale documented
  • βœ… Spacing system (8px base) defined
  • βœ… Accessibility standards clear (WCAG 2.1 AA)
  • βœ… Ready for Team 2 Storybook integration

βœ… TEAM 2: Storybook Infrastructure (1.5 people-days)

Lead: Frontend Architect 3 Support: Technical Writer

Deliverable: Storybook environment fully configured and ready for stories

Monday Nov 18

  • 09:00 - Kickoff meeting (30 min)
  • 10:00 - Install Storybook 7.x in monorepo
  • 11:00 - Configure Chromatic integration for visual testing
  • 14:00 - Set up build pipeline and CI/CD
  • 16:00 - Checkpoint: Storybook running locally

Tuesday-Wednesday (Nov 19-20)

  • Create Storybook templates for common patterns
  • Configure component documentation patterns
  • Set up Storybook addons (accessibility, actions, controls)
  • Create CSF (Component Story Format) templates
  • Document story writing standards

Thursday-Friday (Nov 21-22)

  • Test Storybook build and deployment pipeline
  • Create quick-start guide for story authors
  • Verify Chromatic integration working
  • Final testing and documentation
  • Hand off to Phase 1.C teams

Deliverable File: storybook/STORYBOOK_SETUP.md

Definition of Done:

  • βœ… Storybook 7.x installed and running
  • βœ… Chromatic integration configured
  • βœ… CSF templates ready for story writing
  • βœ… Accessibility addon enabled
  • βœ… CI/CD pipeline working
  • βœ… Story templates documented
  • βœ… 100+ stories can start writing Dec 8

βœ… TEAM 3: E2E Test Planning (3 people-days)

Lead: QA Engineer 1 Support: QA Engineer 2

Deliverable: 100+ E2E test scenarios designed and ready for execution

Monday Nov 18

  • 09:00 - Kickoff meeting (30 min)
  • 10:00 - Review Phase 1.C blocks and requirements
  • 11:00 - Plan E2E test scenarios (user journeys, critical paths)
  • 14:00 - Map test coverage matrix (features Γ— browsers Γ— devices)
  • 16:00 - Checkpoint: Test plan document 50% complete

Tuesday-Wednesday (Nov 19-20)

  • Design 100+ test scenarios (detailed steps for each)
  • Create test data generators (user fixtures, mock data)
  • Document cross-browser matrix (Chrome, Firefox, Safari, Edge)
  • Design accessibility testing scenarios (WCAG 2.1)
  • Document performance testing approach
  • Create Playwright test templates

Thursday-Friday (Nov 21-22)

  • Review and finalize all test scenarios
  • Create test execution checklist
  • Document expected results for each test
  • Prepare test environment requirements
  • Hand off to QA team for Dec 8-13 execution

Deliverable File: testing/E2E_TEST_PLAN.md

Definition of Done:

  • βœ… 100+ test scenarios documented with steps
  • βœ… Cross-browser testing matrix defined
  • βœ… Test data generators created
  • βœ… Accessibility scenarios included
  • βœ… Performance testing approach defined
  • βœ… Playwright templates ready
  • βœ… Test environment requirements clear
  • βœ… Execution ready for Phase 1.C

βœ… TEAM 4: Performance Infrastructure (2 people-days)

Lead: Frontend Performance Specialist Support: DevOps Engineer 2

Deliverable: Performance monitoring infrastructure operational and validated

Monday Nov 18

  • 09:00 - Kickoff meeting (30 min)
  • 10:00 - Review current performance baseline
  • 11:00 - Set up Core Web Vitals monitoring (FCP, LCP, CLS, INP)
  • 14:00 - Configure performance profiling tools
  • 16:00 - Checkpoint: Monitoring dashboard online

Tuesday-Wednesday (Nov 19-20)

  • Establish performance targets verification
  • Create CI/CD performance gates
  • Set up automated bundle size analysis
  • Configure production monitoring alerts
  • Document performance optimization workflow
  • Create performance testing checklist

Thursday-Friday (Nov 21-22)

  • Validate all monitoring and alerting
  • Test performance gates in CI/CD
  • Create performance optimization guide
  • Prepare dashboards for Phase 1.C team
  • Document edge cases and fallbacks

Deliverable File: performance/PERFORMANCE_INFRASTRUCTURE.md

Definition of Done:

  • βœ… Core Web Vitals monitoring operational
  • βœ… Performance profiling tools configured
  • βœ… CI/CD gates set (FCP <1.5s, LCP <2.5s, CLS <0.1)
  • βœ… Bundle size tracking enabled
  • βœ… Alerting and notifications working
  • βœ… Performance dashboards accessible
  • βœ… Optimization workflow documented
  • βœ… Ready for Phase 1.C performance block

πŸ“… Daily Coordination (All Teams)

Daily Standup: 09:15 AM (15 minutes)

Attendees: All 4 team leads + System Director Format:

  • Each team: 2-min status (on track / blockers)
  • Blockers: 1-2 min each for resolution
  • Alignment on dependencies

Location: Zoom or in-person (TBD)

Daily End-of-Day Check-in: 17:00 (10 minutes)

Attendees: All 4 team leads Format:

  • Status update
  • Anything needed for next day
  • Progress toward deliverables

🎯 Daily Targets

Monday Nov 18 (Kickoff Day)

  • Team 1: Component hierarchy documented
  • Team 2: Storybook installed and running locally
  • Team 3: Test plan document started (50% complete)
  • Team 4: Performance monitoring dashboard online

Tuesday Nov 19

  • Team 1: Color palette + typography documented
  • Team 2: CSF templates and documentation complete
  • Team 3: 100+ test scenarios drafted
  • Team 4: CI/CD gates configured and testing

Wednesday Nov 20

  • Team 1: 90% of standards doc complete
  • Team 2: Story writing guides ready
  • Team 3: Test data generators created
  • Team 4: Production monitoring validated

Thursday Nov 21

  • Team 1: Final review and sign-off
  • Team 2: Storybook fully tested and documented
  • Team 3: All 100+ scenarios finalized
  • Team 4: Performance dashboards prepared

Friday Nov 22 (Checkpoint Day)

  • Team 1: βœ… Design System Standards document DONE
  • Team 2: βœ… Storybook infrastructure DONE
  • Team 3: βœ… E2E test plan with 100+ scenarios DONE
  • Team 4: βœ… Performance infrastructure DONE

Friday End-of-Day Celebration: All 4 deliverables complete, teams ready for Phase 1.C


🚨 Blocker Resolution

If a team discovers blockers:

  1. Immediate Action (same day):

    • Report in daily standup (09:15)
    • Identify if blocker blocks other teams
    • Propose workaround or solution
  2. Resolution Paths:

    • Dependency blocker: Coordinate with other team leads
    • Technical blocker: Escalate to System Director
    • Resource blocker: Request additional resources (approved by director)
  3. Example Blocker Scenarios:

    • "Storybook 7.x has breaking change" β†’ Design System team adjusts templates
    • "Performance monitoring needs backend API" β†’ DevOps Engineer 2 creates API
    • "Test scenario requires feature not yet built" β†’ QA team documents dependency, Phase 1.C team prioritizes

No blocker will be allowed to derail Nov 22 deliverables without explicit System Director decision.


πŸ“Š Success Metrics (Friday Nov 22)

Team 1: Design System

  • βœ… 100% of standards documented
  • βœ… All naming conventions clear with examples
  • βœ… Accessibility requirements (WCAG 2.1 AA) documented
  • [ ] βœ… Ready for Storybook integration

Team 2: Storybook

  • βœ… Storybook 7.x fully operational
  • βœ… Chromatic integration working
  • βœ… CSF templates ready for 100+ stories
  • βœ… CI/CD pipeline verified

Team 3: E2E Testing

  • βœ… 100+ test scenarios documented
  • βœ… Test data generators created
  • βœ… Cross-browser matrix defined
  • βœ… Playwright templates ready

Team 4: Performance

  • βœ… Core Web Vitals monitoring operational
  • βœ… CI/CD performance gates working
  • βœ… Performance dashboards accessible
  • βœ… Optimization workflow documented

πŸŽ‰ Phase 1.C Launch: Dec 8

After this week's prep work completes:

  • All infrastructure ready (0 ramp-up time)
  • Day 1 (Dec 8): Immediate productivity
  • Blocks 1-3 run in parallel
  • Dec 13: Phase 1 complete βœ…

πŸ“ž Key Contacts

System Director: For approvals and escalations Team Leads: For daily coordination Tech Leads: For technical decisions


πŸš€ LAUNCH STATUS

βœ… APPROVED - Start Time: NOW (Nov 18, 2025)

All team leads: Check your email for task assignments. All team members: Check Slack for team channel invites.

First Daily Standup: Nov 18, 09:15 AM


Generated: Nov 17, 2025 By: Claude Code - Priority 3 Fast-Track Next Review: Nov 22 Friday EOD (All deliverables checkpoint)