hash stringlengths 32 32 | doc_id stringlengths 5 12 | section stringlengths 5 1.47k | content stringlengths 0 6.67M |
|---|---|---|---|
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.33.2 Conformance requirement | If the UE receives:
-a PHYSICAL CHANNEL RECONFIGURATION message;
it shall:
1> perform the physical layer synchronisation procedure as specified in TS25.214;
1> act upon all received information elements as specified in TS25.331 subclause 8.6, unless specified in the following and perform the actions below.
The UE shall... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.33.3 Test purpose | 1. To confirm that the UE transits from CELL_FACH to CELL_DCH according to the PHYSICAL CHANNEL RECONFIGURATION message.
2. To confirm that the UE transmits PHYSICAL CHANNEL RECONFIGURATION COMPLETE message on the uplink DCCH using AM RLC on a dedicated physical channel in a different frequency. |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.33.4 Method of test | Initial Condition
System Simulator: 2 cells–Cell 1 is active and cell 6 is inactive.
SYSTEM INFORMATION BLOCK TYPE 1 (see specific message contents).
UE: PS_DCCH+DTCH_FACH (state 6-11) as specified in clause 7.4 of TS 34.108.
Test Procedure
Table 8.2.6.33
Parameter
Unit
Cell 1
Cell 6
T0
T1
T0
T1
UTRA RF Channel Number
... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.33.5 Test requirement | After step 3 the UE shall transmit a PHYSICAL CHANNEL RECONFIGURATION COMPLETE message on the DCCH using AM RLC in cell 6.
After step 4 the UE shall be in CELL_DCH state in cell 6. |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.34 Physical channel reconfiguration from CELL_FACH to CELL_PCH (Frequency band modification): Success | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.34.1 Definition | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.34.2 Conformance requirement | If the UE receives:
-a PHYSICAL CHANNEL RECONFIGURATION message;
it shall:
1> act upon all received information elements as specified in TS25.331 subclause 8.6, unless specified in the following and perform the actions below.
1> enter a state according to TS25.331 subclause 8.6.3.3.
In case the procedure was triggered ... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.34.3 Test purpose | 1. To confirm that the UE transmits a PHYSICAL CHANNEL RECONFIGURATION COMPLETE message on the uplink DCCH using AM RLC.
2. To confirm that the UE transits from CELL_FACH to CELL_PCH according to the PHYSICAL CHANNEL RECONFIGURATION message.
3. To confirm that the UE selects a common physical channel in a different fre... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.34.4 Method of test | Initial Condition
System Simulator: 2 cells – Cell 1 is active and cell 6 is inactive.
UE: "Registered idle mode on PS" (state 3) in cell 1 as specified in clause 7.4 of TS 34.108, depending on the CN domain supported by the UE. If the UE supports both CS and PS domains, the initial UE state shall be "Registered idle m... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.34.5 Test requirement | After step 6 the UE shall transmit a PHYSICAL CHANNEL RECONFIGURATION COMPLETE message on uplink DCCH using AM RLC in cell 1.
After step 8 the UE shall be in CELL_PCH state in cell 6. |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.35 Physical channel reconfiguration for transition from CELL_FACH to URA_PCH (Frequency band modification): Success | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.35.1 Definition | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.35.2 Conformance requirement | If the UE receives:
-a PHYSICAL CHANNEL RECONFIGURATION message;
it shall:
1> act upon all received information elements as specified in TS25.331 subclause 8.6, unless specified in the following and perform the actions below.
1> enter a state according to TS25.331 subclause 8.6.3.3.
In case the procedure was triggered ... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.35.3 Test purpose | 1. To confirm that the UE transmits a PHYSICAL CHANNEL RECONFIGURATION COMPLETE message on the uplink DCCH using AM RLC.
2. To confirm that the UE transits from CELL_FACH to URA_PCH according to the PHYSICAL CHANNEL RECONFIGURATION message.
3. To confirm that the UE selects a common physical channel in a different freq... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.35.4 Method of test | Initial Condition
System Simulator: 2 cells–Cell 1 in active and cell 6 is inactive
UE: Registered idle mode on PS" (state 3) in cell 1 as specified in clause 7.4 of TS 34.108, depending on the CN domain supported by the UE. If the UE supports both CS and PS domains, the initial UE state shall be "Registered idle mode ... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.35.5 Test requirement | After step 3 the UE shall transmits a PHYSICAL CHANNEL RECONFIGURATION COMPLETE message on the DCCH using AM RLC in cell 1.
After step 8 the UE shall be in URA_PCH state in cell 6. |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.36 Physical channel reconfiguration for transition from CELL_FACH to CELL_FACH (Frequency band modification): Success | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.36.1 Definition | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.36.2 Conformance requirement | If the UE receives:
-a PHYSICAL CHANNEL RECONFIGURATION message;
it shall:
1> act upon all received information elements as specified in TS25.331 subclause 8.6, unless specified in the following and perform the actions below.
1> enter a state according to TS25.331 subclause 8.6.3.3.
If the UE was in CELL_FACH state upo... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.36.3 Test purpose | 1. To confirm that the UE transits from CELL_FACH to CELL_FACH according to the PHYSICAL CHANNEL RECONFIGURATION message.
2. To confirm that the UE transmits PHYSICAL CHANNEL RECONFIGURATION COMPLETE message on the uplink DCCH using AM RLC on a common physical channel in a different frequency. |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.36.4 Method of test | Initial Condition
System Simulator: 2 cells – Cell 1 is active and cell 6 is inactive.
UE: "Registered idle mode on PS" (state 3) in cell 1 as specified in clause 7.4 of TS 34.108, depending on the CN domain supported by the UE. If the UE supports both CS and PS domains, the initial UE state shall be "Registered idle m... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.36.5 Test requirement | After step 6 the UE shall transmit a CELL UPDATE message on the CCCH in cell 6.
After step 8 the UE shall transmit a UTRAN MOBILITY INFORMATION CONFIRM message on the DCCH using AM RLC in cell 6.
After step 9 the UE shall transmit a PHYSICAL CHANNEL RECONFIGURATION COMPLETE message on the DCCH using AM RLC in cell 6.
A... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.37 Physical channel reconfiguration for transition from CELL_DCH to CELL_DCH (Hard handover to another frequency with timing re-initialised) | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.37.1 Definition | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.37.2 Conformance requirement | The UE shall:
1> be able to receive any of the following messages:
…
2> PHYSICAL CHANNEL RECONFIGURATION message;
1> perform a hard handover and apply physical layer synchronisation procedure A as specified in [29], even if no prior UE measurements have been performed on the target cell and/or frequency.
…
In case the ... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.37.3 Test Purpose | To confirm that the UE is able to perform a hard-handover with change of frequency, with and without prior measurements on the target frequency.
To confirm that the UE answers with a PHYSICAL CHANNEL RECONFIGURATION COMPLETE message when the procedure has been initiated with the PHYSICAL CHANNEL RECONFIGURATION message... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.37.4 Method of test | Initial Condition
System Simulator: 4 cells – Cell 1 and cell 2 on frequency f1, cell 4 and cell 5 on frequency f2. Cells 2 and 5 shall have the same primary scrambling code.
UE: "CS-DCCH+DTCH_DCH" (state 6-9) or "PS-DCCH+DTCH_DCH" (state 6-10) as specified in clause 7.4 of TS 34.108, depending on the CN domain support... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.37.5 Test Requirement | After step 1, the UE shall send a MEASUREMENT REPORT message triggered by event 1a for cell 2.
After step 3, the UE shall send an ACTIVE SET UPDATE COMPLETE message to acknowledge that it has added cell 2 to its active set.
After step 5, the UE shall transmit a PHYSICAL CHANNEL RECONFIGURATION COMPLETE message to the S... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.38 Physical channel reconfiguration for transition from CELL_DCH to CELL_DCH (Hard handover to another frequency with timing re-initialised): Failure (Physical channel failure and reversion to old channel) | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.38.1 Definition | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.38.2 Conformance requirement | When a physical dedicated channel establishment is initiated by the UE, the UE shall start a timer T312 and wait for layer 1 to indicate N312 "in sync" indications. On receiving N312 "in sync" indications, the physical channel is considered established and the timer T312 is stopped and reset.
If the timer T312 expires ... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.38.3 Test purpose | To confirm that the UE reverts to the old configuration (including measurement configurations, ciphering procedures and compressed mode configurations if required) and transmits a PHYSICAL CHANNEL RECONFIGURATION FAILURE message on the DCCH using AM RLC if the UE fails to reconfigure the new physical channel according ... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.38.4 Method of test | Initial Condition
System Simulator: 4 cells – Cell 1 and cell 2 on frequency f1, cell 4 on frequency f2and cell 5 on frequency f3.
UE: "CS-DCCH+DTCH_DCH" (state 6-9) or "PS-DCCH+DTCH_DCH" (state 6-10) as specified in clause 7.4 of TS 34.108, depending on the CN domain supported by the UE. If the UE supports both CS and... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.38.5 Test Requirement | After step 1, the UE shall send a MEASUREMENT REPORT message triggered by event 1a for cell 2.
After step 3, the UE shall send an ACTIVE SET UPDATE COMPLETE message to acknowledge that it has added cell 2 to its active set.
After step 5, the UE shall transmit a PHYSICAL CHANNEL RECONFIGURATION COMPLETE message to the S... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.39 Physical Channel Reconfiguration for transition from CELL_DCH to CELL_DCH: Success (Seamless SRNS relocation) (without pending of ciphering) | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.39.1 Definition | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.39.2 Conformance requirement | 1> if the reconfiguration procedure is simultaneous with SRNS relocation procedure:
2> if the transmitted message is a RADIO BEARER RECONFIGURATION:
3> include the IE "New U-RNTI".
2> else:
3> include the IE "Downlink counter synchronisation info".
The UE shall:
1> if the received reconfiguration message included the ... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.39.3 Test purpose | 1. To confirm that the UE performs a combined hard handover and SRNS relocation and then transmit a PHYSICAL CHANNEL RECONFIGURATION COMPLETE message in the new cell.
2. In the case that ciphering is applied by the network, to confirm that the UE applies the new ciphering algorithm following a successful SRNS relocatio... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.39.4 Method of test | Initial Condition
System Simulator: 2 cells – Cell 1 and 2
UE: PS-DCCH+DTCH_DCH (state 6-10) or CS-DCCH+DTCH_DCH (state 6-9) or PS+CS-DCCH+DTCH_DCH (state 6-14) as specified in clause 7.4 of TS 34.108, depending on the CN domain(s) and services supported by the UE. If UE supports PS+CS but only supports streaming servi... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.39.5 Test requirement | After step 3, the UE shall transmit a PHYSICAL CHANNEL RECONFIGURATION COMPLETE message on the uplink DCCH using AM RLC which includes a calculated new START value according to the formula “STARTX' = MSB20 (MAX {COUNT-C, COUNT-I | radio bearers and signalling radio bearers using the most recently configured CKX and IKX... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.40 Physical Channel Reconfiguration for transition from CELL_DCH to CELL_DCH: Success (Two radio links, change of HS-PDSCH configuration) | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.40.1 Definition and applicability | All UEs which support FDD and HS-PDSCH. |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.40.2 Conformance requirement | In case the procedure was triggered by reception of a PHYSICAL CHANNEL RECONFIGURATION message, the UE shall:
1> transmit a PHYSICAL CHANNEL RECONFIGURATION COMPLETE as response message on the uplink DCCH using AM RLC.
…
The variable HS_DSCH_RECEPTION shall be set to "TRUE" only when all the following conditions are me... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.40.3 Test purpose | To confirm that, when two radio links are used, the UE changes HS-DSCH specific uplink DPCH power control and measurement feedback configuration according to the received PHYSICAL CHANNEL RECONFIGURATION message. |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.40.4 Method of test | Initial Condition
System Simulator: 2 cells - Cell 1 and 2 are active
UE: PS_DCCH_DTCH_HS_DSCH (state 6-17) as specified in clause 7.4 of TS 34.108.
Related ICS/IXIT statement(s)
- UE supports FDD
- UE supports HS-PDSCH
Test Procedure
Table 8.2.6.40
Parameter
Unit
Cell 1
Cell 2
T0
T1
T0
T1
UTRA RF Channel Number
Mid Ra... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.40.5 Test requirements | After step 1, the UE shall transmit a MEASUREMENT REPORT message.
After step 5, the UE shall transmit a PHYSICAL CHANNEL RECONFIGURATION COMPLETE message.
8.2.6.40a Physical Channel Reconfiguration for transition from CELL_DCH to CELL_DCH: Success (change of HS-PDSCH configuration)
8.2.6.40a.1 Definition and applicabil... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.41 Physical Channel Reconfiguration for transition from CELL_DCH to CELL_DCH: Success (Timing re-initialised hard handover to another frequency, signalling only) | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.41.1 Definition and applicability | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.41.2 Conformance requirement | In case the procedure was triggered by reception of a PHYSICAL CHANNEL RECONFIGURATION message, the UE shall:
1> transmit a PHYSICAL CHANNEL RECONFIGURATION COMPLETE as response message on the uplink DCCH using AM RLC.
1> the procedure ends.
…
If IE "Timing indication" has the value "initialise", UE shall:
1> execute t... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.41.3 Test purpose | To confirm that the UE makes a timing re-initialised interfrequency hard handover on a signalling only configuration without prior measurement on the target frequency according to the received PHYSICAL CHANNEL RECONFIGURATION message. |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.41.4 Method of test | Initial Condition
System Simulator: 2 cells–Cells 1 and 6 are active.
UE: PS_DCCH_DCH (state 6-7) as specified in clause 7.4 of TS 34.108.
Test Procedure
The SS transmits a PHYSICAL CHANNEL RECONFIGURATION message to the UE, which includes new frequency information and IE "Timing indicator" set to initialise. The UE sh... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.41.5 Test requirements | After step 1, the UE shall transmit a PHYSICAL CHANNEL RECONFIGURATION COMPLETE message on the uplink DCCH using AM RLC in cell 6. |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.42 Physical Channel Reconfiguration for transition from CELL_DCH to CELL_DCH: Success (Timing re-initialized hard handover to another frequency, Serving HS-DSCH cell change) | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.42.1 Definition and applicability | All UEs which support FDD or TDD and HS-PDSCH. |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.42.2 Conformance requirement | In case the procedure was triggered by reception of a PHYSICAL CHANNEL RECONFIGURATION message, the UE shall:
1> transmit a PHYSICAL CHANNEL RECONFIGURATION COMPLETE as response message on the uplink DCCH using AM RLC.
1> the procedure ends.
…
The variable HS_DSCH_RECEPTION shall be set to "TRUE" only when all the foll... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.42.3 Test purpose | To confirm that the UE is able to perform a timing re-initialised hard handover to another frequency without prior measurement on the target frequency in conjunction with a serving HS-DSCH cell change according to the received PHYSICAL CHANNEL RECONFIGURATION message. |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.42.4 Method of test | Initial Condition
System Simulator: 2 cells - Cell 1 on frequency f1, and cell2 on frequency f2. Cells 1 and 2 have different primary scrambling codes (FDD only),
UE: PS_DCCH_DCH (state 6-7) as specified in clause 7.4 of TS 34.108.
Related ICS/IXIT statement(s)
- UE supports FDD or TDD
- UE supports HS-PDSCH
Test Proc... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.42.5 Test requirements | After step 1, the UE shall transmit a PHYSICAL CHANNEL RECONFIGURATION COMPLETE message.
8.2.6.42a Physical Channel Reconfiguration for transition from CELL_DCH to CELL_DCH: Success (Timing re-initialized hard handover to another frequency, Serving HS-DSCH cell change)
(Cells belong to different frequency bands for LCR... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.43 Physical Channel Reconfiguration for transition from CELL_DCH to CELL_DCH: Success (Seamless SRNS relocation with pending of ciphering) | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.43.1 Definition | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.43.2 Conformance requirement | <from sub-clause 8.2.2.3>
If the UE receives:
- a PHYSICAL CHANNEL RECONFIGURATION message:
it shall:
…
The UE shall transmit a response message as specified in TS 25.331 subclause 8.2.2.4, setting the information elements as specified below. The UE shall:
1> if the received reconfiguration message included the IE "Dow... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.43.3 Test purpose | To confirm that the UE includes the previously received new keys from the last SECURITY MODE COMMAND in the new ciphering configuration in the case the ciphering configuration for RB2 from the last received SECURITY MODE COMMAND has not yet been applied because the activation times not having been reached. |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.43.4 Method of test | Initial Condition
System Simulator: 2 cells – Cell 1 and 2
UE: PS-DCCH+DTCH_DCH (state 6-10) or CS-DCCH+DTCH_DCH (state 6-9) or PS+CS-DCCH+DTCH_DCH (state 6-14) as specified in clause 7.4 of TS 34.108, depending on the CN domain(s) supported by the UE.
Test Procedure
Table 8.2.6.43
Parameter
Unit
Cell 1
Cell 2
T0
T1
T0... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.43.5 Test requirement | After step 1, UE shall transmit a SECURITY MODE COMPLETE message on the uplink DCCH using AM RLC.
After step 4, the UE shall transmit a PHYSICAL CHANNEL RECONFIGURATION COMPLETE message on the uplink DCCH using AM RLC which includes a calculated new START value according to the formula “STARTX' = MSB20 (MAX {COUNT-C, C... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.44 Physical Channel Reconfiguration for transition from CELL_DCH to CELL_DCH: Failure (Radio link failure in new configuration) | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.44.1 Definition | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.44.2 Conformance requirement | <from sub-clause 8.2.2.14>
If the criteria for radio link failure is met in the new configuration during the reconfiguration procedure (i.e. while UE is waiting for RLC acknowledgement for a response message.) as specified in subclause 8.5.6, the UE shall:
1> if the received reconfiguration causes either:
- the IE "Rec... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.44.3 Test purpose | To confirm that the UE enters idle mode state when UE detects radio link failure after UE started using the new configuration but before receiving the RLC acknowledgement of the reconfiguration complete message. |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.44.4 Method of test | Initial Condition
System Simulator: 2 cells – Cell 1 and 2
UE: PS-DCCH+DTCH_DCH (state 6-10) or CS-DCCH+DTCH_DCH (state 6-9) or PS+CS-DCCH+DTCH_DCH (state 6-14) as specified in clause 7.4 of TS 34.108, depending on the CN domain(s) and services supported by the UE. If UE supports PS+CS but only supports streaming servi... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.44.5 Test requirement | After step 2, the UE shall transmit a PHYSICAL CHANNEL RECONFIGURATION COMPLETE message on the uplink DCCH using AM RLC which includes which includes a calculated new START value according to the formula “STARTX' = MSB20 (MAX {COUNT-C, COUNT-I | radio bearers and signalling radio bearers using the new CKX and IKX from ... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.45 Physical Channel Reconfiguration for transition from CELL_DCH to URA_PCH: Failure (Radio link failure in old configuration) | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.45.1 Definition | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.45.2 Conformance requirement | If the criteria for radio link failure are met in the old configuration during the reconfiguration procedure as specified in TS 25.331 subclause 8.5.6, the UE should:
1> if the UE would have entered CELL_PCH or URA_PCH as a result of this reconfiguration procedure and the UE has already submitted a response message to ... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.45.3 Test purpose | To confirm that the UE aborts reconfiguration to URA_PCH and performs cell update when UE detects radio link failure before receiving the RLC acknowledgement of the reconfiguration complete message in the old configuration. |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.45.4 Method of test | Initial Condition
System Simulator: 1 cell – Cell 1
UE: PS-DCCH+DTCH_DCH (state 6-10) as specified in clause 7.4 of TS 34.108.
Specific Message Contents
System Information Block type 1 of Cell 1 to be transmitted before idle update preamble
Use the same message sub-type found in clause 6.1 of TS 34.108, with the follow... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.45.5 Test requirement | After step 1, UE shall send PHYSICAL CHANNEL RECONFIGURATION COMPLETE message to SS.
After step 3, UE shall send CELL UPDATE message to SS, with cell update cause set to “radio link failure”.
After step 5, UE shall send PHYSICAL CHANNEL RECONFIGURATION COMPLETE message to SS. |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.46 Physical channel reconfiguration for transition from CELL_DCH to CELL_DCH (Hard handover to another frequency with timing re-initialised. Serving HS-DSCH cell change): Failure (Physical channel failure and reversion to old channel) | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.46.1 Definition and applicability | All UEs which support FDD or TDD and HS-PDSCH. |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.46.2 Conformance requirement | If the received message caused the UE to be in CELL_DCH state and the UE according to subclause 8.5.4 failed to establish the dedicated physical channel(s) indicated in the received message the UE shall:
1> if the CM_PATTERN_ACTIVATION_ABORTED flag is not set to TRUE:
2> revert to the configuration prior to the recepti... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.46.3 Test purpose | To confirm that the UE reverts to the old configuration (including measurement configurations, ciphering procedures and compressed mode configurations if required), and transmits a PHYSICAL CHANNEL RECONFIGURATION FAILURE message on the DCCH using AM RLC if the UE fails to reconfigure the new physical channel according... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.46.4 Method of test | Initial conditions
System Simulator: 2 cells - Cell 1 on frequency f1, and cell2 on frequency f2. Cells 1 and 2 have different primary scrambling codes.
UE: PS_DCCH_DTCH_HS_DSCH (state 6-17) as specified in clause 7.4 of TS 34.108.
Related ICS/IXIT statement(s)
- UE supports FDD or TDD
- UE supports HS-PDSCH
Test Proce... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.46.5 Test requirements | After step 1, the UE shall revert to the old configuration and transmit a PHYSICAL CHANNEL RECONFIGURATION FAILURE message. |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.47 Physical channel reconfiguration for transition from CELL_DCH to CELL_DCH (Compressed mode initiation, with active HS-DSCH reception): Success | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.47.1 Definition | All UEs which support FDD, HS-PDSCH and compressed mode. |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.47.2 Conformance requirement | If the UE receives:
-a PHYSICAL CHANNEL RECONFIGURATION message;
it shall:
1> set the variable ORDERED_RECONFIGURATION to TRUE;
1> if the UE will enter the CELL_DCH state from any state other than CELL_DCH state at the conclusion of this procedure:
2> perform the physical layer synchronisation procedure A as specified... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.47.3 Test purpose | 1. To confirm that the UE configures compressed mode according to a PHYSICAL CHANNEL RECONFIGURATION message during active HS-DSCH reception.
2. To confirm that the UE activates compressed mode according to the previously stored configuration when receiving a MEASUREMENT CONTROL message during active HS-DSCH reception. |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.47.4 Method of test | Initial Condition
System Simulator: 2 cells–Cell 1 is active and cell 6 is inactive
UE: PS_DCCH_DCH (state 6-7) as specified in clause 7.4 of TS 34.108.
Related ICS/IXIT statement(s)
- UE supports FDD
- UE supports HS-PDSCH
- Compressed mode required yes/no
Test Procedure
Table 8.2.6.47
Parameter
Unit
Cell 1
Cell 6
T0... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.47.5 Test requirement | After step 2 the UE shall transmit a PHYSICAL CHANNEL RECONFIGURATION COMPLETE message on the uplink DCCH using AM RLC.
After step 5 the UE shall transmit a MEASUREMENT REPORT message containing the IE "measured results" reporting cell 6's CPICH RSCP and Ec/No values, also report the triggering of event '2b' included i... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.48 Physical Channel Reconfiguration for transition from CELL_DCH to CELL_DCH: Success (Timing re-initialized hard handover to another frequency, serving HS-DSCH cell change, compressed mode) | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.48.1 Definition and applicability | All UEs which support FDD, HS-PDSCH and compressed mode. |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.48.2 Conformance requirement | In case the procedure was triggered by reception of a PHYSICAL CHANNEL RECONFIGURATION message, the UE shall:
1> transmit a PHYSICAL CHANNEL RECONFIGURATION COMPLETE as response message on the uplink DCCH using AM RLC.
1> the procedure ends.
…
If IE "Timing indication" has the value "initialise", UE shall:
1> execute t... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.48.3 Test purpose | To confirm that the UE is able to perform a timing re-initialised hard handover to another frequency after compressed mode measurement on the target frequency in conjunction with a serving HS-DSCH cell change according to the received PHYSICAL CHANNEL RECONFIGURATION message. |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.48.4 Method of test | Initial Condition
System Simulator: 2 cells - Cell 1 on frequency f1, and cell 6 on frequency f2. Cells 1 and 6 have different primary scrambling codes.
UE: PS_DCCH_DTCH_HS_DSCH (state 6-17) as specified in clause 7.4 of TS 34.108.
Related ICS/IXIT statement(s)
- UE supports FDD
- UE supports HS-PDSCH
- Compressed mode... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.48.5 Test requirements | After step 1, the UE shall transmit a PHYSICAL CHANNEL RECONFIGURATION COMPLETE message.
After step 4, the UE shall transmit a MEASUREMENT REPORT message with cell 6 as the reported cell.
After step 6, the UE shall transmit a PHYSICAL CHANNEL RECONFIGURATION COMPLETE message in cell 6.
8.2.6.48a Physical Channel Reconf... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.49 Physical Channel Reconfiguration from CELL_DCH to URA_PCH: Success (stop of HS-DSCH reception) | |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.49.1 Definition and applicability | All UEs which support FDD or TDD and HS-PDSCH. |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.49.2 Conformance requirement | If the UE receives:
- a PHYSICAL CHANNEL RECONFIGURATION message; or
it shall:
1> if the UE will enter the CELL_DCH state from any state other than CELL_DCH state at the conclusion of this procedure:
2> perform the physical layer synchronisation procedure A as specified in TS 25.214;
1> act upon all received informatio... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.49.3 Test purpose | To confirm that the UE transmits a PHYSICAL CHANNEL RECONFIGURATION COMPLETE message and enter URA_PCH state after it received a PHYSICAL CHANNEL RECONFIGURATION message, which invokes the UE to transit from CELL_DCH with active HS-DSCH reception to URA_PCH. |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.49.4 Method of test | Initial Condition
System Simulator: 1 cell
UE: PS_DCCH_DTCH_HS_DSCH (state 6-17) as specified in clause 7.4 of TS 34.108.
Related ICS/IXIT statement(s)
- UE supports FDD or TDD
- UE supports HS-PDSCH
Test Procedure
The UE is in the CELL_DCH state and has a radio bearer mapped on HS-DSCH established with active HS-DSCH ... |
4251e2eb3ecde7c73983ce7a4175ddf3 | 34.123-1 | 8.2.6.49.5 Test requirement | After step 1 the UE shall transmit a PHYSICAL CHANNEL RECONFIGURATION COMPLETE message on the DCCH using AM RLC. |
Subsets and Splits
No community queries yet
The top public SQL queries from the community will appear here once available.